ESS licensing process and Readiness Reviews

Slides:



Advertisements
Similar presentations
Final Competence Assessment Assessment Documents Assessment strategy (SummitSkills) Assessment methodology (SQA) Assessment guidelines (SQA)
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Pakistan Nuclear Regulatory Authority
UNRESTRICTED Infrastructure Assessment as Viewed by Technology Holders IAEA Technical Meeting December 10-12, 2008 R. Godden.
IAEA International Atomic Energy Agency. IAEA Outline Learning objectives Introduction Functions of Regulatory Body (RB) on EPR Appraisal guidance: Part.
Safety at ESS. Thomas Hansson Nuclear Safety Engineer at ESS, since November 2011 Experience from Swedish Nuclear Power Plants since 1991 (Mainly Fuel.
INSAG DEVELOPMENT OF A DOCUMENT ON HIGH LEVEL SAFETY RECOMMENDATIONS FOR NUCLEAR POWER Milestone Issues: Group C. Nuclear Safety. A. Alonso (INSAG Member)
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
Swedish IRRS mission 6-17 Feb 2012 IRRS lessons learned workshop – Brussels 22 nd and 23 rd January Elisabeth Öhlén and Ingemar Lund.
School for drafting regulations Nuclear Safety Operation Vienna, 26 November -7 December 2012 Tea Bilic Zabric.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
Thailand’s Preparation for Starting a Nuclear Power Program Mr. Pricha Karasuddhi Technical Advisor Nuclear Power Program Development Office(NPPDO) Ministry.
Aspects of the Management of High Level Waste and Spent Fuel – the Swedish Perspective Johan Anderberg Director, SSM Sweden Johan Anderberg.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
Milestones for Nuclear Power Infrastructure Development Establishment of A Regulatory Framework Gustavo Caruso, Section Head, Regulatory Activities Section.
Preparations of the Dutch IRRS-mission 1st ENSREG IRRS-WS Brussels, January 2014 By: R.Jansen (KFD)/A.Sedee (NIV)
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
Electrical Engineering for NSS - Status and Planning- Thomas Gahl Electrical Engineering Group Leader February 26, 2014.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
European Spallation Source Science Advisory Committee February 5-6, 2014 Jim Yeck CEO & Director General.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
Instrument Construction Phase 1 and beyond Rob Connatser Chief Instrument Project Engineer September, 2014.
1 Interfaces, Engineering and Standards. 2 Interfaces LoKI Interface document description for deliverables Elements: PBS number, Deliverable description,
ESS Accelerator| Construction Phase| | MC | 1 ESS Accelerator management & governance for Product Integration - Construction phase 25 January 2013.
Rob Connatser NSS Instrument Work Packages and XLPM.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
Site Organization and services for machine installation/commissioning Peter Rådahl June 2016.
Installation and Commisioning SE view point Romuald Duperrier ESS SE manager.
Operations WBS Dictionary Integrated Control Systems Henrik Carling ESS/ICS Date:
Container Freight Station, Utilities and Drainage at Bayport Container Terminal (RFQ-148) Brenda Trevino, P.E. Project Manager October 11, 2016.
East Area Renovation Project Team meeting # 2 – EDMS News
FC facilitation of Installations
Licensing update ESHAC #9, October 2018
ESHAC #9 – 1/2 October 2018 Ralf Trant
Radiation protection organisation
Radioactive waste management - status
Mikael Jakobsson ESS Installation Manager
Helen Boyer OHS group leader
ESS Project Status Roland Garoby – Technical Director August 2018.
ESS Installation Binders Readiness Reviews Work Orders Mikael Jakobsson ESS Installation Manager Sep , 2018.
Quality Regulation for Mechanical Equipment RESSQ – Mech
Operations/Control room organization during commissioning
Ian Evans SSRL Safety Office
Bunker Internal Review Welcome & Charge
Welcome and charge to the committee
Testing Coordination at ESS
Imaging & Engineering STAP Meeting 12th-13th of April 2018
PSS verification and validation
ESS Handbook for Radiation Protection
ESS Management System SSM visit 24th October
Licensing update TAC 18 October 2018
Internal Audits Management Review Meetings
Rules for Mechanical Design and Pressure Testing for Detector vessel
Radiation Protection Handbook
ESH&Q General Information
Radwaste: status & way forward
Radiation Protection Updates
INSTALLATION & COMMISSIONING TAC 14
High Level Readiness Reviews
Licensing update ESHAC #7, October 2017
Radiation Safety External hazards & antagonistic threats
Lessons from the 1st Safety Readiness Review
ESHAC Meeting # Peter Jacobsson Head of ESH
Bunker Critical Design Review Welcome & Charge
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Machine All Hands meeting #4 WoW-Ways of Working
Stuart Birch On behalf of Protection Systems Group
The European Commission’s science
Presentation transcript:

ESS licensing process and Readiness Reviews Peter Frisk Johan Waldeck Project Manager SSM Licensing Project Manager ESS

Presentation Outline SSM perspective of the licensing process and planned inspection program -Peter Frisk SSM ESS perspective of the licensing process and planned readiness reviews -Johan Waldeck ESS

The Swedish Radiation Safety Authority (SSM) reviews of the ESS facility The SSM reviews are performed according to the EU Basic Safety Standard (EU-directive), the Swedish Radiation Protection Act, the SSM regulations and the specific SSM conditions given to ESS The SSM reviews only include safety ralated to radiation (not chemical safety, electrical safety etc.) The SSM review team consists of about 30 reviewers, a mix of engineers, PhDs, etc. from different specialities, all based at SSM. There will be no SSM site office at ESS but SSM will perform regular site inspections. The SSM reviews will be stepwise and verifications of fulfilment of SSM requirements will be performed by site inspections. The SSM site inspections will be separated from the ESS readiness reviews both in time and in content.

The SSM reviews of the ESS facility The SSM document reviews will be based on the ESS safety analysis report including areas described below and a self assessments from ESS describing how they fulfil/are going to fulfil requirements given by SSM. Review areas: Organisation and Management of the Activities Protection of Workers Protection of Public and Environment Planned Emergency Preparedness Construction and Safety Analysis Mechanical Devices Physical Protection Cyber security Operation For each trial operation application ESS has to present a trial operation plan. SSM will review the plan and, thereafter, create an appropriate inspection program. ESS has to present operation limits and conditions for each trial operation application.

Licensing managed as a project Core Team composed of central resources and project representatives Team meets every week Coordinate work to be performed across ESS projects Licensing not a separate thread integrated part of “normal“ project activities Licensing project core team One member from each Project/division Johan Project manager Per N Target Sub-project Peter S NSS Sub-project Peter ESH Sub-project Lali Acc Sub-project Mikael J Admin & Proj. Man. Sub-project Henrik C ICS Sub-project Francois Systems engineering Carl Q Sub-project Michael CF Sub-project

Alignment of ESS project phases to SSM licensing steps Preliminary Design Detailed design & Construction Procurement and Installation Commissioning Operation ESS project phases Permissibility Permit Installation Trial operation Routine operation SSM stepwise licensing process

Key events in next trial operation permits ESS Application SSM Request ESS Response SSM Conditional permit ESS readiness review SSM Inspection Beam on Use this time to develop evidence

Split permit in parts to optimize overall schedule Warm LINAC Trial operation permit SC LINAC Neutron production

Within a permit, split commissioning into conditional steps IoS-RFQ Commissioning IoS-DTL2 Commissioning IoS-DTL4 Commissioning Warm LINAC commissioning ESS Readiness review SSM Inspection

Thank You!