SPP/FIELDS Quarterly UMN 27 September 2016

Slides:



Advertisements
Similar presentations
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
Advertisements

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R GLAST Pre-Ship Review (PSR) LAT Payload I&T Review CONTRACT NO.
GLAST LAT ProjectF2F, June 15, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety Assurance Manager.
GoetzFIELDS iCDR - TDS Solar Probe Plus - FIELDS Instrument CDR Time Domain Sampler TDS Keith Goetz University of Minnesota 1.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
THEMIS INSTRUMENT PER 1 UCB, May, 2005 EMC / Mag Instrument Test Plan & Results Michael Ludlam University of California - Berkeley.
GoetzFIELDS iPDR – I&T SPP/FIELDS Integration and Test Preliminary Design Review Keith Goetz University of Minnesota 1.
Linac Marx Modulator Update Trevor Butler 5/20/2015.
THEMIS Instrument CDR(1) UCB, April 19 & 20, 2004 Mission Assurance Critical Design Review Ron Jackson University of California - Berkeley.
Solar Probe Plus FIELDS Team Meeting Management Items 08/05/2014.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Jerry Kim, SSL Mechanical.
GERB 4 Instrument Status GIST 25 23rd October 2006 Presenter: N Morris.
PFP Instrument Status All PFP Instruments Except SWEA have been delivered, integrated, and tested; supporting environmental tests Issues: –EUV alignment.
ISUAL HIGH VOLTAGE SUPPLIES P.BERG. CDR 9 JULY 20012NCKU UCB Tohoku High Voltage Supplies P. Berg HIGH VOLTAGE P0WER SYSTEM OVERVIEW HIGH VOLTAGE IS REQUIRED.
THEMIS Instrument FM2/FM3 PEREnvironments- 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review Environments Jeremy McCauley University.
GoetzPre-PDR Peer Review October 2013 FIELDS TDS FPGA Peer Review Keith Goetz University of Minnesota 1.
Solar Probe Plus Fluxgate Magnetometer QSR – Oct SPF MAG Quarterly Report – Oct 2014 The MAG EM1 (EQM) (board and frame at right) was successfully.
TRIO-CINEMA 1 UCB, 8/10/2010 CINEMA Project Update Thomas Immel UCB/SSL Space Sciences Laboratory University of California, Berkeley.
FIELDS iCDR – RFS Analog Dennis Seitz 1 Solar Probe Plus FIELDS Instrument CDR RFS Analog Dennis N. Seitz UC Berkeley SSL
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 W. N. Johnson Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem.
June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota
Programme for “Target 3” – test of alternative bearing materials (from Jason Tarrant) –Drawing updates by 11 th November –Bearings: Material approval –
FM2/FM3 PSR FM4/FM5 PERSCM - 1UCB, November 10, 2005 THEMIS FM2/FM3 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) THEMIS FM4/FM5 INSTRUMENT SUITE PRE- ENVIRONMENTAL.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
GoetzPre-PDR Peer Review October 2013 FIELDS Time Domain Sampler Peer Review Keith Goetz University of Minnesota 1.
FM1 Instrument Suite PSRSCM - 1UCB, September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) SEARCH COIL MAGNETOMETER (SCM) Michael Ludlam.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 9 EFW Overview and Status Keith Goetz University of Minnesota.
SPP FIELDS DFB Quarterly November 21, 2014 Solar Probe Plus FIELDS Instrument Quarterly Digital Fields Board (DFB) 1.
MAVEN-SWEA Assembly, Integration & Test (AIT) Contents AIT: CESR Team Facilities Main subcontractors Applicable documents AIT documentation Cleanliness.
Workshop on Appraisal of Disassembled Magnets: Lessons learned March 17 th, 2005 Boundary Conditions-Technical Specification Jos Vlogaert.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.
Goetz22 June 2016 SPP/FIELDS Quarterly UMN 22 June 2016 Keith Goetz 1.
FIELDS MEP Thermal Vacuum Cycling iPER
Solar Probe Plus – FIELDS SCM FM2 Instrument Pre-Ship Review
Resource Loaded Schedule and Budget Profile
Davin Larson, Roberto Livi, Phyllis Whittlesey,
Bill Raynor Naval Research Lab
Solar Probe Plus – FIELDS V1234 PA/Antenna Instrument Pre-Ship Review
Solar Probe Plus FIELDS MEP iPSR SOC Marc Pulupa April 10, 2017
Solar Probe Plus – FIELDS Main Electronics Package
Gayle K. Martin November 14, 2016
SPF MAG Quarterly Report – Feb 2015
Status of the MICE Construction Project
Brief Status SPS Prototype PSB Prototype Installed in LS1
Solar Probe Plus FIELDS
Keith Goetz University of Minnesota
Solar Probe Plus FIELDS
Solar Probe Plus – FIELDS Main Electronics Package
Dave McComas on behalf of the ISʘIS Team
Agenda. Solar Probe Plus FIELDS Main Electronics Package iPER Agenda Feb 2, 2017.
Solar Probe Plus – FIELDS Main Electronics Package
SPP FIELDS V1234 Thermal PSR
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
Solar Probe Plus – FIELDS Verification Instrument mini-PER (V5)
Solar Probe Plus – FIELDS V1234 PA/Antenna
THEMIS Mission Assurance
FIELDS SCM Thermal iPER
FIELDS Keith Goetz Solar Probe Plus A NASA Mission to Touch the Sun
EM pre-integration review
COSMOS Status David Sprayberry, Sean Points & Jay Elias
0.0 Instrument Suite Name Presenter’s name
Enterprise Content Management Owners Representative Contract Approval
How to keep your Enterprise GIS Project on Track
TSF Upgrade Project Overview Resources Plans and Timetable
GLAST Large Area Telescope
Software Engineering Lecture 17.
Report on ATF2 Third Project Meeting ATF2 Magnet Movers ATF2 Q-BPM Electronics Is SLAC ILC Instrumentation Group a good name?
Integration and Test Organization Chart
Introduction and Overview
Presentation transcript:

