PERT CPM assumes duration of activity is known with certainty.

Slides:



Advertisements
Similar presentations
Chapter 13 Project Scheduling: PERT/CPM
Advertisements

ES=32 EF=34 LS=33 LF=35 ES=10 EF=16 LS=10 LF=16 ES=4+6=10 EF=10 LS=4
Project Management - Part 2
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
pert and cpm ch 9 Learning objectives:
Fall 2001BA Project Management1 BA 301 – Spring 2003.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Chapter 9 Project Management.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
In the name of Allah the Most Gracious the Most Merciful.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved. 1 Chapter 3 part 2 Project Management.
Project Management Techniques.
BA 333 Operations Management
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Project Management OPIM 310-Lecture.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
SEEM 3530 Program Evaluation and Review Technique
Project Management CPM, PERT, Crashing – An Illustrative Example
Project Management Chapter 13 OPS 370. Projects Project Management Five Phases 1. Initiation 2. Planning 3. Execution 4. Control 5. Closure.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 6 th Edition Chapter.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Project Management (專案管理)
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
© The McGraw-Hill Companies, Inc., Project Management CPM and PERT.
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
Q1) A precedes C. B precedes D & E. C precedes F & G. D precedes G.
PERT/CPM F G A E H I J K D St T B C
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Beni Asllani University of Tennessee at Chattanooga
Chapter 3 Project Management. Chapter 3 Project Management.
PERT/Activity Diagrams, Completion Probability and the Z Score
Project Management (專案管理)
Project Management Chapter Topics
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
PERT and CPM.
Hospital Establishment
Project Planning & Scheduling
Project Planning & Scheduling
17 Project Management.
PROJECT MANAGEMENT WITH CPM/PERT.
17 Project Management.
Project Management CPM Method Tutorial-p2
Project Planning and Budgeting
Probabilistic Time Estimates
Stevenson 17 Project Management.
CHAPTER 8: SCHEDULING (PENJADUALAN)
ENM448-Project Planning and Management
Chapter 3 Project Management.
Planning and Managing Projects
PERT/Activity Diagrams, Completion Probability and the Z Score
Managing Risk Chapter 7.
Presentation transcript:

PERT CPM assumes duration of activity is known with certainty. PERT assumes duration of activity as a random variable. For an activity, PERT estimates three quantities: a : optimistic duration under most favorable condition b : pessimistic duration under least favorable condition m : most likely value for activity’s duration

Probabilistic Estimates Activity start Optimistic time Most likely time (mode) Pessimistic time to tp tm te

Let Tij be the duration of activity (i,j) Let Tij be the duration of activity (i,j). PERT assumes that Tij follows a beta distribution and, mean and variance of Tij may be approximated by : expected duration of activities on any path : variance of duration of activities on any path

Example variance of PROJECT = variance of CRITICAL PATH if more than one critical path, PROJECT VARIANCE=largest of CRITICAL Example Activity a b m (1,2) 5 13 9 (1,3) 2 10 6 (3,5) 3 8 (3,4) 1 7 (4,5) 12 (5,6) 15

Project Diagram

Specified time – Path mean Path standard deviation critical path = B-D-E-F. Thus, E(CP) = 9 + 0 + 7 + 10 + 12 = 38 var(CP) = 1.78 + 0 + 4 + 0.44 + 1 = 7.22 standard deviation for CP is (7.22)1/2=2.69 What is the chance of completing project within 35 days ? there is a 13% chance of completing project within 35 days. Z = Specified time – Path mean Path standard deviation Z indicates how many s.d the specified time is beyond the expected path duration.

PERT Example activity duration predecessor te A 2 / 3 / 6 weeks - 3.33 B 3 / 6 / 10 weeks A 6.17 C 1 / 1 / 2 week A 1.17 D 3 / 3 / 3 weeks B, C 3.00 CRITICAL PATH: A-B-D EXPECTED DURATION: 3.33 + 6.17 + 3 = 12.5 VARIANCE: { (6-2) / 6}^2 + {(10-3) / 6}^2 + {(3-3) / 6}^2 = 1.805 STD = 1.344 e.g. if critical path expected = 9.5, and STD = 1.354 target=10 , Z = (10-9.5) / 1.354 = .369 probability = .644

EXAMPLE

EXAMPLE (Cont.) Identify all paths and their estimated completion times and variances.

