PIXEL CAEN Installation Status

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

Questionnaire Response
8/11/2006 FPIX TB meeting L. Perera 1 Pixel Power Supply Response Measurement Lalith Perera - Univ. of Iowa Carlos Florez, Simon Kwan, Charles Newsom,
Preparation of SPD Cabling Calo comissioning meeting – 19th July 2006 – CERN I.Status of cables II.Cable reels III.Labelling IV.Cabling inside a VFE box.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
AnDY Hardware. Run 12 Layout Detector set: – ZDCs, BBC-Y, BBC-B, PreShower phase 1, Ecal phase-1, Hcal phase-2.
Electrical and Optical Cables Installation at P5 What When How H. Breuker
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
Status of NA62 straw electronics and services Peter LICHARD, Johan Morant, Vito PALLADINO.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
DCS T0 DCS Answers to DCS Commissioning and Installation related questions ALICE week T.Karavicheva and the T0 team T0 DCS Answers to.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Technical Board Meeting, 14/06/07 Kristján Gulbrandsen, NBI 1 Progress on and Status of the Forward Multiplicity Detector Kristján Gulbrandsen Niels Bohr.
Status of NA62 straw electronics Webs Covers Services Readout.
Pixel Endcap Power Distribution Phase 1 Upgrade Plans Fermilab, University of Mississippi, University of Iowa Lalith Perera University of Mississippi CMS.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
RPC Trigger Electronics Review Subjects: Link System Low Voltage Link System Upgrade Krzysztof Doroba, University of Warsaw Krzysztof Doroba, RPC TRigger.
P. Paolucci - I.N.F.N. of Napoli 1 RPC workshop, 2 march 07 RPC Power system P. Paolucci, G. Polese and D. Lomidze I.N.F.N. di Napoli.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
8-May-2010 LV Workshop1 Alignment LV: quick’n dirty HW review Alignment uses CAEN low voltage –No HV –Low power consumption electronics: under kW.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
1 Update on Power Supplies TB L.Jirden u LV u Concerns u Orders & deliveries u Maintenance u HV u Overview u purchasing.
Cables Ian Crotty 8 May 2012 Cables for the RE4 Upscope in CMS News. The HV cables are in the Integration DB (INB/904) The Hv order is confirmed. Need.
J. Valls, CMS L2-L3 Meeting, Sept ROD Production at CERN  ROD Flow During Production  ROD Flow at CERN  ROD Testing Areas  Infrastructure  Equipment.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
Pixel Action Matrix C. Newsom July 15, Overview Critical Parameters Initial Discussion – Top 6 critical failures Discussion - Detailed Documentation.
Faculty of Physics, University of Belgrade Collaboration meeting, Budapest 15 th of May, ToF-L/R detector HV upgrade Jovan Puzović, Faculty of Physics,
Faculty of Physics, University of Belgrade Collaboration board meeting 31 th of January, ToF-L/R detector HV upgrade Jovan Puzović, Faculty of Physics,
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
TRT HV System status and plans for LS1 LPI Moscow, K. Zhukov.
Cables for the RE4 Upscope in CMS
Status of NA62 straw electronics and services
Cabling for LHCb Upgrade
LKr status R. Fantechi.
LV-workshop during CMS Electronics week
09/02/2006 Muon week HV and LV systems status for Magnet Test S. Braibant, P. Giacomelli, M. Giunta.
GEM DAQ-Chamber Integration Test Stand for GE2/1 & ME0 at Florida Tech
Injectors BLM system: PS Ring installation at EYETS
Christian Veelken last updated 11/09/06
RPC Barrel HV & LV system Lappeenranta University
T1 Electronic status Conclusions Electronics Cards:
Mini-drawers, FE-ASIC , Integrator
PMD PMD Plans Detector Issues and solution Plans for LS1 29 June 2012.
HV & LV status LV system in W+1 and W+2 is OK
Pierluigi Paolucci - I.N.F.N. Naples
Pierluigi Paolucci - I.N.F.N. Naples
RPC HV&LV status Introduction HV power supply tender
First Assembled Rod in US
Module Tests at MPP Test setup prepared by Philipp Leitl
Magnet PS Controls Hardware Status
VELO-meeting January 25, 2007 Sub-projects: SX & SX
CSC Hot Spares LV Modules (24 units needed) HV Modules Custom Modules
RPC Detector Control System: towards the final system
HV & LV status LV system in W+1 and W+2 is OK
Current Module LT Testing Capability
HV & LV status DELIVERED AT BLG /60  67% of the A3009 (LV)
US Rod Burn-in Readiness DAQ Hardware/Power Supplies
Equipment Status ARCS equipment status DAQ equipment status
19-April-05 Peripheral Crate Testing, Installation, and Commissioning PC I&C Feb ’06 EMU Fred Borcherding 16-May-19 PC I&C Feb'06.
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Hardware needs (ARCS) Current ARCS capabilities at both sites should be able to keep up with production assuming software changes Automatic I-V curves,
ME I&C -- PC Electronics
Racks PC Rack >> 24 mini and 12 tall PC racks Mini Racks
CSC Shift Training and Operation + B904 Status
Presentation transcript:

