2011 Road School Session 75 Wednesday – March 9th 9:00 am – 9:50 am 1 PDH/.1 CEU
CULVERT SLIP LINING Part 1 – LaPorte District Slip Lining- Case Study Stephen Ritzler INDOT LaPorte District Project Manager Part 2 – Flowing More Water with a Smaller Pipe Scott Brown, EIT Part 3 – Recent INDOT Specification Changes, Oval Liner Darin Duncan, PE Part 4 – INDOT QPA Sam Martin
INDOT LaPorte District Case Study Stephen Ritzler INDOT LaPorte District Project Manager
Flowing More Water with a Smaller Pipe Scott Brown, EIT
Flowing More Water with a Smaller Pipe Overview Pipe liners are smoother than the existing A smoother pipe means higher velocity A higher velocity means a higher flow Under inlet control conditions, pipe smoothness becomes a minor factor – the end area/geometry become the key factors
Flowing More Water with a Smaller Pipe Manning’s Equation Equation that gives flow estimates based on friction of the pipe material, pipe size, and pipe slope Gives an “apples-to-apples” comparison Applies to a partially or nearly full flowing culvert
Flowing More Water with a Smaller Pipe Manning’s Equation Q = Flow Rate/Discharge - gpm n = Roughness coefficient (Manning’s “n”) d = Pipe Diameter – in. s = Slope – ft/ft
Flowing More Water with a Smaller Pipe Manning’s “n” Coefficient representative of pipe roughness The smaller the number, the smoother the pipe The smoother the pipe, the faster the velocity
Flowing More Water with a Smaller Pipe Manning’s “n” Factors Solid Wall HDPE n = 0.009 – 0.012 Profile Wall HDPE n = 0.012 Concrete n = 0.012 CMP n = 0.024 Multi-Plate n = 0.035
72” CMP PIPE Slope, s= 0.0025 CMP n = 0.024 Q = 51,475.1 gpm Flowing More Water with a Smaller Pipe 72” CMP PIPE Slope, s= 0.0025 CMP n = 0.024 Q = 51,475.1 gpm
63” OD/59.1” ID HDPE SOLID WALL Flowing More Water with a Smaller Pipe 63” OD/59.1” ID HDPE SOLID WALL Slope, s= 0.0025 HDPE Solid Wall n = 0.01* Q = 72,967 gpm *INDOT Hydraulics typically uses 0.01
63” OD/59.1” ID HDPE SOLID WALL Flowing More Water with a Smaller Pipe 72” CMP VS. 63” OD/59.1” ID HDPE SOLID WALL 72” CMP Q = 51,475.10 gpm HDPE Solid Wall Liner Q = 72,967 gpm 72,967/51,475.10 = 1.42 or 142% 42% Increase in flow
Flowing More Water with a Smaller Pipe INLET CONTROL Occurs when the culvert barrel can convey more than it can accept Flow is limited by pipe opening size Manning’s Equation does not apply
72” CMP under inlet control HDPE LINER HYDRAULICS 72” CMP under inlet control 106.81
63” Solid Wall HDPE liner under inlet control HDPE LINER HYDRAULICS 63” Solid Wall HDPE liner under inlet control 107.18
63” Solid Wall HDPE liner under inlet control Flowing More Water with a Smaller Pipe 63” Solid Wall HDPE liner under inlet control
Flowing More Water with a Smaller Pipe
72” CMP under inlet control Flowing More Water with a Smaller Pipe 72” CMP under inlet control 106.81
63” Solid Wall HDPE liner under inlet control Flowing More Water with a Smaller Pipe 63” Solid Wall HDPE liner under inlet control 106.71
63” Solid Wall HDPE liner under inlet control Flowing More Water with a Smaller Pipe 63” Solid Wall HDPE liner under inlet control 106.81 106.71
Flowing More Water with a Smaller Pipe
Flowing More Water with a Smaller Pipe
Flowing More Water with a Smaller Pipe
Flowing More Water with a Smaller Pipe Energy Dissipator
Dubois/Perry Counties Flowing More Water with a Smaller Pipe Vincennes District INDOT Designer: Richard Thomas Dubois/Perry Counties I-64
Flowing More Water with a Smaller Pipe
Flowing More Water with a Smaller Pipe
Flowing More Water with a Smaller Pipe
Flowing More Water with a Smaller Pipe
Recent INDOT Specification Changes, Oval Liners Darin Duncan, PE
INDOT Standards Committee February 17, 2011 Problem: For the past 4 years, the 725 specification section in the book has been superseded with RSP 725-R-541. Solution: Incorporate the modified 725-R-541 provision into the SS book to replace the existing 725 section
INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 1. OVAL LINER ADDED
2. TYPE A CERTIFICATION REMOVED INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 2. TYPE A CERTIFICATION REMOVED
2. TYPE A CERTIFICATION REMOVED – CONT’D http://www.in.gov/indot/2581.htm
2. TYPE A CERTIFICATION REMOVED – CONT’D http://www.in.gov/indot/div/M&T/appmat/appmat.htm
2. TYPE A CERTIFICATION REMOVED – CONT’D http://www.in.gov/indot/div/M&T/appmat/pubs/apl25.pdf QCP Plan is a major factor in getting on the approved list.
3. OVALING MANUFACTURING REQUIREMENTS INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 3. OVALING MANUFACTURING REQUIREMENTS
4. QUALITY CONTROL CHANGES - INSPECTIONS INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 4. QUALITY CONTROL CHANGES - INSPECTIONS
5. PIPE CLEANING AND INSPECTION INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 5. PIPE CLEANING AND INSPECTION
INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 6. SIZING ALL OF CHART DELETED
7. PAY ITEM – SF OPENING, NOT DIAMETER INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 7. PAY ITEM – SF OPENING, NOT DIAMETER
INDOT Standards Committee February 17, 2011 NOTABLE CHANGES: 8. BULKHEADS
OVALED LINERS: Solid Wall HDPE Only
INDOT QPA Sam Martin