Week 13: R. Assmann, J. Wenninger

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ion Commissioning: Thursday & Friday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Machine availability reaching well over 80%
Summary of Week 11: 14 – 21 March
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
MD#4 Progress MD Coordinators: Giulia Papotti, Frank Zimmermann
LHC commissioning Week 38
Lost at 12:05 to power converter (RTQX2.R1) problem
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Wed :40 Lost S78 - QPS controller.
Mike Lamont, Jorg Wenninger
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Friday 23rd March 08:00 Access
(on behalf of the LHC team)
Sunday/Monday & :30 Stable beams. Fill #1851.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Saturday Nov Stop proton operation. Switch back to ions
Tue/Wed 12/ :00 Probe beam back again
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
MD Planning Fri – Sat (1. – 2.7.)
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Summary for LPC (March 7th, Ralph Assmann)
Monday :15 fill 3523 dumped by BPMs IP6
Plan for 1 m b* J. Uythoven & J. Wenninger
LHC Morning Meeting - G. Arduini
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Tuesday – Morning and Evening
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Tuesday
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Week 13: R. Assmann, J. Wenninger Last 24h RP alignment for TOTEM and ALFA All H for TOTEM, all but one for ALFA aligned Dumped by octupole trip during test with octupoles RP control exhibited some issues to address in TS1 Completion of dump protection studies Results in week report BI studies Week 13: R. Assmann, J. Wenninger 4/2/12 LHC 8:30 meeting

Last 24h 4/2/12 LHC 8:30 meeting

The Last Week Full cycle for nominal bunch: RF blowup issues in ramp Orbit optimization and reference orbits for nominal bunches all through cycle Improvement of lifetime with tight collimation settings Final optics corrections for beta* = 0.6m First collisions Instabilities, tune tracking and octupoles Setup of collimation, injection & dump protection All completed. Collimation automatic setup worked (faster). Qualification for stable beams. Mostly completed. Few missing for final machine functions. Other tests: Dry runs for high beta* optics 4/2/12 LHC 8:30 meeting

Ramp: RF Blow Up Problems It is clear that there is a problem with the new blow up, and it is not understood. Since the present configuration is acceptable, it was decided not to touch the system for the weekend. RF will decide on Monday morning whether we revert to the old blow-up in the ramp in the meantime RF wants a ramp with observations in SR4 before taking decision The new blowup will be re-tested in MD. 4/2/12 LHC 8:30 meeting

RF Stability Issue Manifests as… correct bunch length average (around 1.1 ns), thanks to the feedback adjusting the excitation amplitude from a measurement of bunch length mean, but different lengths for the two bunches. John, Themis, Andy and Philippe We observed quadrupole oscillations (bunch lenght modulation) of growing amplitude, resulting in debunching and finally beam dump caused by excess loss on momentum collimator. Plot Giulia P. LHC 8:30 meeting 4/2/12

Three explanations were proposed 4/2/12 LHC 8:30 meeting Three explanations were proposed The opening of phase loop during blow-up An increase in machine longitudinal impedance compared to 2011 A less stable bunch profile (more Gaussian) The Phase loop influence was tested first. In Fill 2427 we had 4 equispaced bunches per ring, 9E10p, Phase loop ON (B1), OFF (B2). Both OK Then we ramped 2 bunches per ring, higher intensity (1.1-1.2E11), spacing ½ turn B1 and ¼ turn B2. Phase loop ON for both rings. No instability but we observed diverging bunch length towards end of ramp (mean remains OK). Fill 2428

Collimator Gaps at 4 TeV LHC 8:30 meeting 4/2/12

Lifetime with Tight Coll. + Normal Emittance flat top injection ramp Both beam 1 and beam 2 lifetimes are fine at flat top. Fully acceptable reduction during ramp. Lifetime reduction during ramp is unavoidable and not surprising at all: Collimators go down in normalized “real” sigma (8.2s  6.2s) and tails are cut. Note: Tails do not contribute to luminosity! LHC 8:30 meeting 4/2/12

