CONTRACT RCSP / ICB / SB / 01 SUNKOSHI BRIDGE AND APPROACHES SEMINAR

Slides:



Advertisements
Similar presentations
Hussey Fraser Solicitors
Advertisements

PROJECT MANAGEMENT & BUSINESS PLANNING PROCESS
Subchapter M-Indian Self- Determination and Education Assistance Act Program Part 273-Education Contracts under Johnson-OMalley Act.
Develop an Information Strategy Plan
Railway Grade Separations Issues. Railway Grade Separations 1.Introduction Qualifications/experience to undertake bridge planning for railway grade separations:
Note: Lists provided by the Conference Board of Canada
Session 8 Implementing PPPs
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
1 Conference Call December 7 th h 30 Agenda 1.Concerns on wording and inclusion of glossary of terms; 2.Issues: 3.Scope of RFP equipment required;
1 Comprehensive Management Plan for East Hampton Airport  Safety, Noise and Operations Peter J. Kirsch December 1, 2011.
Government Services How to Respond to a Request for Proposal (RFP) 2006.
Time for a new standard - AS General Conditions of Contract
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
Senior Design – Acceptance Test Plan Review The goal is to: define the criteria for approving the application. Tightly coupled to the Requirements document.
Codex Guidelines for the Application of HACCP
Audit of Public Procurement
Ministry of Transport and Road Safety. Introduction Historical Approach to Contracting with Foreign Companies Current Policy and Requirements for Foreign.
Encouraging Diversity Growth & Equity 123: Demonstration of Good Faith Todd McGonigle EDGE Program Manager Phone (614) FAX (614)
2011 CDBG Recipients’ Workshop What’s New? Keeping current with the changing landscape.
James Aiello PricewaterhouseCoopers Africa Utility Week 06 International Good Practice in Procurement.
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Education Beyond the Classroom BA Hons Education Studies.
The new labor legislation - More flexibility for companies? Mihai Anghel.
Local Assessment of Code of Conduct Complaints. 2 Background  On 08 May 2008 – the local assessment of Code of Conduct complaints was implemented due.
South East Europe Transnational Cooperation Programme Bologna, 15° June 2009 Kick-off meeting of project SARMa SEE Joint Technical Secretariat.
Gulana Hajiyeva Environmental Specialist World Bank Moscow Safeguards Training, May 30 – June 1, 2012.
Integrated Risk Management Charles Yoe, PhD Institute for Water Resources 2009.
Effective Communication for Colleges, 10 th ed., by Brantley & Miller, 2005© Chapter 11 Chapter 11 – Slide 1 Reports, Proposals, and Instructions for the.
Copyright  2005 McGraw-Hill Australia Pty Ltd PPTs t/a Australian Human Resources Management by Jeremy Seward and Tim Dein Slides prepared by Michelle.
Varteg Hill – Coal Recovery and Land Reclamation Pre-Application enquiry by Glamorgan Power Ltd. Members Seminar 31/3/14.
Click on Next to continue Next Introductio n Inputs Tools and Techniques Outputs The process of managing procurement relationships, monitoring contract.
Contractor Alternate Design Serving the Public’s Best Interest.
Experience of Accessing EU Financial Support in Lithuania 4th PG Funding Meeting , Paris.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
Small Purchase of Professional Service Providers Administrative Rule R
Developing a Local Authority Policy Document Jim Gibbins Cheshire County Council
Improving Compliance with ISAs Presenters: Al Johnson & Pat Hayle.
Overview Interim Advice Note 85/06 Minor Improvements to Existing National Roads Development of Approach / Issues Identified NRA TA 85/11 Guidance on.
Construction Work Packaging
Introduction for the Implementation of Software Configuration Management I thought I knew it all !
Municipal Class Environmental Assessment
MONEY, FRAUD AND THE POLITICIAN
Implementation of the IPS MDTF
Administration of a FIDIC Contract - Project Control
12.3 Control Procurements The process of managing procurement relationships, monitoring contract performance and making changes or corrections as needed.
Particular Conditions of Contract & Appendix to Tender
Administration of a FIDIC Contract - Pre-Contract Phase -
Administration of a FIDIC Contract - Financial Management
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
The ARC Process for New Program Proposals
City of Norfolk Office of the Purchasing Agent
Review of the 1958 Agreement
Particular Conditions of Contract & Appendix to Tender
OHS Staff Introduction Training
بسم الله الرحمن الرحيم Tests on Completion Dr. Kamaleen Sha’ath
PROCUREMENT POLICIES AND GUIDELINES
Role and Responsibility for Quality Assurance Vishnu P. Shrestha
Equitable Services Sections 1117 and 8501 of the Elementary and Secondary Education Act (ESEA), as amended by the Every Student Succeeds Act (ESSA),
MODULE B - PROCESS SUBMODULES B1. Organizational Structure
Joint Office Presentation for Modification 0678
EU Tyre Industry comments on document ECE/TRANS/WP.29/GRB/2019/6
Experimental Internet Resource Allocations
(Project) SIGN OFF PROCESS MONTH DAY, YEAR
Provision of HR Services, UNOPS Nepal
Colorado “Protections For Consumer Data Privacy” Law
Brieana Reed-Harmel, Broadband Project Manager
Role and Responsibility for Quality Assurance Vishnu P. Shrestha
HELCOM Meeting May 2019 OSPAR’s monitoring and assessment in reducing discharges of radioactive substances to the North-East Atlantic Kinson Leonard (Vice.
Presentation transcript:

