2017 AGC Summer Conference July 28, 2017 Todd Steagall, P.E., Director of Construction
Organizational Changes
Organizational Changes DEA District 6 – Tim Henderson replaces Robert Clark DEA District 7 – Kevin Gantt Acting Deputy Secretary for Intermodal Planning – Jim Feda Chief Engineer for Project Delivery – Randall Young Director of Environmental – Chad Long Assistant Bridge Construction Engineer – Steve Nanney DEA District 1 – Robert Dickinson replaces Bryan Jones
Organizational Changes RCE Changes: York (Jared Bragg replacing John Huskins) Chester/Fairfield (Mike Moss interim for Jeremiah Bradley) Charleston (Darlene Broughton replaces Rickie Green) Charleston (Sarah Gaffney replaces John Paulus) Charleston Bridge (Vacant – Jeff Rajabi) Colleton Bridge (Keith Green replaces Tony Ragos) Richland (Derek Frick replaces Chris Kelly)
Organizational Changes RCE Changes: Greenville (Jack Valetti replaces Kimberly Bishop) Cherokee (Wes Spencer replaces Shane Parris) District 5 Travis Patrick replaces Jason Thompson (Jason left SCDOT for Horry County) Darlington (Philip Bethea replaces Heather Ford) Dillon (Trey Parnell replaces Scott Ward) Lexington (Joey McIntyre to HQ) Sumter (Jeffrey Wilkes moved to Lee Maintenance)
Upcoming Construction Retirements DCE Lee Neighbors – District 2 RCE Tim Callenback - Pickens RCE John Huskins – York DCE Robbie Isgett – Military duty for 1 year
Current Contract Status
*Does not include ER or County projects
*Total Highway Construction Projects: 416 Total Current Contract Amount Total Value of Work Performed Contracts in Force *Total Highway Construction Projects: 416 Federal: State: Other: $1,609,993,021 $2,905,620,361 $ 388,208,408 $ 907,418,932 Federal: State: Other: $ 577,889,900 $882,435,313 $ 125,398,283 $ 179,147,130 Total Remaining Contract Value Federal: State: Other: $ 1,032,103,121 $2,023,185,048 $ 262,810,125 $ 728,271,802 As of 05/20/17 Source: DOC *Include only contracts in SCDOT’s name Includes through May 2017 letting, Wando DB, I85/385 DB, Bridge PKG E DB, US701 DB, I77 DB, I20DB, Port Access, I85DBPH1/2, and Volvo Does not include Emergency Recovery projects (ER). ER projects have a separate slide.
*ER contracts not included
Future Projects
Upcoming Bid Build Asphalt Projects (Tentative Dates) I-26 MM 75-85 Total Reconstruction (2018) I-26 MM 65-75 Reconstruction (2019/2020) I-95 MM 171-193 SB Overlay (2018/2019) I-95 MM 193-198 (2017) I-26 MM 22-43 (2017) I-95 MM 22-33 (2017) I-95 MM 33-60 (2020)
Upcoming Design Build Major Interstate Projects (Tentative Dates) I-85 Widening MM 98-106 (2017) - Asphalt I-26 Widening MM 85-101 (2018) Carolina Crossroads (2019) I-85 Widening MM 40-69 (2020-2022) I-526 Widening MM11-18 Low Country Corridor (2020) I-26 Widening MM 14-22 (2023) I-526 Widening MM 18-30 (2024) I-26 Widening MM 212-218 (2026)
Upcoming Low Country Projects I-26 Widening MM 194-197 (Summer 2018) Jedburg to Nexton Parkway US 17 – Jasper County (Late 2018) 4 miles of widening from 2 to 4 lanes w/divided median Berlin Myers Parkway (2019-Permit Dependent) I-26 Widening MM 187-194 (Summer 2021) SC 27 to Jedburg
Upcoming Upstate Projects Anderson – Browns Rd./Kings Rd. Roundabout (Nov. 2017) Anderson – Concord Rd./Harris Bridge Rd. Roundabout (Nov. 2017) Spartanburg – S-30 Roundabout (Nov. 2017) Spartanburg – Crescent Ave. Bridge Replacement (Nov. 2017) Pickens – S-153 Extension (Nov. 2017)
Upcoming Upstate Projects Edgefield – S-68 Bridge Replacement over Turkey Creek (Dec. 2017) McCormick – S-823 Bridge Replacement over Little River (Dec. 2017) Greenville – Roper Mountain Road Ext. and Widening (Jan. 2018) Greenville – Batesville Road Widening (March 2018)
Upcoming Pee Dee Projects Dillon - I-95 SB Rehab MM 171-193 (Dec. 2018) Florence/Lee – US 76 Bridge Replacement over Lynches River (March 2019) Florence – Alligator Road Widening (June 2019) Williamsburg – Andrews By-Pass Phase II New Location (August 2019)
Upcoming Midlands Projects Lexington – US 378 Bridge Replacements over Horse and Hollow Creeks (Nov. 2017) York – I-77 at Gold Hill Road Interchange Improvement (April 2018) Lexington - US 1 Widening (Summer 2018) Newberry - I-26 Reconstruction MM 75-85 (Summer 2018)
Upcoming Midlands Projects Laurens/Newberry - I-26 Rehab MM 60-75 (Summer 2019) Richland – I-77 Rehab MM 22-27 (Summer 2019) Lexington – Columbia Avenue Widening in Chapin (Fall 2019)
Specifications
Notable Specification Updates Approved Muck Excavation – defined maximum limits and quantity if no bid item in contract Prompt Payment Clause – added a resolution clause Claims Procedure – added timeframe for decision acceptance In Progress Cement Modified Recycled Base SC-M-400 – Hot Mix Asphalt Quality Assurance
Program Challenges Manpower Project Management Loss of institutional knowledge SCDOT Contractors CE&I Limited number of available bodies State forces reducing Reduced experience factor Increased reliance on consultant forces Qualified Labor Availability
Program Challenges Capacity Are contractors nearing capacity? Plant production and laydown capabilities equal? New plants (new sites as well as silos at existing plants) Labor Pool Dwindling interest in career field Training Recruitment Retention Projects and Letting Size Scope Timing of letting
Bottom Line
Bottom Line SCDOT and AGC are in this together We will not deliver this program without working side by side Trust and Communication are essential We will succeed or fail as a team
QUESTIONS ??