2016 Alaska Western Workshop Cost Estimating 101

Slides:



Advertisements
Similar presentations
Presented by: Waymon Lofton & Jerry Coppo Practical Risk Analysis 2007 AACEI Conference.
Advertisements

Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
Chapter 3: Cost Estimation Techniques
AACEI Contingency Forum Contingency Management
Best Practices for an Owner Estimating Organization
Chapter 8 Pricing General Expenses. Introduction The direct costs of a building project include the cost of labor, material, equipment, and subtrades.
Chapter 14 Pricing General Expenses. Objectives Upon completion of this chapter, you will be able to: –Define general expenses –Use a checklist to identify.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
1 The Cost Approach An introduction Wayne Foss, MBA, MAI Wayne Foss Appraisals, Inc.
Chapter 41 Chapter 10 Strategic Cost Management. 2 Definition Strategic Cost Management: Supply chain partners working together to identify design changes,
Review of Plans & Estimating Introduction Architect’s Responsibilities Types of Estimates Factors Affecting Cost Film Project:
Project Cost Evaluation February 7, 2002 Richard Chung Department of Chemical and Materials Engineering San Jose State University.
Cost Estimating EGR 386. Estimating Up till this point in our economics lesson –assumed known future cash flows, but… An important aspect of engineering.
INTRODUCING THE COST APPROACH Chapter 11. Base cost Builder’s profit Building shell Building size and shape Comparative square-foot method Construction.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
CAPITAL COST ESTIMATES INSTALLED EQUIPMENT COSTS.
Project Risk and Cost Management. IS the future certain? The future is uncertain, but it is certain that there are two questions will be asked about our.
Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE.
Copyright ©2009 by Pearson Education, Inc. Upper Saddle River, New Jersey All rights reserved. Engineering Economy, Fourteenth Edition By William.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 10 Project Cost Management.
Specification & Quantities Estimating
Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
1 COST ESTIMATING. 2 Time Data Cost Data Performance Data Procurement Data Owner special Data Brainstorming Process Company Needs Market Research. Feasibility.
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
Underground Cost Analysis; Option 10 and 11 - TRTP Project Project Segment 8A Corridor October 21, 2012.
Produced by: Towards a Rational Cost Model Presenter: Tom Lenahan Tom Lenahan Limited.
BSBPMG504A Manage Project Costs 7.1 Estimate Costs Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of developing.
CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
ALI SALMAN1 LECTURE - 05 ASST PROF. ENGR ALI SALMAN ceme.nust.edu.pk DEPARTMENT OF ENGINEERING MANAGEMENT COLLEGE OF E & ME, NUST DEPARTMENT.
Costs and Cash Flows Estimation. Engineering Economic Analysis - Seven Steps 1. Recognition and formulation of the problem. 2. Development of the feasible.
English for Construction Engineering Management ,建筑工 程专业英语 赖小东 授课教师:赖小东 Cell# 江西财经大学旅游与城市管理学院工程管理系.
Multivariate Analysis - Introduction. What is Multivariate Analysis? The expression multivariate analysis is used to describe analyses of data that have.
DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.
Construction Tender Process Tender steps between Client, Contractor and Subcontractor Dr A Kimmance.
ENGINEERING n MANAGEMENT n ENVIRONMENTAL
Chapter 3: Cost Estimation Techniques
Project Cost Management
DNP Initiative ENG-003 Standard Design Process Overview Configuration Management Benchmarking Group June 12, 2017.
Project Management MGT 30725
The Design Team Carl James.
Chapter 3: Cost Estimation Techniques
Copyright All Rights Reserved by
Process Economics Factors that affect profitability
Process Layout Chapter #6.
Feasibility.
7.3 Determine Budget The process of aggregating the estimated costs of individual activities or work packages in order to establish an authorised cost.
Saint- Petersburg State University of Aerospace Instrumentation
Multivariate Analysis - Introduction
Manajemen Industri Instructor: Rama Oktavian
Estimating Project Costs
Costing and Project Evaluation
Assembling a Project Budget
Costs and Economics of Construction
(Additional materials)
STEPS IN THE DEVELOPMENT OF A DETAILED ESTIMATE
COST PLANNING AND ESTIMATION
The Cost Approach.
Pre-Contract Cost Control
Project Estimating Overview
Estimating Capital Costs
Chapter 3: Cost Estimation Techniques
Chapter 3: Cost Estimation Techniques
A SUMMARY NOTE ON REVISED GDP ESTIMATES
Introduction DEFINATION :-
Cost Behavior: Analysis and Use
Cost Estimating Best Practices
Cost Behavior: Analysis and Use
Multivariate Analysis - Introduction
Chapter 3: Cost Estimation Techniques
Presentation transcript:

