LHC Performance Workshop LS1 Session Cryogenic system: strategy to achieve nominal performance and reliable operation J. Bremer, K. Brodzinski, J. Casas,

Slides:



Advertisements
Similar presentations
Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
Advertisements

Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Going towards LHC Run2 CRYOGENICS 5 th Evian Workshop 2-4 June 2014 SESSION 4 - Systems 2 - Status and commissioning plans (HW perspective) Krzysztof Brodzinski.
L. Tavian, TE/CRG, Page 2 12 th September 2013 Accelerator Consolidation Workshop L. Tavian, TE-CRG.
ESS Cryogenic System Design
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The cryogenic systems of the ATLAS and CMS detectors Johan Bremer on behalf of TE/CRG 06/06/2013AFF.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
AT-ACR B. VULLIERMECSOC Meeting 29 September Cryogenics for LHC Test Benches Safety Aspects Overview of the Test Station Overview of the Operation.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
LHC CRYOGENICS – new experience of run with increased beam energy and intensity Krzysztof Brodzinski CERN, Geneva, Switzerland With contribution from:
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
TE-CRG Activities A. Perin, on behalf on the Cryogenics Group.
CONSOLIDATION day in view of HL-LHC Cryogenic aspects
Z. W. Zhou, Q. Y. Zhang*, X. F. Lu, L. B. Hu and P. Zhu
M Chorowski, H Correia Rodrigues, D Delikaris, P Duda, C Haberstroh,
Innovative He cycle Francois Millet.
CRG-TM: LS1 projects review
Update of cryogenic activities
SPS cryogenic proximity equipment and SM18 validation
LHC Performance Workshop (Chamonix 2016)
CRYOGENICS – strategy, unavailability root causes and limitations
Long Shutdown for the LHC: Vacuum Beam Pipes
Update on HW commissioning
Preparation of the activities for the LHC Long Shutdown 2
Consequences of warming-up a sector above 80 K
Keeping LHC cold during LS periods Preliminary proposal
Hollow e- lens, Cryogenic aspects
Accelerator and Experiment Interface Session: LS2, LS3
Activities of the ME section during LS2 ( )
Overview & baseline of LS2 and roadmap for CRG
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
TEST PLANS for HL LHC IT STRING
Collimator Control (SEUs & R2E Outlook)
Mathew C. Wright January 26, 2009
ILC Experimental Hall Cryogenics An Overview
SNS Cryoplant Commissioning Past Experiences
Guidelines defined early Dec 2012
Summary post TCC#54_02Aug’18
Review of hardware commissioning
Cryogenic management of the LHC Run 2 dynamic heat loads
Laurent Delprat CERN, Geneva, Switzerland
HL-LHC New MS optimisation WP9, Preliminary cost estimates
Presentation transcript:

LHC Performance Workshop LS1 Session Cryogenic system: strategy to achieve nominal performance and reliable operation J. Bremer, K. Brodzinski, J. Casas, S. Claudet, D. Delikaris, N. Delruelle, G. Ferlin, C. Fluder, A. Perin, G. Perinic, M. Pezzetti, O. Pirotte, L. Tavian & U Wagner Chamonix 2012, 08 February 2012

LS1 cryogenics strategy Priority ++ + Nominal performance recovery Safety (personnel, hardware, He inventory) Cryogenic equipment Reliability/availability improvement Cryogenic equipment (hardware) Spare strategy (hot vs stored) Redundancy Upgrades (sectorization, …)

Nominal performance recovery: Safety first Resp. Status Personnel IT (& RF?) SV collectors DFB deflectors Machine platforms Helium ring line (HRL) sectorization Instrumentation air panel for cryo consignation Tunnel ventilation conditions (P, T, v) TE-CRG EN-MEF + ? Y Machine Safety valve consolidation (presently OK up to 5 TeV) SV final design installation (machine & QRL side) Beam vacuum protection (rupture disks) TE-MSC/CRG TE-VSC Detectors (N/A) He inventory Quench line consolidation (in case of massive quenches) Responsibilities for machine platforms to be consolidated. About on tracks! Y: planned & approved

