CBETA Project ALD’s Cost and Schedule Review February 6, 2017

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Subrecipient Monitoring. A formal binding legal agreement between your institution and another legal entity A portion of your sponsored project's.
1 BROOKHAVEN SCIENCE ASSOCIATES As-Built Drawings and Commissioning Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional.
Reimbursements, Reporting & Budget Modifications
PROCUREMENT POST REVIEW OF WORLD BANK FINANCED PROJECTS IN INDIA October 11, 2007.
Monitoring & Oversight Adult Education and Literacy (AEL) Programs Brenda B. Williams Project Manager Texas Workforce Commission Regulatory Integrity Division.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
School Finances for Finance Subcommittees School Councils.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
MyFloridaMarketPlace MyFloridaMarketPlace User Meeting July 20, 2004.
METROPOLITAN TRANSPORTATION COMMISSION Key Steps to Delivering Project 1.Lead agency submits final project scope, budget and schedule to MTC 2.MTC.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
NWPP Multiple-Award Technical Support Contract (eff. 08/2005) Unit 8 Unit 8 “Managing the Task Order”
Overview of Grant Agreements - Agreement Process - Roadmap to the Agreement Document - Agreement Requirements/ Compliance Issues - Timelines for Reporting.
Grants and Contracts Jim Butterfield and Kathy Blackwood October 5, 2004.
JEOPARDY FINANCIAL MANAGEMENT EDITION Documentation Procurement Mystery Cost Principles Administrative Requirements Q $100 Q $200 Q $300 Q $400 Q $500.
Framework Consultants Presentation Judith Chivers Estates and Capital Developments.
Understanding the Financial Management of Your Cooperative Agreement Quito, Ecuador October 2009.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
For Life™ [Insert Date Here] [Insert Instructor Name Here] Project Management Skills.
American Recovery and Reinvestment Act (ARRA) Reporting Requirements Duquesne University Office of Research.
Contract Compliance Training
Project Management PTM721S
Chapter 6 Cash Budgets.
Preparation of the Self-Study and Documentation
Camera PDR/CD1 Planning 19 September 2008
Page Headline Project Management Cost & Schedule Review Rob Michnoff.
ACCT 201 FINANCIAL REPORTING Chapter 3
Award Set-Up and Advances
Subaward - 2 CFR A formal legal agreement between your institution and another legal entity An award provided by a pass-through entity (PTE) to.
By Lillian Irene Stormo, HiB
Jackson State University
Page Headline Beam Commissioning Adam Bartnik.
Status of the MICE Construction Project
Administration of a FIDIC Contract - Project Control
2011 Prioritization Update to Market Subcommittees
NATA Foundation General Grants Program Process
Oversight Board Meeting October 3, 2017 Rob Michnoff
DIRECTOR OF FINANCE/hr
Subaward Life Cycle 10/24/17.
Project Genome Mapping
Springbrook Estates Sewer Improvement Area Informational Meeting
Jackson State University
Request for Proposal & Proposal
SCD Grants & Contracts Policy & Procedure 670.
SKADS Controller’s Meeting Timeline Annual Financial Report
FY19/FY20 Detroit Collective Impact Funding
Management Breakout: MREFC Budget Summary Victor L
Eagle Programme : 4 Box Summary
Kick-off meeting of the project UMBRELLA
WGARM Appraisal Decision Assistance Phase 1, Dec. 2002
Jackson State University
Jackson State University
[Team Name] Monthly Technical Report [Safe Genes Program]
Exit Capacity Substitution and Revision
Back-End Payor Sub-Group
Sheri Bozic, Director Department of Planning & Development
Action Kick-off Meeting
Values/Attributes assigned to 5-FUNDs used to Identify Billing and Revenue Recognition
Department Of Energy Review Linac Coherent Light Source Project
NATA Foundation General Grants Program Process
Second Avenue Subway Project Execution Strategy
(Project) SIGN OFF PROCESS MONTH DAY, YEAR
SNS-PPU upgrades the existing accelerator structure
Brieana Reed-Harmel, Broadband Project Manager
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
Office of Grants and Contracts Presenter: Stephanie Chandler-Thompson
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

CBETA Project ALD’s Cost and Schedule Review February 6, 2017 Invoice Processing and Reporting S. LaMontagne NPP Business Operations Manager

CBETA Project Objective and Schedule The fundamental objective of this NYSERDA project is to build, test and evaluate a critical subsystem of the large scale EIC facility, before competitive bids are due to DoE, so that BNL is in the strongest position to win the award. Our objective defines the timeline as DoE is expected to issue a competitive solicitation in April 2018 to determine an appropriate site and team to design, construct and operate an Electron-Ion Collider (EIC).