2016 Alaska Western Workshop Cost Estimating 101

Agenda Introduction Estimate Terminology Estimate Classifications Estimate Methodology Application of Estimate Methodology Understanding Direct & Indirect Costs Questions

Estimating – What does this mean? Cost estimating is the predictive process used to quantify, cost, and price the resources required by the scope. Cost estimating may be used to quantify, cost and price any investment activity, such as building an office building or process power plant, developing a software program, or producing a stage play. The basic estimating steps are the same: Understand the scope of the activity to quantify the resources and material required, then apply costs to those resources and materials

Estimate Terminology Cost Estimating Basis of Estimate Direct Costs Predictive process used to quantify, cost, and price the resources required by the scope of an investment option, activity, or project. A compilation of all the probable costs of the elements of a project or effort included within an agreed upon scope. Costs of completing work that are directly attributable to its performance and are necessary for its completion. Cost Estimating Basis of Estimate Direct Costs 1. Direct Costs 2. Basis of Estimate 3. Cost Estimating

Estimate Terminology In-Direct Costs Take-off Contingency Costs not directly attributable to the completion of an activity, which are typically allocated or spread across all activities on a predetermined basis. A specific type of quantification that is a measurement and listing of quantities of materials from drawings in order to support the estimate costing process An amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs In-Direct Costs Take-off Contingency 1. In-Direct Costs 2. Contingency 3. Take-off

Estimate Terminology Allowances Escalation Benchmarking 1. Escalation Resources included in estimates to cover the cost of known but undefined requirements for an individual activity, work item, account or sub‐account. A provision in costs or prices for uncertain changes in technical, economic, and market conditions over time. A measurement and analysis process that compares practices, processes, and relevant measures to those of a selected basis of comparison with the goal of improving performance. Allowances Escalation Benchmarking 1. Escalation 2. Allowances 3. Benchmarking

Estimate Classifications AACE identifies five classes of estimates, which it simply designates as Class 1, 2, 3, 4, and 5. A Class 5 estimate is associated with the lowest level of project definition (or project maturity), and a Class 1 estimate is associated with the highest level of project definition. For each class of estimate, five characteristics are used to distinguish one class of estimate from another. The five characteristics used in the AACE Recommended Practice are: degree of project definition end usage of the estimate estimating methodology estimating accuracy effort required to produce the estimate

Estimate Classifications   ESTIMATE CLASS MATURITY LEVEL OF PROJECT DEFINITION DELIVERABLES Expressed as % of complete definition END USAGE Typical purpose of estimate METHODOLOGY Typical estimating method EXPECTED ACCURACY RANGE Typical +/- range relative to index of 1 (i.e. Class 1 estimate) [a] PREPARATION EFFORT Typical degree of effort relative to least cost index of 1 [b] 0% to 2% Screening or feasibility Capacity factored, parametric models, judgment, or analogy 4 to 20 1 1% to 15% Concept study or feasibility Equipment factored or parametric models 3 to 12 2 to 4 10% to 40% Budget authorization or control Semi-detailed unit costs with assembly level line items 2 to 6 3 to 10 30% to 75% Control or bid/tender Detailed unit cost with forced detailed take-off 1 to 3 5 to 20 65% to 100% Check estimate or bid/tender Detailed unit cost with detailed take-off 10 to 100 Class 5 Class 4 Class 3 Class 2 Class 1

Estimate Methodology In general, estimating methodologies commonly fall into two broad categories: conceptual and deterministic. Conceptual estimating methods usually involve modeling (or factoring), similar projects. Deterministic estimating methods are more or less a direct measure of the item being estimated.

Estimate Methodology Conceptual Estimating Methodologies End-Product Units Method Used when the estimator has enough historical data available from similar projects to re late the end-product units (capacity units) of a project to its construction costs. Example would be the construction cost of a hotel and the number of patient beds. Physical Dimensions Method Uses the physical dimensions (length, area, volume, etc.) of the item being estimated as the driving factor. For example, a building estimate may be based on square feet/meters or cubic volume of the building. Capacity Factor Method A capacity factored estimate is one in which the cost of a new facility is derived from the cost of a similar facility of a known (but usually different) capacity. It relies on the (typical) non-linear relationship between capacity and cost.