Nominal performance recovery: Hardware Resp. Status Machine DFB consolidation (Splice, DFBX CL, flexible hoses, NC...) Inner triplet braids Y lines Leaks (in S3-4, P8…) Beam screen circuit (Q6R5) Instrumentation NC TE-CRG TE-MSC TE-VSC/MSC/CRG TE-CRG/MSC/VSC Y Distribution Leak in S4-5 Stand-alone magnet and DFB cooling limitation TE-CRG/MSC Detectors (N/A) Cryoplants Leaks in LN2 precoolers Special attention on newly On tracks! approved consolidation! (DFBA 13 kA splices) Y: planned & approved

LS1 cryogenics strategy Priority ++ + Nominal performance recovery Safety (personnel, hardware, He inventory) Cryogenic equipment Reliability/availability improvement Cryogenic equipment (hardware) Spare strategy (hot vs stored) Redundancy Upgrades (sectorization, …)

Reliability / availability data: Cryo stops 2010-2011 comparison (No SEU in 2010) : - Important reduction of short and medium stops - Stable number of long stops ~ - 40 % ~ - 70 % ~ 0 % 20 11 21 5 Induced beam dumps: - ~ 50 % of short stops - By cryo (including SEU): 32 (~ one per week) - By other (affecting cryo): 25 Cryo-SEU : Consolidation during present Xmas stop Cryo down (w/o SEU): - Less than 1/3 for short and long stops ~30 % ~33 % ~60 % S. Claudet et al

Reliability / availability data: 2011 medium and long cryo-failures Point Date Equipment Origin Action / Decision Treated for 2012 > LS1 P2 26 Apr Cold compressor magnetic bearings Old card type on pre-series Cards upgraded after failure Yes P4 18 Aug Cold compressor Lost of instrumentation with diagnostic issue TT replaced, new diagnostic and degraded restart procedures 16 Nov Cold compressor frequency drive CC4 power card 1st error Systematic HW exchange every 10 y No 20 Nov CC4 power card 2nd error Systematic preventive renewal 28 Nov Superconducting link Common vacuum of the DSLC with a DFBLC heater vacuum Separation of vacua per type P8 13 May PLC (4.5 K plant) PLC 1st crash Considered as “normal” MTBF (1/y) 25 May PLC 2nd crash Crashed PLC CPU systematic replacement by now 18 Jun Screw compressor Early bearing damage due to balancing piston depressurization Consolidation done during Xmas’11 stop 13 Aug Hard landing of CC4 rotor New procedure to shorter the recovery time 1 Nov Oil valve positioner Positioner failure No medium/long stops at P6  Confidence in room for improvement! S. Claudet

Reliability / availability data: 2011 cryo near-misses Point Equipment Origin Action / Decision Treated for 2012 > LS1 P2 Screw compressor Compressor failure Shared operation P18/P2 No, but Yes, if Valve bellows Big leak on a valve bellows (Ex-LEP) Cannibalization of components on the P8 stopped plant Consolidation budget for LS1 Yes Cold compressor electronics Electronic card failure Cannibalization of components on the P6 stopped plant Additional spare ordered P4 Shared operation with adjacent plant Cold compressor electronics P8 No, but: 2011 mitigation measures still possible Yes, if: new spare strategy for compressors to be approved and implemented S. Claudet

LS1 cryogenics strategy Priority ++ + Nominal performance recovery Safety (personnel, hardware, He inventory) Cryogenic equipment Reliability/availability improvement Cryogenic equipment (hardware) Spare strategy (hot vs stored) Redundancy Upgrades (sectorization, …)

Reliability/availability improvement : Hardware Mode Resp. Status Maintenance and major overhauling S, T TE-CRG Y Machine SEU consolidation (see A.L. Perrot talk) Stand-alone magnet level capillaries (3 Q6) DFBAO & DFBMJ instabilities S T TE-MSC Distribution Line B mixing chamber in QUI Quench valve control for fast CD improvement N Cryoplants New CV241 QURC IHI linde Ex-LEP Cryo-valve consolidation Cryoplant configuration for cooldown (bypass) Dryers for ATLAS (MR) and CMS All improvements for steady-state modes will be treated during LS1 ! S: Improvement for Steady-state (with beam) T: Improvement for Transients (e.g. recovery time, Cool-down…) Y: planned & approved N: Not planned

