Stator Plan & Schedule Chris Booth 2nd March 2009

Slides:



Advertisements
Similar presentations
Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Advertisements

MICE Target Report Video Conference 15/03/07 Chris Booth Sheffield 15 th March 2007.
April 05 Jason Tarrant CCLRC1 PRR of SCT off-detector cooling system l Cooling System »Design - Off-cylinder & On-cylinder »Installation – Off-cylinder.
ATD Assembly. ATD Assembly #1 Dewar Assembly #1 Status: Dewar has been completely assembled and vacuum tested. No vacuum leaks were detected on the outer.
The MICE Target Lara Howlett University of Sheffield.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
K. Long, 14 June, 2015  Target K. Long, Friday, 24 th April 2009.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
MICE Target Status Chris Booth Sheffield 10 th May 2006.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre.
GLAST LAT ProjectLAT Mgr’s Meeting LAT Planning Meeting Mechanical/Thermal Systems March 17, 2005 Marc Campell.
Target Update – Mico Meeting Monday 21 st April 2008 General Expect to obtain new coils for stators anytime New Shafts at RAL for metrology. Will be back.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
Cryo Capture Cavity II Progress Mike McGee April 6, 2005.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
HTS Solenoid Punch: Team Supercool. The Story So Far tos/boxeo/box-punch.jpg.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Target Design – Status and Plans Chris Booth Sheffield 12 th January 2005.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
EE planning meeting Lucie Linssen 1 CERN EE regional centre and Dee assembly plans Dee assembly TA3, not for EE Supercrystal regional centre.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Tuesday, November 16, 2010G. Favre EN/MME1 PIMS prototype construction experience Details of the construction procedure elaborated by CERN for the PIMS.
TCDI operation until LS2 LIU-SPS-to-LHC Transfer Line Protection Devices (TCDI) Review 1 Oliver Aberle 26/03/2014 O. Aberle (EN-STI-TCD)
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
1 Booster Corrector BPM Status AD/ Instrumentation Jim Fitzgerald.
DOE Rev of Run IIb Sep 24-26, Detector Production WBS James Fast Fermilab.
Installation and Testing of Optical Harnesses John Matheson Rutherford Appleton Laboratory Schedule for test and assembly Outline of required tests Acceptance.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Target Installation Plan. Requirement Assemble and test two complete target systems in time for August shutdown How do we do this? What do we need to.
Conceptual design of JPARC Horn 2 assembly L. Bartoszek Bartoszek Engineering/CU 5/5/04.
MICE Target Mechanical Design l Status of Target ref. Schedule »Drawings –Drawing list created (see next slide) includes inventory –Drawings being released.
Issues with variable thickness absorbers Iouri Ivaniouchenkov, RAL MICE Video Conference, 22 Jan
Refurbished Booster RF John Reid October 24, 2012.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
Decay Solenoid – what do we have to do to make it work?
Update on Module Mounting on Staves and Stavelets 25/8/11 1.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
LARP Collaboration Meeting Racetrack Coil Fabrication
1 FPA Stage 2 Peer Review May 12, 2006 T. Brown. 2 FPA Stage 2 Status Summary of Stage 2 activities Review current design status Review schedule details.
MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Chris Booth Sheffield 29th March 2006
Target Installation Plan
MQXC Nb-Ti 120mm 120T/m 2m models
Service channels between Tracker and PP1
Ladder Assembly All tools and jigs produced Glue dispensing works
CSP 25th November 2010 Technical agreement number 3: overview
HO Corrector Magnets: decapole test and future plans
MICE Target Report Video Conference 29/11/07
Ladder Assembly All tools and jigs produced Glue dispensing works
Teleconference ACS – FREIA 20th February 2018
NEG-coated gun: Black R30 arc at 227kV, white R30 arc at 164 after refurbishing and second bake Carlos Wednesday, August 10, 2018.
LCLS Vacuum System Plans (July 07)
UPPSALA UNIVERSITY_GERSEMI PROJECT
SC1R Cold Box PDR Assembly Sequence
Presentation transcript:

Stator Plan & Schedule Chris Booth 2nd March 2009 3 stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable from 2 demonstrator drives. If better coils available from Cambion in time, they will be used instead

University of Sheffield Parts Required Vacuum tubes (3) – To be ordered by & delivered by RAL. Not part of Sheffield assembly. (What delivery date?) Kapton tape – sufficient in stock. Coils (72 plus spares, say 90) 30 new, tested coils available 1 coil assembly (24 coils) usable as is; needs overall insulation check. Other coils (48) recoverable from demonstrator drives – may need cleaning and individually testing. Copper shims (about 450). Probably sufficient in stock. Check, order more if required. Heat transfer compound – available. End spacers (6) – make as required (quick). Cooling jackets (3) – all available (recoverable). Chris Booth University of Sheffield

Assembly Procedure & Schedule (1 ) Coils first assembled on temporary former, for later transfer to vacuum tube. Need 3 formers & holding jigs. (3 days to make all jigs.) Clean & electrically test coils; select by thickness. (3 days for all?) Fit end spacers, coils (with heat transfer compound), shims onto former. Clamp in holding jig. Check total length. (6 days for 3 assemblies) Fit cooling jackets. Final insulation check. (2 days – time for rebuild required if problem found!) Transfer coil assemblies to RAL. Chris Booth University of Sheffield

Assembly Procedure & Schedule (2) Transfer coil assemblies to RAL. Vacuum tubes covered in kapton tape (1 day) Stator assemblies fitted to vacuum tubes & flanges, prior to welding. (How is assembly fixed in place during mounting?) Electrical connections made after welding and assembly completed. (Where? RAL or Sheffield?) Swagelock fittings for water cooling added, prior to full test or install. (1 day) NB Construction (up to transfer to RAL) will be sequentially by stator; some tasks (e.g. electrical testing) in parallel. 28 working days available before Easter! Chris Booth University of Sheffield