PANDA Magnet Iron Yoke Strength Analysis

Slides:



Advertisements
Similar presentations
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
Advertisements

Guenther Rosner FAIR Design Study, PANDA 3, GSI, 19/1/06 1 PANDA3: Magnet design and integration of detectors Tasks & participants Progress Milestones.
October 21, 2003LST Mechanical Design Review - SLACN. Yu BaBar IFR Upgrades An FEA Study of the Effects of Adding Brass Plates in the IFR.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
Twin Solenoid Twin Solenoid - conceptual design for FCC-hh detector magnet - Matthias GT Mentink Alexey Dudarev Helder Pais Da Silva Leonardo Erik Gerritse.
ZQNA Electrostatic Quadrupoles for ELENA Transfer Lines 1.Conceptual design 2.Performance 3.Engineering details 4.Interfaces 5.Production planning D. Barna,
MUON_EDR-06 (Alignment) Enrique Calvo Alamillo February 28-March 1, 2002 Link Mechanics: Status.
1 Design of Solenoid and iron yoke for GLD KEK Hiroshi Yamaoka Ken-ichi Tanaka July 13, ‘05.
Multiple Coil Lift Calculation. Purposes of the Study  To investigate the stress distribution in the MCWF and the lifting device.  To make sure mounting.
Joint Institute for Nuclear Research Further optimization of the solenoid design A.Efremov, E.Koshurnikov, Yu.Lobanov, A.Makarov, A.Vodopianov GSI, Darmstadt,
TOPICS COVERED Building Configuration Response of Concrete Buildings
1m 3 SDHCAL Mechanic Structure M.C Fouz 8/10/2010 The 1m 3 prototype Mechanical Structure is financed by: Spanish HEP National Program by the project FPA
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
Support and magnet coil KEK Hiroshi Yamaoka Nov. 10, ‘04.
1 MC Assembly over the VV FPA Station 3 FDR Review July 17, 2007 T. Brown.
Hall D Design Status GlueX Collaboration Meeting JLab, Ravi Anumagalla.
An Analysis of Shell Structure for Dead Load H.M. Fan PPPL September 16, 2005.
ECAL End Cap Dee Assembly, Transport, InstallationCERN January 2006AR / RJSG – 1 Alexandre Riabov (IHEP, Protvino) Justin Greenhalgh (RAL) Finite Element.
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown.
1. Introduction 2. Magnetic field design Optimization of yoke configuration in several conf. Boundary conditions -
FEM Analysis of the Stage3 Support Frame H.M. Fan March 14, 2007.
A View of NCSX Structural System and Load Path for the Base Support Structure.
Project Office Activities R. Vuillermet 08/09/2015R. Vuillermet PH-ADO-PO1.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
Status of report on chapter 6: Warm cryostat mechanical calculation PH-DT Engineering Office, CERN Page 1 CERN, May 20th 2015.
Visit to Börkey GmbH February 05, 2013 (Resume of discussions) Presented by Evgeny KoshurnikovHagen-Vorhalle (250 km Nord-West from Darmstadt) (250 km.
May 31, 2010Bill Wisniewski1 Mechanical Integration Issues.
CONCEPTUAL DESIGN OF D2 MECHANICAL STRUCTURE (DOUBLE COLLARING OPTION) S. Farinon, P. Fabbricatore (INFN-Sezione di Genova) Sept. 24 th 2015.
Status of the PANDA Magnet Yoke Presented by E. Koshurnikov GSI, February 7, 2013.
Joint Institute for Nuclear Research Deformations and stresses in the flux return yoke A.Efremov, Yu.Lobanov, A.Makarov Darmstadt,
Joint Institute for Nuclear Research Status of the magnet for the PANDA Target Spectrometer Report from Dubna A.Efremov, E.Koshurnikov, Yu.Lobanov, A.Makarov,
Thermal screen of the cryostat Presented by Evgeny Koshurnikov, GSI, Darmstadt September 8, 2015 Joint Institute for Nuclear Research (Dubna)
12 July 2007IRENG07 WG-A M. Breidenbach1 SiD Concept SiD is relatively modest in scale compared to the LHC detectors, and comparable to SLD: Tracker Radius.
Page 1 GSI, Hydraulic Actuators for PANDA Target Spectrometer Jost Lühning, GSI Darmstadt Functional Specifications for moving the TS: Two synchronous.
Status of the Yoke Interfaces Presented by Evgeny Koshurnikov February 2013.
PANDA Yoke unsolved Interface problems Presented by E. Koshurnikov (Dubna) December 9, 2011, GSI.
Cavity Supporting Scheme Paulo Azevedo, CERN – TE/MSC SPL Conceptual Review, 04/11/2010.
Status of the PANDA Magnet Yoke Presented by E. Koshurnikov GSI, June 26, 2013.
Status of work (cryostat, control Dewar, cooling system). Plans for 2015 Evgeny Koshurnikov, Jülich December 9, 2014 Joint Institute for Nuclear Research.
Miscellaneous MEC Topics Mainz, CM September 2016, MEC Session J
Roller/rail - System for PANDA
Status of work (cryostat, control Dewar, cooling system)
Update on PANDA solenoid design
Ferrara MECHANICAL SUPPORT for forward tracking detectors Federico Evangelisti INFN - Ferrara GSI – 2-6 march 2009.
Status of the PANDA Magnet mechanics (yoke & cryostat)
Some Updates on Mechanics CM-MEC Session Dec J. Lühning, GSI
Miscellaneous Topics MEC Session, CM March 2017 at GSI J. Lühning, GSI
STRAW TRACKER SYSTEM CAD STATUS :
Platform for moving and positioning Target Spectrometer on the floor
Platform Design for the Target Spectrometer using Heavy-Weight Rollers J. Lühning, GSI Darmstadt, Three design goals for Platform: Low construction.
Solenoid Yoke Door-Barrel Connection
TQS Structure Design and Modeling
Present status of the flux return yoke design
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
PANDA Yoke of the Magnet
AQQABA SECONDRY SCHOOL Structural Design.
BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016
PANDA Collaboration Meeting , BINP Sergey Pivovarov.
Platform for Target Spectrometer using linear montion drive Rexroth
Status of the PANDA Magnet
FRESCA2 Update on the dipole design and new calculations
By Arsalan Jamialahmadi
Step IV - Engineering Jason Tarrant – Integration Engineering
Chapter-2 Parts of Steel Bridges.
Status of the PANDA Solenoid Magnet Production in BINP
Integration and IR Hall
Assembly, survey, alignment of the CBM Dipole Magnet
as a prototype for Super c-tau factory
Presentation transcript:

PANDA Magnet Iron Yoke Strength Analysis Status report Presented by E. Koshurnikov December 11, 2012

Initial Data All main dimensions of the yoke FE model are in accordance with CAD model https://edms.cern.ch FAIR Project, PANDA, Magnets, Solenoid yoke ID = 1064509 Cryostat FE model (dimensions, loads and points of their application) is in accordance : http://panda-wiki.gsi.de/pub/Magnet/Internal/keep_away_25_02_2011.zip http://panda-wiki.gsi.de/pub/Magnet/Internal/pandaTS_spectrometer_25_02_2011.zip http://panda-wiki.gsi.de/pub/Magnet/Internal/panda_coil_25_02_2011.zip, (Letter from R.Parodi of 30.11.11) Material properties of the cryostat shells are from presentation «Panda TS Aluminium Cryostat» (letter from R.Parodi of 12.05.12).

Gravity loads, Magnetic and seismic forces New load table of R. Parodi and H. Orth, May 8, 2012   m∙103 (kg) Zg (mm) SC coil and cryostat 10 355 Inner detectors 22 220   Fx (kN) Fy (kN) Fz (kN) Zg (mm) Magnetic forces in nominal position - -  -40 Magnetic decentering forces ±45 ±100 355 Horizontal seismic forces ±24 264

Requirements for the Rail Track Distance between the rails: 2860 ±0.5 mm Rail nonparallelism <0.2 mrad (1 mm/5 m) Rail dimensions 325-0.14 x 70 mm Gap between cam followers and rail +0.5 mm.