Probability of Critical Path Being Completed in 39 Weeks or Less

PERT Example 1 2 4 6 7 3 5 9 8 Manual Testing Dummy System Training System Testing Orientation Position recruiting System development Equipment testing and modification Final debugging System changeover Job training Equipment installation 25

Example (Cont.) Time estimates (wks) Mean Time Variance Activity a b c t s2 1 - 2 6 8 10 8 .44 1 - 3 3 6 9 6 1.00 1 - 4 1 3 5 3 .44 2 - 5 0 0 0 0 .00 2 - 6 2 4 12 5 2.78 3 - 5 2 3 4 3 .11 4 - 5 3 4 5 4 .11 4 - 8 2 2 2 2 .00 5 - 7 3 7 11 7 1.78 5 - 8 2 4 6 4 .44 7 - 8 0 0 0 0 .00 6 - 9 1 4 7 4 1.00 7 - 9 1 10 13 9 4.00 26

Example (Cont.) Activity t s2 ES EF LS LF S 1 - 2 8 0.44 0 8 1 9 1 1 - 2 8 0.44 0 8 1 9 1 1 - 3 6 1.00 0 6 0 6 0 1 - 4 3 0.44 0 3 2 5 2 2 - 5 0 0.00 8 8 9 9 1 2 - 6 5 2.78 8 13 16 21 8 3 - 5 3 0.11 6 9 6 9 0 4 - 5 4 0.11 3 7 5 9 2 4 - 8 2 0.00 3 5 14 16 11 5 - 7 7 1.78 9 16 9 16 0 5 - 8 4 0.44 9 13 12 16 3 7 - 8 0 0.00 13 13 16 16 3 6 - 9 4 1.00 13 17 21 25 8 7 - 9 9 4.00 16 25 16 25 0 27

Example (Cont.) ( ) ( ) ( ) ( ) 1 2 4 6 7 3 5 9 8 ( ) ES=8, EF=8 LS=9, LF=9 ES=6, EF=9 LS=6, LF=9 ( ) ES=3, EF=5 LS=14, LF=16 ES=0, EF=3 LS=2, LF=5 ES=0, EF=6 LS=0, LF=6 ES=3, EF=7 LS=5, LF=9 ES=9, EF=13 LS=12, LF=16 LS=9, LF=16 ES=13, EF=13 LS=16 LF=16 ES=13, EF=25 LS=16 LF=25 ES=8, EF=13 LS=16 LF=21 ( ) ES=0, EF=8 LS=1, LF=9 ( ) ES=13, EF=25 LS=16 LF=25 s2 = s2 13 + s2 35 + s2 57 + s2 79 = 1.00 +0.11 + 1.78 + 4.00 = 6.89 weeks 28

. Determining Probability From Z Value s Z 0.00 0.01 … 0.09 What is the probability that project is completed within 30 weeks? s2 = 6.89 weeks, s = 6.89 = 2.62 weeks Z = x - m = 30 - 25 = 1.91 P(Z < 1.91) = 0.9719 2.62 s P( x < 30 weeks) = 0.50+ 0.4767 = 0.9767 . Z 0.00 0.01 … 0.09 1.9 0.4713 0.4719 … 0.4767 m = 25 Time (weeks) x = 30 33

What is the probability that project will be completed within 22 weeks ? Time (weeks) x = 22 P( x< 22 weeks) = 0.1271 22 - 25 -3 2.62 2.62 P(Z< -1.14) = 0.1271 = Z = = -1.14 34

PERT Probability Example A project has an expected completion time of 40 weeks, with a standard deviation of 5 weeks. What is the probability of finishing the project in 50 weeks or less? T = 40 s = 5 50 X Normal Distribution Z = - 40 5 2 . m z = 0 = 1 2.0 Standardized Normal Distribution 48

Obtaining the Probability m z = 0 s Z = 1 2.0 .00 .01 .02 0.0 .50000 .50399 .50798 : .97725 .97784 .97831 2.1 .98214 .98257 .98300 Standardized Normal Probability Table (Portion) Probabilities in body 49