HMS Status Steven Lassiter Jan 20, 2017.

Slides:



Advertisements
Similar presentations
April 6th 2009Olympus Meeting at DESY, F.Brinker1 Detector power supply Detector cooling Polarity switches Kicker pulser Preparation of the experimental.
Advertisements

19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
G2P Target installation and Beyond. Schedule Pivot before.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
RHIC CRYOGENICS SYSTEM Time meeting /28/20141TIME MEETING RUN 14 –CRYOGENIC.
"AIR COOLER" Heat Exchanger
SS and AFC Control Systems Brian Martlew 21 st Sept 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
Zachary Wolf Undulator Oct 12, LCLS Undulator Tuning Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko,
SHMS Detector Commissioning and Installation Howard Fenker Hall-C Users Meeting Jan-2015.
Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31,
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
Hall C’s HMS PLC Controls by Steven Lassiter. What Constituents a PLC System PLC (processors) Programming. I/O modules. Field Device Signals (sometimes.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
05/30/08J. Dunne -- SANE Collaboration Meeting 1 Beamline Status Upstream beamline –Chicane –SEM –Rasters –Girder Downstream beamline –Helium bag –Extension.
Experiment beam line installation (9/4/2014) SystemThus FarTo Do Vacuum~ Torr, IP’s on, Vac interlock checkNone Fast valveValve + CCG installed,
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Electron Spectrometer Work Package Simon Jolly 19 th May 2014.
Some Thoughts on Magnetic Measurements for MICE Michael A. Green Lawrence Berkeley Laboratory Berkeley CA 94720, USA.
Forum March 2003H.Taureg1 Magnetic Fields in ALICE Mapping and Monitoring.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Yousef I. Makdisi DIS03 St. Petersburg April 24,2003 Polarized Jet target status The overall view The Dissociator stage The Atomic Beam stage The RF transitions.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
NML/RFCA002 Status ILC Cryomodule meeting 3 July 2012 E. Harms.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
Work in the Tevatron A0 D0 B0 C0 E0 F0 Separators A49 Separator B48 TEL 2 installation A0 Xtal Collimator 1.5 m collimator A48 Shimming 6 magnets/day At.
ELENA installation progress F. Butin / ELENA collaboration.
Current Status of QBPM Electronics and Magnet Movers D. McCormick, J Nelson, G White SLAC S Boogert Royal Holloway Y. Honda, Y.Inoue KEK.
LCLS-II Prototype Cryomodule Darryl Orris 21 January 2015 Final Design Review: Instrumentation.
S A Griffiths CM42 June 2015 Electrical & Control.
Report Technical Director Storage-Ring-Installation Completed
Report Technical Director Storage-Ring-Installation Completed
High energy beam transport.
E4 hall technical specifications
ELENA installation and commissioning status
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Gas System Commissioning
PLC-based control systems at SOLEIL - ICALEPCS 2017
CLEX* Status and Plans CTF3 complex CLEX
The LHC - Status Is COLD Is almost fully commissioned
ATF2 Magnet Power Supplies
Hall A Target Status 9/27/16 Dave Meekins.
352MHz Klystron Control for the 3MeV Linac test stand
XFEL Vacuum System Commissioning
SHMS Q2Q3Dipole Acceptance Test Plans Operations and Lessons Learned
DOE/SC Status Review of 12 GeV SHMS HB Magnet: Update since Oct 2015
SHMS Cryogenics and Q2(Q3Dipole) Cool Down
OPERATING STATUS OF BES SUPERCONDUCTING MAGNET
Cryogenics – The Basics
Testing Plan and Status
Hall C SHMS & Configuration Status
A. Freyberg Aug 2016 ECT’16 =>
Safety, reliability and maintainability
Status Vacuum Control-Command for AdV
Ola Ingemansson Electrical & Instrumentation Engineer
Hall C SHMS & Configuration Status
Operation of Target Safety System (TSS)
LCLS Control System Personnel Linac & BC2 Controls progress
IR Beam Transport Status
Polarized 3He target installation
Presentation transcript:

HMS Status Steven Lassiter Jan 20, 2017

HMS Dipole 3000A Dipole was successfully excited to 3,000A several times this past summer. The power supply units and control racks were unaffected by the dipole’s stray fields. Stray fields did affect the quadrupole dump racks. This will require relocation or magnetic shielding of the dump racks.

HMS Dipole @ 3000A

HMS Dipole NMR NMR probe 5 will not lock in above 1.8T. Cannot find a sweet spot to locate probe. Iron saturation leads to non-uniform field outside of vacuum chamber, where the probes are housed. Next generation of NMR probes and controllers have 100x better stability in non-uniform fields. Field regulation module, that talks directly to the power supply, are not available for the next generation NMR yet. Requires software correction signal to the PSU. Demo unit is expected to arrive Jan 23.

HMS Dipole He leak All CVI seals have been replaced on Dipole U-tubes (x4) Quad’s CVIs will be replaced opportunistically (x12)

Dipole Current Status Epoxy replenishment of the vapor cooled current lead seal is underway while the dipole is warm ~90K. Dipole’s OVC is being pumped on. Cool down of the magnet will occur early next week followed by testing of the new version of the NMR unit.

HMS Quadrupole Current Lead Mass Flow controllers New current lead mass flow controllers have been mounted and pressure tested. Final plumbing to the current leads, cable connections and check out still ongoing.

Spectrometer Rotation SHMS rotation replaces the SOS rotation in the PLC, HMI and hardware. Cabling from the SHMS to the Control rack is near completion. Final termination within the control rack is left. Final hookup to the SHMS interlocks is being worked on. Check out of rotation to occur after beamline installation and safety devices mounted.

HMS Maintenance and repairs have been ongoing with help from spectrometer support group: Items such as aged JT actuators, signal connections corrosion and motor control relay replacement. The full HMS checkout, including rotation, is planned for Feb 2017. Signed check out list will then be turned over to Hall Coordinator for turning over the keys to users.

HMS Summary Magnets have been excited to full currents. New NMR unit will be tested soon for high precision field control at full current. New current lead mass flow controllers for Quadrupole magnets. Full checkout planned for Feb