Allowable Deviations Inclination of the Cryostat Axis Cryostat axis inclination under action of magnetic forces has to be limited Δα ≤ 0.3 mrad Herbert Orth letter of 31.10.12.

Cryostat fixation units Option 1. Bottom beam fixation Option 2. Inclined beam fixation

Magnet door component arrangement

Magnet supports

Passages for tubing and cabling Additional space requested for muon cabling

FE model of the Magnet Model - Shell and beam finite elements Number of elements ~260 000 Computation time of a basic load case ~30 minutes Data base volume for one computation case -1.5Gb

List of Load Cases LC# Support scheme Door position and fixation type*) Gravity load Magnetic forces are applied to the yoke and to the coil at maximal current and for nominal position of the cryostat Magnetic forces applied to the cryostat and to the yoke at maximal current due to tolerable misalignments of the cryostat Horizontal seismic forces (acceleration) applied to the yoke parts and to the cryostat Run over an on-path irregularity of 1 mm in height Separation of platform beams due to misalignment of the rails   Doors at the cornices Doors weight is applied to the barrel (without stiffness) Doors stiffness is applied (without weight) FX = -45 kN FY = +45 kN FZ = -100 kN aX = -0.75 m\s2 aZ = -0.75 m\s2 Two supports for every platform beam (magnet transportation) Fifteen steady-state supports for every platform beam (magnet assembly and magnet operation) Gravity of the yoke Gravity of cryostat Gravity of the inner detectors Δ11 = +1mm Δ11= -1mm Δ12 = +1mm Δ12 = -1mm 51 x 52** 53** 54 55** 61 62 63 64 65 66 67 68 69 71 72 73 74 75 76 77 78 81*** 82**** 83 84 85  x 86 87

Vertical characteristics of the magnet supports Maximal vertical load on a support (roller carriage) in the process of movement 1221 kN Torsion stiffness of the yoke rigid fixation of the door 387 kN/mm nonrigid fixation of the door 225 kN/mm Separation on rail/roller interface rigid fixation of the door 2.1 mm nonrigid fixation of the door 3.7 mm

Axial characteristics of the magnet supports Axial stiffness of the yoke platform beam arrangement 152 kN/mm The friction force between the roller carriage and the rails in lateral direction (friction factor is 0.1) 1221 kN x 0.1 = 122 kN Maximal possible separation of the platform beams before roller carriage starts slipping 122/152=0.8 mm The roller carriages will start slipping before cam followers at the roller carriages interact with the rails because of platform beam separation in the process of movement 0.8<1 mm

Equivalent stress (Von Mises) in the plate L13 of the beam W7 (LC64) 62+40=102MPa η = 140/102 ≈1.4 LC61 (transportation position on four rollers) Run into on-path irregularity 1 mm in height

Deformity and Equivalent stress (Von Mises) for a run into on-path irregularity 1 mm in height (without gravity load)

Equivalent stress (Von Mises) in the side plate (W8/W1 junction) 50MPa+45MPa = 94 MPa LC61 (transportation position on four rollers) Widening of the roller track up to +1mm η = 140/94 ≈1.5 LC67

Vertical deformation of the cornices under action of the door jacks Vertical sag up to 0.6mm

Vertical deformity of the yoke barrel beams Maximal variation of the slots for muon panels ±0.5mm

Deformity and Equivalent stress (Von Mises) for barrel beam plate L1W1 with “b” and without “a” gravity of the disc calorimeter Maximal sag ≈0.7mm

Reference points of the yoke and cryostat

Cryostat deformity under action of magnetic forces Fx=45kN + Fz=140kN Cryostat Support Option 1 Deformity in X direction Deformity in Y direction 0.64 0.22 0.65 -0.18 0.23 -0.07 0.41 0.44 0.3 0.41 0.12 -0.41 0.03 0.13 0.04 -0.09 Δαmax = 0.137 mrad < [0.3 ] mrad