LS1 cryogenics strategy Priority ++ + Nominal performance recovery Safety (personnel, hardware, He inventory) Cryogenic equipment Reliability/availability improvement Cryogenic equipment (hardware) Spare strategy (hot vs stored) Redundancy Upgrades (sectorization, …)

Reliability/availability improvement : Spares, redundancy & upgrades Resp. Status Spare strategy (hot vs stored) Warm compressors (LHC and its detectors) Electrical motors (LHC and its detectors) Special electronic equipment (Safety PLC, VFD…) Turbines, Cold compressors TE-CRG S N Done Redundancy Better sharing of HP-MP-BP flows 2 cryoplants with one 1.8 K refrigeration unit 24 V electrical supply redundancy (LHC and its detectors) Upgrades Sectorization for HWC flexibility improvement LN2 for parallel cool-down Robustness to power glitches above typical standard Interlock chain redundancy ATLAS cryo-distribution (decoupling toroid / solenoid) Y Warm-compressor spare strategy need urgent approval (procurement delays)! & sectorization improvement Y: planned & approved N: Not planned S: Under Study

A typical warm compressor station of LHC

4.5 K cryoplant compressors: Present situation Consequences of a compressor failure on nominal (7 TeV) operation? 9 types of compressors: 2 Aerzen types (536M & 536H) - 7 Stal types (S73_lp, S73_hp, S75, S87, S89, S93_lp & S93_hp)

Installed vs required volumetric flows High-stages Boosters ~1500 m3/h or ~265 g/s @ 4 bar missing at P18 ~2000 m3/h or ~350 g/s @ 4 bar missing at P2 ~1050 m3/h or ~50 g/s @ 1.05 bar missing at P18 K. Brodzinski

4.5 K cryoplants: Nominal capacity consolidation To guarantee nominal operation with minor MTTRestore (~1 day) Hot spares at P18 and at P2 Stored spares for the other plants: Use of LN2 precooling to save HP flow (LN2 consumption compensated by electrical power saving but logistics to be reliable) Exchange of compressor during the next TS (or 3 additional days to restore) Review of the plant LP, MP, HP by-passes But: How many stored spares are required? Stal spares are not available any more on the market! (repair and major overhauling still possible) Space for the hot spare at P2 is not available !

How many spares are required for the compressors? Case 1: Failure rate λ = 0 (7 types concerned) Within the observation time no failure has occurred. The observation time might be too short? A failure can occur tomorrow! A spare should be available (stored/hot) in those cases where the impact of a compressor failure is major or catastrophic for the scientific objectives of LHC. Case 2: Failure rate λ > 0 (2 types concerned) What stock availability can be guaranteed with 1, 2 or 3 spares taking into account the repair time of the compressors? Aerzen VMY536H Stal S73 Failure rate λ estimation from available data [h-1] 6 x 10-6 Population on LHC [-] 12 6 MTTRepair from recent experience [h] 7200 2500 Stock availability = probability to fulfil spare part demand  Spares Aerzen VMY536H Stal S73 1 0.58 0.91 2 0.9 0.974 3 0.986 0.998 G. Perinic , A. Perin

Proposed strategy for 4.5 K cryoplants Use as spares some existing Stal compressors at Point 2 and Point 4 Install new compressor skids with larger capacity (To free slot space) Complete the missing spares 2 1 1 1 1 1 1 1 1 Need for stock availability > 90 % For stock availability > 97 %, 1 additional skid and 1 additional spare are required)

Warm compressors of 1.8 K refrigeration units (CCS) Sector Normal Back-up S12 CCSb P18 CCSa P2 S23 / S34 CCSa P4 CCSb P4 S45 S56 CCSb P6 CCSa P6 S67 S78 CCSa P8 CCSb P8 S81 No redundancy for S23, i.e. for a MTTR < ~1 day CCSa at P2 needs a hot spare Stored spares for the other points Static heat inleaks  Sector measurements (5 over 8) Resistive heating  Splice resistance measurements DR nominal beam-induced heating

Proposed solution for detectors 2011 configuration: no spare available, some extra capacity in ATLAS booster Xmas’11 configuration: one hot spare installed for ATLAS May’12 configuration: 2 new spares for CMS (already ordered) LS1 upgrade: Booster upgrade for ATLAS (already ordered) and 2 hot-spare skids for CMS LHC Stal spares available for ATLAS as well!

