Teleconf ACS – FREIA 28th March 2017

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M. Zisman LBNL.
Cryo Capture Cavity II Progress Mike McGee April 6, 2005.
Internal Cryomodule Instrumentation Sensors, Actuators, Heaters, and Wiring ERL Main Linac Cryomodule 9/5/2012 Peter Quigley Internal Design Review.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
1 HIGH ENERGY ACCELERATOR RESEARCH ORGANIZATION KEKB Review Committee/ NAKAI Hirotaka KEK Crab Cavity - Cryogenics - KEKB Crab Cavity Group - presented.
Agenda – Basics of cavity integration into CAST Introduction (M Davenport) Information exchange 2016 – Vacuum in cold bore – 2 cavities Cooling RF Cavities.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
RF power couplers vacuum issues J.M. Jimenez Vacuum, Surfaces and Coatings Group (TE-VSC)
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Installation of the T600 at Fermilab CSN2, September 22,
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
RESEARCH AND DEVELOPMENT FOR FUTURE LHC SUPERCONDUCTING MAGNETS POINT SUR LA STATION D’ESSAIS préparé par Jean-Marc Gheller Steering committee –September.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
S A Griffiths CM42 June 2015 Electrical & Control.
Final Design Cryogenic and mechanical configurations
Teleconference ACS – FREIA 31th May 2017
Teleconf ACS – FREIA 13th March 2017
Mechanical and cryogenic configurations
Installation of the T600 at Fermilab
S1G Experiment Schedule Plan
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
2K Cold Box FDR Introduction
IT-4189 Supply and installation of a cryogenic distribution system
Cryogenic behavior of the cryogenic system
MICE Meeting at RAL, Oct-23, 2005
HFM Test Station Main Cryostat
Proximity Cryogenics P&IDs meeting
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Cryoplant Installation Scope
Teleconference ACS – FREIA 18th April 2017
Teleconference ACS – FREIA 10th May 2017
Cryostat design Mechanical design: Thermal screens: Specifications:
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
Teleconference ACS – FREIA 17th October 2017
LARP Vertical Test Facility
Teleconference ACS – FREIA 31st October 2017
(vertical cryostat, Gersemi)
Cryostat design Mechanical design: Thermal screens: Specifications:
FRESCA Cryostats Outer cryostat during pressure test at the manufacturer Top plate and lambda plate for the outer cryostat Inner cryostat during reception.
Teleconference ACS – FREIA 20th February 2018
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
Schematic diagram of the cryogenic system
Prototype cryomodule development
Double-Spoke Cavities
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Cryogenic behavior of the magnet
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
SNS PPU Cryomodule Instrumentation
CRYOMODULE FINAL ASSEMBLY
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Teleconf ACS – FREIA 28th March 2017 Agenda: - Magnet insert mechanical studies - Liquid insert and cryostat manufacturing - Control and command (electrical equipments, cabling, sequences,  ...) - Simulator - Tests for the commissioning at Lery and Uppsala - Planning

Teleconf ACS - FREIA 28th March 2017 Magnet insert Last meetings et Lery, 21th and 27th March 2017 Heat exchanger Lambda HX683.  a future meeting with the Pro-Beam compagny (Thursday 30th mars 2017 at Lery) Agenda: - Presentation of Electron Beam Welding Technology - Technical design review of the copper HX in order to prepare it for EBW and pricing by ProBeam Teleconf ACS - FREIA 28th March 2017

Cryostat and Liquid insert Last meetings at Lery, 21th and 27th March 2017 All components are welded on the top flange of the liquid insert. The thermal shields of the liquid insert are manufactured, the assembly of all components is started. CD prepare the welding of tubes (length 300 mm) on each side of the lambda seat. Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017 Control and Command Electrical components implantation in the electrical cabinet. 7 AMI level controllers will be used for the liquid and magnet inserts, 2 additional AMI are required for the vacuum configuration. Technergie will try to add them inside the cabinet Electrical cabinet. The volume that will be occupied by the electrical cabinet is more important that 3.5m length . The minimum dimension for the electrical cabinet plus the cable trays is about 3.5 + 0.3m. UU must check the implantation of the cabinet with the cable trays. Connections box. One box for each equipment (valve box, cryostat, liquid insert, magnet insert) The current dimensions of these boxes are 400x400x150. ISII Tech and Technergie propose to extend the new trench (0.3x0.3m) until the cabinet. With this configuration, it will be possible to install directly under the ground the cables between the cryostat and the electrical cabinet.. The starting of the software programming is expected early April and the starting of each sequence tests in the end of May. Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017 Simulator box CD sent a quotation for the manufacturing: 29 615 € Planning: 1 (manufacturing drawings) + 8 (manufacturing) weeks after the order receipt Input Bellows & instrumentation “for free” Same connection to VB as TL012 Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017 Tests at Lery 1/2 Valve Box: Global leak detection (the leak tests of each component will be made during the manufacturing) -> 1 week Checking of the cabling, electrical tests of the valves, thermometers, electrical heaters, pressure sensors, level sensors, flowmeters, … -> 2 weeks Installation / connection of the simulator -> 1 week Cryogenic tests with LN2 and simulator -> 3 weeks to test about 10 sequences Cryostat: Global leak detection of the cold vessel (the leak tests of each component will be made during the manufacturing) -> 2 weeks No cryogenic test Teleconf ACS - FREIA 28th March 2017

Teleconf ACS - FREIA 28th March 2017 Tests at Lery 2/2 Liquid insert: Checking of the cabling, electrical tests -> 1 week No cryogenic test Magnet insert: Checking of the cabling, electrical tests of the valves, thermometers, electrical heaters, pressure sensors, level sensors, flowmeters, … -> 2 weeks Teleconf ACS - FREIA 28th March 2017

Commissioning tests at Uppsala 1/2 Valve Box: Global leak detection to check the valve box after its transport -> 1 week Cables installation -> 2 weeks Cabling checking and electrical tests -> 1 week Installation of the simulator -> 1 week Cryogenic tests with LN2 and LHe and the simulator -> 3 weeks to test about 15 sequences Cryostat: Global leak detection to check the cold vessel and the thermal shield after their transport -> 2 weeks Cables installation -> 3 weeks Installation of the liquid insert -> 1 week Removing of the simulator and installation of the cryogenic line between the cryostat and the valve box, vacuum pumping system in operation -> 1 week Teleconf ACS - FREIA 28th March 2017

Commissioning tests at Uppsala 2/2 Liquid insert: Cryogenic tests with the valve box and the liquid insert -> 2 weeks to test 12 sequences: Test of the sequences without cavity (Conditionning, LN2 cooling, LHe cooling, operation at 4.2K, Operation at 2K, warm up, ….) Magnet insert: Removing the liquid insert / installation of the magnet insert -> 1 week Cabling checking and electrical tests -> 1 week, Cryogenic tests with the valve box and the magnet insert -> 5 weeks to test 18 sequences: Test of the sequences without magnet (Conditionning, LN2 cooling, LHe cooling, operation at 4.2K, Operation at 2K, warm up, ….) Teleconf ACS - FREIA 28th March 2017

Planning of the tests at Lery Teleconf ACS - FREIA 28th March 2017

Planning of the tests at Uppsala Teleconf ACS - FREIA 28th March 2017