Cryostat deformity under action of magnetic forces Fx=45kN + Fz=140kN Deformity in Y direction Cryostat Support Option 2 0.18 -0.02 0.11 0.14 0.02 -0.01 Δαmax = 0.07 mrad 0.05 0.03

Cryostat support characteristics Maximal reactions in cryostat supports (option 1) Vertical Ry=-151kN/+47kN Axial Rz=70kN Lateral Rx=27kN Maximal reactions in cryostat supports (option 2) Vertical Ry=-105kN Axial Rz=74kN Lateral Rx=46kN

Safety Margins of the Fixation Units   ηtension ηshear Position Load case  1. Barrel bolts M24x2 1.7 B5(W8/W1) LC67  2. Platform bolts M24x2 1.4 B8P2 LC63  3. Cryostat support boltsM24x2 2.1 B6CR LC75  4. Space frame bolts M24x2 1.9 B7(W2/F2PL2) LC85  5. Door/barrel bolts M36x3 4 B1(D1/W3) LC64  6. Door wings bolts M36x3 9 B1(D11/D12) LC83 ηmin=

Main Results of Computations The strength of the iron yoke is on a sufficient level. The yoke is able to bear loads in all regimes with minimal safety margin 1.4. The request of muon group for increased passages for cabling has been met. The both cryostat support design options meet the demand of the GSI/INFN colleagues. From yoke strength point of view they are virtually identical. Main characteristics of the yoke supports are prepared for GSI Technical Specification for the rail track.

Design modifications based on the results of calculations It takes to prepare design of the yoke support arrangements on the base of discussion with Boerkey people. Door opener system has to be designed It takes to complete design of the selected option of the cryostat support. Barrel connection bolts are loaded by essential shear forces. Since it is difficult to provide their gapless mounting it takes some addition dowel pins to bear the shear forces in radial and axial directions. 8 bolts in barrel/platform interface bear tension/compression loads but other 12 bolts are always compressed. All bolts accept large shear forces. It takes to remove bolts which doesn’t bear tension loads and to use addition rests for shear. Some bolts in the cryostat supports (first option of the cryostat fixation) are loaded by a small part of the vertical tension load. So it takes to remove them and to take special measures to exclude shear load on these bolts. Vertical sag of the beam plate under action of the disc calorimeter gravity is 0.7 mm. To constrain deflection of the plate it takes a steel pad rigidly fixated to the beam plate.

List of interface problems to be fixed for yoke TDR finalizing Solenoid coil tolerances v.r.t. the yoke Attachment of the cryostat to the yoke: positions (coordinates) of the support points engineering design of the attachment units (part of the unit connected to the yoke) estimates of maximal loads (components of force and momentum) acting on the attachment units Engineering design of the attachment units, loads on them (components of force and momentum) and their geometrical characteristics for fixation to the yoke: target production system target dump (also shape and dimensions of the recess for it in the lower barrel beam) forward EMC and disc DIRC (information taken from presentation by H.Löhner, 2009) backward EMC (possible interference with the door and its rails) cryogenic system on top of the magnet (chimney, bucket) Additional equipment attached to the magnet from outside (fixation points, masses, possible loads and acceptable deformations): on the upper barrel beam (pumps, …?) on the lower barrel beam (optical system for the target dump control, …?) at the magnet side, on the platform (boxes with electronics, …?) – possible interference with the support frame that includes outer inclined beams muon filter – distance to the upstream magnet end cap, possibility of door opening: access to the units of the door halves fixation to each other is necessary Final positions, shape and dimensions of recesses in the yoke for the cable passages Limitations for the yoke parts displacements???

What should be done before announce the tender for the yoke It takes: to complete and to coordinate interfaces; to make some design modifications based on the results of mechanical calculations and to release the final drawings; to prepare technical specification and test manual for the yoke