PIXEL CAEN Installation Status Presented by C. Newsom U. of Iowa March 31, 2008

CAEN Status (1) Cabling Installation is complete. Load testing and certification is complete (0% failures). A1676a controllers at S4F01 (4 ordered, 1 borrowed) 3 have been delivered 1 is installed at P5 and is in use (2 needed) 1 is at PSI 1 is at TIF. One of these will be installed at P5 when the detectors move to P5. 1 borrowed from CAEN is being used for A4603 burn-in at TIF. 1 spare has been ordered and should arrive in June/July.

CAEN Status (2) MAO (48V crate power supplies) at X2F36 and X2F37 (8 ordered) 2 borrowed supplies are installed, one on each rack. 6 are on order with delivery expected in April. They will be needed in early May. Burn in: Guido has promised to take care of this. 2 spares should be delivered in July. Crates (15 ordered) 11 have been delivered plus 2 borrowed (10 needed) 9 are installed. 7 are Pixel, 2 are borrowed from Guido 1 is bad and is being repaired by CAEN 2 are at TIF 1 is at PSI 4 are scheduled for delivery in July. We will have 5 spares.

CAEN Status (3) Interlock cards (12 ordered) 10 are installed at P5 (10 needed) 2 are spares The Patch panel wiring is underway and should be complete this week. A4602 LV power supplies (18 ordered) 17 have been received. 12 are installed at P5 (14 needed) 1 is in use at TIF 2 are in use at PSI 2 failed and are at CAEN awaiting repair. All but the 2 PSI modules have been tested and burned in. 1 is scheduled for delivery in July. Eventually we will have 4 spares.

CAEN Status (4) A4603 LV/HV power supplies (56 ordered) 14 have been received. 5 are installed at P5 (48 needed)* 4 are in use at TIF* 2 are in use at PSI 1 failed and is at CAEN awaiting repair. 2 are awaiting certification and burn-in. 8 are scheduled for delivery tomorrow. 32 more will be delivered in ~1 month 2 will be delivered in July. Eventually we will have 6 spares.

Certification and Burn-in Needs We have 4 load boxes and can certify and burn-in 8 modules per week at TIF. The tests are not quite as thorough as what is done at Prevessin. This procedure will be upgraded this week. Certification of RMS noise OV, UV, OC trips etc is done but other tests are not performed. CAEN has indicated that we will have 10 more modules to “certify” and “burn-in” this week. We should recertify and burn-in all new A4603 modules at Prevessin if this is possible.

Overall CAEN Status We have sufficient power supplies ready to commission ½ of either the Barrel or Forward Pixel detectors right now if we use both racks. In ~2 weeks that fraction will double but we will need additional MAOs to take full advantage of this. Ideally, we would want all 6 MAOs in place 2 weeks before the barrel insertion on May 26. That is sufficient to commission our detectors during installation although it is not optimal as it requires moving the A4603 cables. Simultaneous running of both detectors relies entirely on the CAEN 4603 and MAO delivery schedule.