NYSERDA Contract with BNL Contract Attributes BNL Principal Investigator: Dejan Trbojevic BNL Project Director: Stephen Peggs BNL Project Manager: Rob Michnoff Effective Date of Contract: October 31, 2016 Contract Value: $25.0M Duration: 42 months, through April 30, 2020 Advance Payment: $2.0M received November 18, 2016

NYSERDA Contract with BNL Technical Timeline showing Major Milestones # Technical milestone Month Comment   NYSERDA funding start date Estimate: October 2016 1 Engineering design documentation complete 3 2 Prototype girder assembled 6 Magnet production approved 8 Spreader, combiner & hybrid 4 Beam through Main Linac Cryomodule 10 Go/no go 1 5 First production hybrid magnet tested 14 Fractional Arc Test: Beam through MLC & prototype girder 18 Go/no go 2 7 Girder production run complete 25 Final assembly and pre-beam commissioning complete 28 9 Single pass beam energy scan 32 Single pass beam with energy recovery 36 Key parameters achieved 11 Four pass beam with energy recovery (low current) 38 12 Project complete 42 Estimate: April 2020

NYSERDA Contract with BNL Financial Agreement / Cash Flow Initial advance of $2.0M to fund commencement Monthly invoices for incurred time/material costs Monthly payments to maintain forward financing 2 “go/no go” milestones serve to mitigate NYSERDA’s financial risk Month 10 – Acceleration of Beam through Main Linac Cryomodule Month 18 – Fractional Arc Test which commissions as much CBETA equipment as practically possible before making a commitment to complete construction A second advance of $2.0M timed to the 1st “go/no go” decision in month 10 (July 2017)

NYSERDA Contract with BNL Financial Agreement / Cash Flow Budget Profile, by quarter and year With an advance payment of $2.0M and an obligation profile as shown above, it is critical that invoice payments are received within 30 days Year Q1 ($M) Q2 ($M) Q3 ($M) Q4 ($M) Sub-total ($M) 1 1.7 1.9 2.1 2.3 8 2 8.9 3 1.3 5.6 4 1.2   2.5 Total 25

NYSERDA Contract with BNL Financial Agreement / Cash Flow Invoice payments received within 30 days enable BNL to maintain a positive cash flow Month Invoice Cost / Obligation Payment Balance Comments $2.0   Initial advance received 1 $0.4 $1.6 2 $0.5 $1.5 Payment for month 1 received 3 $0.7 $1.3 Payment for month 2 received Q1 $2.9 $1.7 4 Payment for month 3 received 5 $0.6 $1.4 Payment for month 4 received 6 $0.8 $1.2 Payment for month 5 received Q2 $1.9 $1.8

NYSERDA Contract with BNL Financial Agreement / Cash Flow Invoice payments received within 60 days may impact the ability to procure materials Month Invoice Cost / Obligation Payment Balance Comments $2.0   Initial advance received 1 $0.4 $0.0 $1.6 2 $0.5 $1.1 3 $0.7 $0.8 Payment for month 1 received Q1 $2.9 $2.4 4 Payment for month 2 received 5 $0.6 $0.9 Payment for month 3 received 6 Payment for month 4 received Q2 $1.9 $1.7

NYSERDA Contract with BNL Financial Agreement / Cash Flow Invoice payments received within 90 days will impact the ability to procure materials and maintain uninterrupted work progress Month Invoice Cost / Obligation Payment Balance Comments $2.0   Initial advance received 1 $0.4 $0.0 $1.6 2 $0.5 $1.1 3 $0.7 Q1 $2.9 4 $0.3 Payment for month 1 received 5 $0.6 $0.2 Payment for month 2 received 6 $0.8 $0.1 Payment for month 3 received Q2 $1.9

Monthly Invoice Process Accounts Payable sends invoice to C-AD financial staff Project Director drafts summary status in narrative form C-AD financial staff prepare documentation of invoice details Invoice along with narrative and detailed financial documentation returned to Accounts Payable Accounts Payable forwards invoice along with detailed financial documentation to NYSERDA Accounts Payable notifies C-AD financial staff upon receipt of payment Payment included in monthly DoE contract modification

Cornell University Sub-Contract Contract Attributes Effective Date: December 14, 2016 Period of Performance: Nov 2016 through Apr 2020 Incrementally funded contract Ceiling Amount: $12.75m Initial Commitment: $1.0M Quarterly funding increments planned Monthly invoices for incurred time/materials cost received in the first week of each month Breakdown of invoice cost by WBS element along with bulleted list of activities performed in the prior month to be provided within 5 business days after the receipt of the invoice Cornell invoices accrued by BNL upon receipt of WBS cost breakdown to ensure timely recording of cost for inclusion in BNL’s invoice to NYSERDA

BNL Invoice and Monthly Report Contract provides guidance regarding content of the monthly report Format developed by C-AD financial staff Narrative provided by Project Manager to include a description of activities at both BNL and Cornell Financial data downloaded from PeopleSoft and shown in both summary and detailed formats First invoice sent to NYSERDA on Jan 20, 2017 Invoice format accepted and first payment received on Feb 2, 2017

BNL Invoice and Monthly Report Narrative

BNL Invoice and Monthly Report Financial Details

Quarterly Reporting to NYSERDA Prepared in letter format and submitted to NYSERDA’s Project Manager by the 15th of the month Project Title Agreement Number Reporting Period Progress Identification of Issues Planned Solutions Ability to meet schedule, reasons for schedule slippage Schedule - % complete Analysis of actual cost incurred in relation to estimated cost Deliverables completed during the reporting period Detailed description of activities and planned procurements for the upcoming quarter

In Conclusion My Take Away Message Our objective defines the timeline; in order to ensure that BNL is in the strongest position to win the award for the EIC, the project must be completed on time. Failure to maintain adequate forward financing may necessitate suspension of ongoing efforts, resulting in schedule delays. It is, therefore, critical that invoices be provided and payments received on a timely basis.