Orbit in Squeeze Investigation of ‘spiky’ orbit excursion in the 2011 squeeze improved handling of the separation and Xing bumps. Smoothing using parabolic segments around matched optics. Simulations predicted smaller and smoother orbit leakage from the IRs (bumps) into the arcs. Observed orbit stability in the squeeze is already much better than in 2011. Feed-forward was applied to reduce workload of orbit FB. So far no significant losses observed due to orbit control when operating with tight collimator settings. 4/2/12 LHC 8:30 meeting

Global Orbit Leakage during Squeeze Leakage much improved wrt 2011 (peaks of 150 mm). Can improve further with correction around 1m (~600 s). b* 1 m B1 100 mm B2 100 mm 4/2/12 LHC 8:30 meeting

Local Orbit Leakage to IR7 during Squeeze Orbit around IR7 (including ~10 BPMs either side) stable at the level of 50 mm rms or better. B1 100 mm B2 4/2/12 LHC 8:30 meeting

Global Orbit Leakage during Collision BP Some leakage from complex separation and Xing bumps ramping (up / down). More feed-forward needed (B1 H  LHCb Xing collapse). If required could run with orbit FB – settings prepared. B1 100 mm LHCb H Xing to 0 B2 100 mm LHCb H Xing to 0 4/2/12 LHC 8:30 meeting

Optics B2 – New Local Correction 4/2/12 LHC 8:30 meeting

Optics B2 – New Correction… 4/2/12 LHC 8:30 meeting

Fills Saturday until Sunday: Both in Collisions Minimal losses, no lifetime issue, no instability, … Sudden lifetime drops several minutes after the end of the squeeze 4/2/12 LHC 8:30 meeting

Lifetime Drop after End of Squeeze 4/2/12 LHC 8:30 meeting

Instabilities and Octupoles We twice had after the squeeze significant losses for B2, after the tune peak on B2H jump to a 2nd peak. The resulting instability caused losses and only stabilized with reduced intensity and minor coupling trims. It was observed that the 2nd bunch of B1 (bucket 17851) was blown up by in the transverse by at least a factor 3. We stabilized losses by adding a few units of chroma. We also optimised the coupling to try to improve the spectra. Realized that octupoles were still at some intermediate settings: Octopoles updated to 400A at flat top. 4/2/12 LHC 8:30 meeting

First Collisions 2012 Going into collisions… very smooth. Lumi scans: Offline incorporation from first attempt worked very well. Some collisions in ALICE without any corrections. Lumi scans: CMS and ATLAS first, LHCb last, using standard X/Y optimization. Correcting orbits, fixing coll. functions (for next time)… Tried crossing/orthogonal plane luminosity optimization. Knobs OK: beams move in same direction. Fix sign (B1 wrt B2). Before collisions the RF colleagues corrected the BPTX offsets by 300 ps. 4/2/12 LHC 8:30 meeting

First Fill with Collisions 4/2/12 LHC 8:30 meeting

Lumi Scan Settings Cleaning. Made a clone of the collision BP. Verified the settings of clone and original were really identical (start and end). Zeroed the LUMI-SCAN knob settings in the original BP. Verified the orbit corrector settings of clone and original were still identical (start and end). Rolled back the LUMI-SCAN settings to the state after the first fill on friday (30.03.2012). From the attached figure one can see that the present trims are almost exactly the double of the initial values on Friday. Re-incorporated the LUMI-SCAN knob settings into the collision BP (see figure). 4/2/12 LHC 8:30 meeting