CONTRACT RCSP / ICB / SB / 01 SUNKOSHI BRIDGE AND APPROACHES SEMINAR ROAD CONNECTIVITY SECTOR 1 PROJECT – ADB GRANT No. 0051-NEP(SF) GOVERNMENT OF NEPAL, MINISTRY OF PHYSICAL PLANNING AND WORKS DEPARTMENT OF ROADS CONTRACT RCSP / ICB / SB / 01 SUNKOSHI BRIDGE AND APPROACHES SEMINAR “CONSENSUS ON CONTRACT COMPLETION” MMM GROUP Canada formerly N.D. Lea Inc. in association with CEMAT Consultants (Pvt.) Ltd. Nepal, Soil Test (Pvt.) Ltd. Nepal, Total Management Services (TMS) Nepal

STAGE 1 INFORMATION STAGE

THIS IS A WORKING SEMINAR FORMAT THIS IS A WORKING SEMINAR NO SPEECHES MINIMUM FORMALITIES

THOSE PRESENT ON BEHALF OF THE ARE REQUESTED TO INTRODUCE THEMSELVES INTRODUCTIONS THOSE PRESENT ON BEHALF OF THE EMPLOYER CONTRACTOR ENGINEER ARE REQUESTED TO INTRODUCE THEMSELVES

PURPOSE OF THE SEMINAR PRIMARY PURPOSE TO REACH CONSENSUS ON THE BEST OPTIONS FOR CONTRACT COMPLETION SECONDARY PURPOSE TO AGREE A TIMEBOUND ACTION PLAN TO ACHIEVE THE CONSENSUS

STRUCTURE OF THE SEMINAR THE SEMINAR HAS SIX STAGES STAGE 1 - INFORMATION STAGE STAGE 2 - DESIGN PRESENTATION STAGE 3 - OPTION DEVELOPMENT STAGE 4 - EVALUATION STAGE 5 - CONSENSUS STAGE 6 - ACTION PLANNING

CURRENT STATUS OF THE CONTRACT THE CONTRACT IS APPROXIMATELY 54% COMPLETE THE CONTRACT IS OUT OF TIME THE CONTRACT (AS CURRENTLY DESIGNED) CANNOT NOW BE COMPLETED WITHIN THE LOAN PERIOD TIMEFRAME THIS ADVERSELY AFFECTS THE PERFORMANCE EVALUATION OF THE OVERALL RCSP PROJECT THE SEMINAR IS DESIGNED TO SEEK A SOLUTION IT IS NOT PROPOSED THAT THE REASONS FOR THE CURRENT UNFORTUNATE SITUATION BE DISCUSSED AT THIS SEMINAR

NON-NEGOTIABLE CONDITIONS IN VALUE ENGINEERING EVALUATION BRIDGE DESIGN MUST BE IN ACCORDANCE WITH APPROPRIATE CODES ALL CONSTRUCTION ELEMENTS MUST BE VERIFIABLE UNDER QA PROCEDURES

