LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.

Slides:



Advertisements
Similar presentations
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Advertisements

Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
Carbon for SPS, state or the art and scrubbing runs, P.Chiggiato, P.Costa Pinto, P.Cruikshank, J.Ferreira Somoza, H.Neupert, A.Sapountzis, M.Taborelli,
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
TS, Length of YETS EYETS LIU & CONS Project
Scrubbing Review, 8/9/2015 Paul Cruikshank1. Contents SPS Layout aC factory options Assumptions & Scenarios Transport issues Radiation issues Coating.
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LIU-SPS, 29 April 2015 Paul Cruikshank1. Variants today: Starting point: Assume same boundary conditions as 15/4/2015 presentation Analysis is for SPS.
LIU-SPS, 15 April 2015 Paul Cruikshank1. In the beginning…. First slide that Brennan gave me – everything decided ! LIU-SPS, 15 April 2015 Paul Cruikshank2.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
TE-CRG Activities D. Delikaris, TE-CRG.
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.
ECR (SPS Flange Impedance Reduction) Follow up for IWG C. Vollinger 16/08/2016.
Electrial Safety LS2 days November 2016 AP
Report Technical Director Storage-Ring-Installation Completed
Magnet activities in SPS during EYETS
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
YETS & LS2 Works EN-EL / Power distribution
Linac4-PSB 160 MeV connection readiness review
Framework Schedule from EYETS 2016 to LS2
Update on the Critical Path of the PS Booster Schedule for the EYETS
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
BE-ICS Activities during the LS2 Period (15 min)
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
LIU Wire Scanner Milestones June 2017
Injector De-cabling Project
Cryostat procurement, status and plan, QA/QC
Follow-up of new design of vacuum flange shielding
LIU – EVM status and next steps
AD consolidation activities in LS2
SPS - EYETS 2016/17 Vacuum systems planning
Planning and Installation
EC Activities Status for the LIU
LIU–PLI report LIU SPS meeting.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Layout Drawings and Mechanical Assembly Drawings
Status of the BI Work Package in the LIU-PSB frame
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
EN-STI activities in LHC during EYETS
Diffuser status October 2017
HL Consolidation Day Analysis of needs from BE-ICS
SPS activities during LS2 TE-EPC (Power Converter Group)
Acknowledgments: LIU-PT members and deputies, H. Bartosik
YETS & LS2 Works EN-EL / Power distribution
TE-MSC activities in SPS during YETS
EYETS septa status Septa activities TE/ABT Thierry Masson
EYETS septa status Septa activities TE/ABT Thierry Masson
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Magnet electrical and hydraulic (dis)connections for coating
Impedance working group update
PLAN Results K. Foraz on behalf of LS2 team
SPS Planning meeting for LS2 #19 Vacuum sectors & Magnet campaign situation Antonio Grande EN-ACE 06-Mar-2019.
Project management Ray Veness.
East Hall under construction
SPS Planning meeting for LS2 #25 Vacuum sectors status
Status of the BI Work Package in the LIU-PSB frame
SPS Planning meeting for LS2 #26 Vacuum sectors status
Presentation transcript:

LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016 Paul Cruikshank

EYETS aC & IR activities Vacuum sector valves DS LSS ARC BA4 BA5 existing aC SSS QF works MBB works Drift tube works 9 SSS QF to transport 2 SSS QD to transport 2 QD to transport 10 drifts to transport All magnet removal ( & return) via BA3 LIU & TE-VSC, 19/9/2016 Paul Cruikshank

Opening of the machine (weeks) Extended Year-End Technical Stop 2016-2017 References: 20 weeks beam to beam stop for CMS Ions run Proton-Lead References [1], [3] and [4] Machines Opening of the machine (weeks) not including the xmas break of 2 weeks PSB 11.5 PS 13.5 SPS 12.5 (BA1,BA2) – 13.5 LHC 16 Low intensity protons 55 days

Does TE/VSC have all needed information from LIU Documentation Launch Safety Agreement - done List of hazards - done Safety File Part 1: Descriptive - done Safety File Part 2: Demonstrative – to do Functional spec for impedance reduction – to be closed Functional spec for aC coating – under approval ECR for impedance reduction – to be closed BE/RF need to measure EYETS shielding solution ECR for aC coating – under approval Risk assessment and mitigation for aC – under approval LIU & TE-VSC, 19/9/2016 Paul Cruikshank

Are TE/VSC preparatory activities within expected timeline? aC coating for EYETS Validation of 13 m MBB string in 181 Validation of QF profile coating in 181 Validation of ozone cleaning of contaminated St.St. in 181 Setting up of long test station in 867 (MBB, QF, SSS girder) – done, trails to start. Job open for manufacturing of replacement drift chambers – done, manufacturing ongoing Procurement of components for benches (tunnel & 867) – ongoing (90%) Setup of benches in 867 vacuum lab to do – draft layout done, trial with LEP trailer to do Flange Impedance Reduction for EYETS. Shielding design finalised for EYETS implementation Based on design applied during 1999 impedance reduction – ECR to be closed Cannot wait for RF measurements/simulations on flexible fingers Cannot wait for soft clamp tests (by-pass of insulated flanges) Detailed design and manufacturing will be tight – request for quotation ongoing Planning for EYETS All tunnel activities in same arc – BA4 to BA5 Takes account of learning objectives - time margin for surprises – 55 day window ok VSC activities are staff dominated Methodologies will be confirmed – eg SSS girder/individual magnet handling - ongoing Drift chambers manufactured and coated in advance of EYETS - ok Detailed planning to be elaborated with EN-ACE-OSS – draft planning for discussion LIU & TE-VSC, 19/9/2016 Paul Cruikshank

Has all the LIU required work been declared in PLAN Has all the LIU required work been declared in PLAN? (Are all dependencies on other groups defined…?) Dependencies on other groups identified during costing exercises for aC & flange impedance reduction in 2015. Weekly deployment meeting with representatives of involved group TE-MSC, EN-ACE-SU, EN-HE, TE-VSC, BE-RF, EN-ACE-OSS, HSE-RP, Data entered in PLAN (EYETS, LS2) – some overlapping identified (same data by other Groups) - to be checked and cleaned LIU & TE-VSC, 19/9/2016 Paul Cruikshank

Are the LIU EVM timeline & budget correct? Annual work units based on APT data (agreed budget) Need to establish EVM data to reflect deliverables – not yet done  99273: Committed in 2016 = 447k + 48k to come (396k budget). 65332: Committed in 2016 = 7k + 80k to come (163k budget). LIU & TE-VSC, 19/9/2016 Paul Cruikshank

Are the VSC-CONS items linked to the operation of LIU approved, in time and within specification? All TE-VSC SPS Cons requests up to 2020 have been approved Ion pumps, ion pump power supplies, spare chambers, flanges, bellows, valves, pumping group renovation, …ok, ongoing On-going clarification of SPS controls consolidation (PLC replacements) request. Postponed during 2015 CONS arbitration exercise but now understood to be within ‘CONS envelope’ attached to HL-LHC during C&S – VSC controls request doc in preparation LIU & TE-VSC, 19/9/2016 Paul Cruikshank

EYETS draft planning – to be discussed with contributing teams Paul Cruikshank LIU & TE-VSC, 19/9/2016

Thanks for your attention LIU & TE-VSC, 19/9/2016 Paul Cruikshank