Collimator Set-up 4 TeV Flat Top Collimator setup was completed in 7h45 hours and a single fill (first time). First a coarse setup was performed, using the automatic setup algorithm, in parallel for all collimators per plane in B1 and B2. Then the semi-automatic algorithm was used to fine-tune the parallel alignment and drive in the collimators again towards the beam. Once all collimators were close to the beam, they were aligned sequentially, first with the 12Hz data and then cross-checked with 1Hz data. Betatron loss maps look very good (done with ADT). Off-momentum loss map (+500 Hz, ‘natural’ failure direction) done. 4/2/12 LHC 8:30 meeting

B1H Loss Map 4/2/12 LHC 8:30 meeting

Collimation Setup Before & in Collision TCT/TCL setup at end of squeeze and in collision all finished (22 coll.). TCT-IR1/5 = 9 sigma TCT-IR2/8 = 12 sigma TCL = 10 sigma Loss maps –ADT affect both beams – switch back to resonance crossing (less coupling). Good hierarchy in IR7. 4/2/12 LHC 8:30 meeting

B2 H Loss Maps - Collisions 4/2/12 LHC 8:30 meeting

Off-Momentum 4 TeV 4/2/12 LHC 8:30 meeting

Injection Protection Setup of TCDIs in TI 8 and TI2: Checked TCLIA.4R2 measured center checked with injection of nominal and losses were OK qualified for transmission and protection Checked TCLIA.4R2 checked only lower jaw angle with 0 and +/-1.5 mrad found symmetric results - --> no angle to be applied TCLIB to be set at 8.3 instead of 6.8 sigma Setup of TDIs: angular alignment, found angles and center for both TDIs same angles (within meas. accuracy) as last year Checks Abort gap protection checked: limit bunches 1-31181. MKI failure simulation, beam grazing on TDI. Settings defined for TCLI (6.8s,8.3s), TDI (6.8s), TCDI (4.5s). 4/2/12 LHC 8:30 meeting

LHC 8:30 meeting 4/2/12

Dump Protection I TCDQ angular alignment. Not minimum found for B2 on angle. Decide to remain with ‘0’ angle. B1 TCDQ angle -60 urad, compatible with -100 urad found previously. Apply -100 urad angle. MKD test 14/15 kicker simulation – OK. No increase in losses for ‘-1’ kicker. Dump with extreme bunches (1- 34291) OK. Trigger dump of each beam by switching off the dump septa (RMSD) PCs. FMCMs trigger as expected. Circulating beam aperture in P6 verified reference measurements in case of asynch dump and MPS test Two cases: absorbers in and out 4/2/12 LHC 8:30 meeting

Dump Protection II TCDQ transmission BPMS interlocks - MPS test reference measurement for TCDQ damage in case of asynchronous dump BPMS interlocks - MPS test MSD FMCM interlock test at 450 GeV Dump with RF frequency shift and orbit bump at TCDQ 4/2/12 LHC 8:30 meeting

Follow-Up Collimation at 450 GeV Analysis of high losses in IR6 for B1H: Showed that TCSG.4R6.B1 set up too tight Repeat of IR6 TCSG collimation setup at injection Results:                  center          beam size ratio TCSG.4R6.B1      +0.150         99% TCSG.4L6.B2      -0.318          94% previous alignment from 2012.03.21                  center          beam size ratio TCSG.4R6.B1      +0.110          92% TCSG.4L6.B2      -0.185           94% 4/2/12 LHC 8:30 meeting

B1H Loss Map – IR6  20% Leakage 4/2/12 LHC 8:30 meeting

TCSG.4R6.B1 out  Less than1% Leakage 4/2/12 LHC 8:30 meeting

Without Beam: High Beta Un-squeeze In windows without beam: Successful dry runs of the un-squeezes (no trips): b* = 11 m  90 m 1846 s b* = 90 m  500 m 604 s b* = 500 m  1km 298 s Total un-squeeze time = 2748 s  46 minutes. Next step : test with probe beam. 4/2/12 LHC 8:30 meeting