BIHARI LAL BALLA – RESIDENT ENGINEER STAGE 2 DESIGN PRESENTATION Presented by BIHARI LAL BALLA – RESIDENT ENGINEER

STAGE 3 OPTION DEVELOPMENT DISCUSSION OF DESIGN MODIFICATION OPTIONS TEA BREAK AGREEMENT OF ACCEPTABLE MODIFICATIONS

CONSIDERATION OF GAINS / OFFSETS STAGE 4 EVALUATION OPTIONS & CONSIDERATION OF GAINS / OFFSETS BY EACH CONTRACT PARTY

ESSENTIALLY THERE ARE 2 OPTIONS CONTINUE WITH THE CONTRACT FOR A FURTHER LOW WATER SEASON AND BUILD THE BRIDGE AS ORIGINALLY DESIGNED

OPTIONS 2 OPTION 2 VARY THE CONTRACT TO INCORPORATE AGREED DESIGN MODIFICATIONS AND COMPLETE THE BRIDGE BY END 2012

ASSESSMENT OPTION 1 FAILS TO COMPLETE THE BRIDGE WITHIN THE STIPULATED LOAN PERIOD OPTION 2 IS THE PREFERRED OPTION OF THE 2 PARTIES TO THE CONTRACT

ANALYSIS OPTION 2 REQUIRES ANALYSIS OF THE GAINS / OFFSETS OF EACH CONTRACT PARTY THIS IS A VALUE ENGINEERING ANALYSIS In accordance with GCC Clause 13.2 Value Engineering Sub-Clause (c)

For information: GCC CLAUSE 13.2 VALUE ENGINEERING Sub-Clause (c) (ii) STATES The reduction (if any) in the value to the Employer of the varied works, taking account of any reductions in quality, anticipated life or operational efficiencies

EARLIEST POSSIBLE COMPLETION LESS ROBUST FACTORS OF SAFETY EMPLOYER – GAINS EARLIEST POSSIBLE COMPLETION EMPLOYER – OFFSETS LESS ROBUST FACTORS OF SAFETY

REDUCTION OF DIFFICULT ACTIVITIES (SINKING) CONTRACTOR – GAINS REDUCTION OF DIFFICULT ACTIVITIES (SINKING) CONTRACTOR – OFFSETS SUGGESTED OFFSETS ARE

IN ACCORDANCE WITH GCC CLAUSE 13.2 VALUE ENGINEERING Sub-Clause (c) SUGGESTED OFFSETS IN ACCORDANCE WITH GCC CLAUSE 13.2 VALUE ENGINEERING Sub-Clause (c) CONTRACTOR WAIVES ALL COST CLAIMS RELATED TO TIME PROLONGATION AND ALLEGED UNFORSEEABLE PHYSICAL CONDITIONS

EVALUATION EMPLOYER ACCEPTS CONTRACTOR WAIVING ALL COST CLAIMS RELATED TO TIME PROLONGATION AND ALLEGED UNFORSEEABLE PHYSICAL CONDITIONS AS BEING REASONABLE OFFSET FOR LESS ROBUST SAFETY FACTORS (BUT WITHIN THE CODE) THE EMPLOYER AGREES NOT TO IMPOSE PENALTIES FOR LATE COMPLETION PROVIDED BRIDGE IS COMPLETED BY END DECEMBER 2012

Consensus to be defined by VISHNU P. SHRESTHA – DEPUTY TEAM LEADER STAGE 5 CONSENSUS Consensus to be defined by VISHNU P. SHRESTHA – DEPUTY TEAM LEADER

CONSENSUS TO COVER ACCEPTABLE DESIGN MODIFICATIONS OFFSETS AGREED BY CONTRACTOR

EXECUTION OF THE CONSENSUS STAGE 6 ACTION PLANNING EXECUTION OF THE CONSENSUS WILL REQUIRE 3 STEPS

STEP 1 CONTRACTOR Present agreed Design Modification under GCC Clause 13.2 Value Engineering Undertake responsibility for design in accordance with GCC Clause 13.2 (a) Provide revised Construction Program Step 1 to be complete by ?

STEP 2 ENGINEER Prepare Variation Order under GCC Clause 13.3 Variation Procedure Covering Design Modification, “Offsets” agreed by Contractor and revised Program Obtain Contractor’s signed agreement Step 2 to be complete by ?

STEP 3 EMPLOYER Approval of Variation Order Step 3 to be complete by ?

SUMMARY & CLOSE THANK YOU – ALL PARTICIPANTS HOPEFULLY WE NOW HAVE A ROUTE TO SUCCESSFUL COMPLETION LUNCH IS THE NEXT ACTIVITY