SPP/FIELDS Quarterly UMN 27 September 2016 Keith Goetz

UMN Activity UMN contract with SwRI is producing good results - at a price Nearly complete Flight hardware assembly is well along All UMN flight hardware is complete and delivered to UCB LNPS1 delivered to I&T at UCB LNPS2 delivered to I&T at UCB TDS delivered to I&T at UCB Integration was successful Final end-to-end calibrations were recently completed with flight preamplifiers Final conformal and such remain

UMN Activity FIELDS slices at UCB (July)

FIELDS2 Activity On-going development of FPGA/VHDL firmware A second flight-like proto-RTAX was burned and tested Corrected serious timing problems in earlier VHDL design EM testing shows the problems was corrected Proto-RTAX was installed in FM and is full functional On-going development of flight software On-going development of ground software

TDS Activity TDS FM is now fully assembled and tested Issues Resolved Screened ADCs were delivered and installed At risk – lot jeopardy – as qualification continues to mid-November Instrument calibration is now complete Stability will be revisited throughout I&T Issues Resolved Circuit Breaker design error (typo) – introduced in FM Corrected, implemented and tested Circuit Breaker mixed voltage – introduced in STEREO V5 Gain error – overlooked in EM testing Non-flight (no PIND testing) AD829 op-amps installed by accident Corrected (replaced) and tested

TDS Status TDS FM is assembled and in I&T at UCB Proto-RTAX has been installed Corrected AEB clock problem revealed in I&T Full end-to-end phase and gain calibrations have been done TDS EM1 used at UCB with SWEAP FM to verify wave particle correlation (WPC) with real particles! TDS EM1 is in normal use in EM stack at UCB Timing compatibility with DFB and MAG instruments demonstrated TDS EM2 is constant use at UMN Continuing development of flight firmware, software and ground software FPGA/VHDL has seen continuous development Working data down-sampling

TDS WPC

LNPS Activity LNPS1/2 FMs are complete and ready for final assembly Instrumented TV conducted on both FM units Verified heat rejection and hot spots Delivered to UCB I&T LNPS1/2 FMs have a tin-whisker issue Magnetic parts have been built with tin-plated cans Mitigations are understood Large scale size Tag plate pins fully solder coated Conformal will be applied effectively to can interiors, exteriors and boards No bare metal - Impedes growth and penetration Voltages/currents will burn whiskers away PMPCB approved – with waiver LNPS1/2 EMs are complete Functional at UMN (1) and UCB (2)

Parts Activity Parts and materials lists are complete As-built parts lists complete De-ratings have been revisited AD7621 ADC is not yet fully approved AD7621 ADC beam testing accomplished at Texas A&M Test write-up complete Commercial PEM qualification is on-going – to mid-November Vendor has not inspired confidence PMPCB suggested long (7d) duration hot test is running at ambient Scope captures of circuit-breaker action will be captured on FM at UMN Waiver for not beam testing implemented circuit breaker is in the works Magnetics tin-whisker issue is resolved PMPCB has approved Mitigations in place Waiver is in the works

Coming Up Flight hardware will return to UMN Final soldering touch-up Final cleaning (ROSE) MIP Staking and conformal Final assembly Flight hardware will be re-tested at UMN Flight RTAX to be burned, assembled, tested and installed in FM TDS Flight PROM to be burned, tested and installed in FM TDS Flight hardware will be re-delivered to UCB – November FIELDS1 and FIELD2 re-I&T at UCB PER FIELDS environmental test program PSR

Financial Activity UMN spending continues within contract plans (thru August) Target CV is $6.7M Spending continues somewhat behind the proposed