This Week Access for experiments before stable beams RF work to fix problem with blow-up Completion loss maps for final machine functions  OK from rMPP for stable beams First stable beams Check ADT excitation with colliding beams Excitation of one beam couples (through beam-beam transfer function?) to the other beam Different parameters for excitation Use as MD tool Set up for 50 ns 4/2/12 LHC 8:30 meeting

NEW longitudinal blow up P. Baudrenghien, M. Jaussi, T. Mastoridis, J. Molendijk

4/2/12 LHC 8:30 meeting Why change the blow-up? In 2011 we have implemented longitudinal blow-up through the main phase loop. This loop updates the RF frequency at every turn and it therefore acts on all bunches at the same time. No batch per batch action is possible. That system is used in the SPS as well With ions, it was observed in 2011 that the blow-up transforms a Gaussian bunch profile (at injection) into a non-Gaussian shape (at flat top). (For protons the shape is non-Gaussian at start ramp, due to manipulations in the SPS). A test with ions at flat top energy showed that the new blow-up preserves the Gaussian shape. It would thus hopefully reduce heating effect with protons For batch-per-batch action at injection, the new implementation is needed as we need to modulate the excitation amplitude at the revolution frequency

4/2/12 LHC 8:30 meeting Latest observations The new long. blow up was commissioned on March 20th, achieving a promising doubling of the longitudinal emittance in 5 minutes at injection. It was then tested in the ramp with single pilot. Worked fine 450 GeV Ramp

4/2/12 LHC 8:30 meeting The first fill with single bunch nominal went fine as well, although the bunch length was a bit shaky in the last part of the ramp, but it calmed down on flat top Fill 2402 When we first ramped two nominal bunches, we observed instability at current/longitudinal emittance for which beam was stable last year. Fill 2218 showed marginal stability B1. Fill 2422, Beam 1, 1E11 p/bunch was clearly unstable Bunch length shows quadrupole oscillations developing in the second part of the ramp and surviving on flat top

Three explanations were proposed 4/2/12 LHC 8:30 meeting Three explanations were proposed The opening of phase loop during blow-up An increase in machine longitudinal impedance compared to 2011 A less stable bunch profile (more Gaussian) The Phase loop influence was tested first. In Fill 2427 we had 4 equispaced bunches per ring, 9E10p, Phase loop ON (B1), OFF (B2). Both OK Then we ramped 2 bunches per ring, higher intensity (1.1-1.2E11), spacing ½ turn B1 and ¼ turn B2. Phase loop ON for both rings. No instability but we observed diverging bunch length towards end of ramp (mean remains OK). Fill 2428

4/2/12 LHC 8:30 meeting Fill 2429 ramped 2 bunches per ring, nominal. OK this time. No instability, no diverging bunch lengths. But blow up does not equalize bunch lengths as much as it did in 2011. We now observe a larger spread at 4 TeV than at 450 GeV.

4/2/12 LHC 8:30 meeting Summary and plans Without the beam phase loop, there is clear evidence of instabilities in the last part of the ramp With the phase loop On, the instabilities disappear, but we still get a divergence in bunch length growth: We obtain a larger spread in bunch length at 4 TeV than at 450 GeV. Last year the blow up was equalizing bunch length We will use the RF MD time to study the new blow-up at 450 GeV: resulting bunch profile (that influences stability threshold), origin of the length variations between bunches We will decide on Monday morning whether we revert to the old blow-up in the ramp in the meantime We want a ramp with observations in SR4 before taking decision

Additional material. More fills during the week-end… 4/2/12 LHC 8:30 meeting Additional material. More fills during the week-end…

4/2/12 LHC 8:30 meeting Fill 2439 ramped 2 bunches per ring, nominal. OK for B1, significant spread in bunch length B2

4/2/12 LHC 8:30 meeting Fill 2440 ramped 2 bunches per ring, nominal. Large spread (400 ps) in bunch length for the two bunches B1 (1/2 turn apart). Less in B2