Estimate Methodology Conceptual Estimating Methodologies Ratio or Factor Method Ratio or factored estimating methods are used in situations where the total cost of an item or facility can be reliably estimated from the cost of a primary component. For example, this method is commonly used in estimating the cost of process and chemical plants where the cost of the specialized process equipment makes up a significant portion of the total project cost. This is often referred to as “Equipment Factor” estimating. Parametric Method A parametric model is a mathematical representation of cost relationships that provide a logical and predictable correlation between the physical or functional characteristics of a plant. For example Total Installed Cost/Dim in mile for pipelines.

Estimate Methodology Deterministic Estimating Methodologies A detailed estimate is one in which each component comprising a project scope definition is quantitatively surveyed and priced using the most realistic unit prices available. Detailed estimates are typically prepared to support final budget authorization, contractor bid tenders, cost control during project execution, and change orders (Class 3 through Class 1 estimates). The following steps comprise the activities undertaken during preparation of a detailed estimate: Prepare project estimate basis and schedule Prepare Direct Field Cost (DFC) estimate Prepare Indirect Field Cost (IFC) estimate Prepare Home Office Cost (HOC) estimate Prepare escalation estimates Prepare project fee estimate (for contractors) Prepare cost risk analysis/contingency determination Preview/validate estimate

Application of Estimate Methodology End Product Estimating Methodology If the construction costs for a 25 guest room hotel was $8,000,000 what would a 95 guest room hotel cost be utilizing the end product methodology? $30,400,000 If the construction costs for a 100 patient bed hospital was $18,000,000 what would a 185 patient bed hospital cost be utilizing the end product methodology? $33,300,000

Application of Estimate Methodology End Product Estimating Methodology If the construction costs for a 100 parking space garage was $13,000,000 what would a 30 parking space garage cost be utilizing the end product methodology? $3,900,000 If the construction costs for a 100 room storage complex was $1,800,000 what would a 150 room storage complex cost be utilizing the end product methodology? $2,700,000

Application of Estimate Methodology Physical Dimensions Estimating Methodology If the construction cost of a 2000 sf warehouse was recently built down the road for $600,000 what will your approximate construction cost be for a 3000 sf warehouse? $900,000 If the house next door which is 50’ wide x 100’ long cost $400,000 to build last week, what would your approximate cost be for your 5000 square foot house? $400,000

Application of Estimate Methodology Ratio or Factor Estimating Methodology In 1947, Hans Lang first published an article in Chemical Engineering introducing the concept of using the total cost of equipment to factor the total estimated cost of plant. Total Plant $ = Total Equipment $ X Equipment Factor Lang proposed three separate factors based on the type of process plant (see table below). Lang’s factors were meant to cover all the costs associated with the total installed cost of a plant. Lang Factor Type of Plant Factor Solid Process Plant 3.10 Solid-Fluid Process Plant 3.63 Fluid Process Plant 4.74

Application of Estimate Methodology Ratio or Factor Estimating Methodology If the total equipment cost for a gas liquid plant was $1,500,00 what would the Total Plant Cost be? Total Plant Cost = $1,500,000 x 4.74 Total Plant Cost = $7,110,000 If the total equipment cost for a wood pellet solid process plant was $5,000,000 what would the Total Plant Cost be? Total Plant Cost = $5,000,000 x 3.1 Total Plant Cost = $15,500,000

Deterministic Estimating Methodologies – Understanding Direct & Indirect costs The installation hours associated with a worker installing piping inside of a module would be considered a Direct or Indirect Man-hour? The travel time between hotel and the module where the worker is installing the pipe would be considered a Direct or Indirect Man-hour? Direct In-Direct 1. Direct 2. In-Direct

Deterministic Estimating Methodologies – Understanding Direct & Indirect costs Snow removal man-hours and equipment needed to get access to the module where the workers are installing piping inside of the module would be considered a Direct or Indirect cost? The installation hours and material costs associated with the structural crew who attaches lifting lugs to the module so that module can be set on truck with a crane would be considered a Direct or Indirect cost? In-Direct Direct 1. Direct 2. In-Direct

Deterministic Estimating Methodologies – Direct Examples Mechanical Man-hours Piping Man-hours Electrical & Instrumentation Man-hours Structural Man-hours Civil Man-hours Insulation Man-hours Painting & Coating Man-hours Architectural Man-hours Permanently Installed Material

Deterministic Estimating Methodologies – In-Direct Examples Fire watch Snow Removal Mobilization/Demobilization Construction Equipment Training Site Clean-up Small Tools and Consumables Travel to/from Job Site Safety Meetings

Questions ??