Summary of compressor spare/redundancy LHC 4.5 K cryoplants: depending on the stock availability (>90 or >97 %) 8 to 9 new compressor skids to be procured and installed (4 to 4.5 MCHF) 3 to 4 additional spares to be procured (0.9 to 1.2 MCHF) LHC 1.8 K units 1 new Kaeser compressor skid to be procured and installed (~0.5 MCHF) 1 additional Mycom spare to be procured: (~0.5 MCHF) ATLAS and CMS cryoplants 2 new compressor skids to be procured and installed (0.6 MCHF) Space for spare storage: 15 to 17 compressors (+ 8 electrical motors): ~100 m2 Resource needs: ~7 to 8 MCHF (including ~1.5 MCHF non-competitive & ~0.6 MCHF on Team budget) Manpower from TE-CRG, EN-EL and EN-ICE

LS1 cryogenics strategy Priority ++ + Nominal performance recovery Safety (personnel, hardware, He inventory) Cryogenic equipment Reliability/availability improvement Cryogenic equipment (hardware) Spare strategy (hot vs stored) Redundancy Upgrades (sectorization, …)

Sectorization in between sectors: Present situation Work 2 : Opening of E, F lines C, C’, BS lines D line, SAM CM (e.g. Q6 level capillary) Work 1 : Opening of M lines, CC CM RF cavity CM V, W line (e.g. Splice/diode repair) Work 2 in sector 12 23 34 45 56 67 78 81 Cryo-operation in Work 1 in sector 12 23 34 45 56 67 78 81 Cryo-operation in Work 3 in sector 12 23 34 45 56 67 78 81 Cryo-operation in Work 3 : Opening of B, X, Y lines (e.g line Y repair or magnet removal)

Sectorization improvement: New valve integration Possible in S23, S34, S45, S56, S67, S78 & S81 (7 sectors): ~150 kCHF per sector ~1 MCHF for 7 sectors What about S12? G. Ferlin

Sectorization: P2 configuration QRL return module integrated in the interconnection box ! Cryo Operation Today, no solution for work 2 and Work 3 in S12 in parallel with cryo operation in S23 !

Sectorization in between sectors: Summary Work 1 : Opening of M lines, CC CM RF cavity CM V, W lines Work 2 : Opening of E, F lines C, C’, BS lines D line, SAM CM Work 3 : Opening of B, X, Y lines Work 1  Ultimate sectorization already existing Work 2  Present sectorization does not allow Work 2 in S12 in parallel with cryo-operation in S23. Today no straight forward improvement envisaged. Work 3  the sectorization could be improved at the same level than Work 2 by upgrading the interconnection boxes  budget: ~ 1 MCHF Present Upgraded Work 3 in sector 12 23 34 45 56 67 78 81 Cryo-operation in Work 3 in sector 12 23 34 45 56 67 78 81 Cryo-operation in + 1 MCHF

Conclusion Consolidation for nominal performance recovery of cryogenics is about on tracks Improvement of the cryogenic availability: Some measures already taken  2012 objective: overall cryo-availability improvement from 90 % to 95 % Direct cryo-downs (including SEU) represent 50 % of the total stops  improvement of user and utility stabilities is also important Some long cryo-stops avoided in 2011 thanks to cannibalization and operation sharing of non-used cryoplants  no more possible for nominal operation after LS1  A strategy of warm compressor spares is proposed: additional budget estimated to ~7-8 MCHF and manpower need must be consolidated. Improvement of sectorization in-between sectors: Already optimized for Work 1 (e.g. splice/diode repair) Optimized on 7 sectors for Work 2 (e.g. intervention on SAM CM, on BS ) Could be improved on 7 sectors for Work 3 (e.g. Magnet removal)  ~ 1 MCHF for interconnection box upgrade