Cryostats for superconducting magnets

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

ColUSM #51 30 th January, 2015 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, Q. Deliege, V. Baglin, F. Savary.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
ZQNA Electrostatic Quadrupoles for ELENA Transfer Lines 1.Conceptual design 2.Performance 3.Engineering details 4.Interfaces 5.Production planning D. Barna,
Construction of Wendelstein 7-X Max-Planck-Institut für Plasmaphysik
Possible HTS wire implementation Amalia Ballarino Care HHH Working Meeting LHC beam-beam effects and beam-beam interaction CERN, 28 th August 2008.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
26 April 2013 Immanuel Gfall (HEPHY Vienna) Belle II SVD Overview.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Technical agreement n 3 New SC Magnets activities P. Fessia (G. De Rijk), D. Reynet, J.M Rifflet.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Date 2007/Oct./25 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Report N. Ohuchi KEK 1.Cryomodule & Cryogenics KOM 2.GDE-meeting discussion I.Interface.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
JRA on Development of High Temperature SC Link Motivation Work Packages Partners & resources Amalia Ballarino Esgard open meeting CERN,
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
The integration of 420 m detectors into the LHC
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Thermal screen of the cryostat Presented by Evgeny Koshurnikov, GSI, Darmstadt September 8, 2015 Joint Institute for Nuclear Research (Dubna)
Cryogenics for SuperB IR Magnets J. G. Weisend II SLAC National Accelerator Lab.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Toward a Reasoned Design.
HL-LHC Magnet components and assemblies
Status of the PANDA Solenoid Magnet Production in BINP
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
Hervé Allain, R. van Weelderen (CERN)
SLHC –PP WP6 LHC IR Upgrade - Phase I.
Roadmap for triplet cryostats
IT-4189 Supply and installation of a cryogenic distribution system
11 T Dipole Integration & Plans M. Karppinen
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
HFM Test Station Main Cryostat
LEP cryostat Procurement strategy and plans
Cryostat procurement, status and plan, QA/QC
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Cryo-assembly design D. Ramos, V. Parma, C. Mucher, H. Prin, M. Souchet, J. Hrivnak, M. Moretti, L. Mora, F. Savary, L. Gentini Review of the 11T Dipoles.
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
Challenges of vacuum chambers with adjustable gap for SC undulators
Status of cryostat integration and conceptual design
Leak Detection Tutorial Work
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
SIS100 quadrupole status S. Kostromin, H. Khodzhibagiyan, G. Trubnikov, FAIR 11th MAC, GSI, May,
Parts exchange for HL-LHC AUP Q1&Q3
The 11T cryo-assembly: summary of design and integration aspects
Design of Distribution Feedbox at LHC P7
Status of the PANDA Solenoid Magnet Production in BINP
The Quench Detection-Wire-Feedthrough Plug-In of W7-X
Phase II Collimators : design status
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Status of the PANDA Solenoid Magnet Production in BINP
as a prototype for Super c-tau factory
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
Magnetic shielding and thermal shielding
Status of QQXF cryostat
Presentation transcript:

Cryostats for superconducting magnets Délio Ramos, CERN, Technology Department 2nd HiLumi Industry Day, Lisboa, 31st October 2016

A typical magnet cryostat in the LHC Superconducting coils in a bath of liquid helium at 1.9 K ~1000 W of electrical power per 1 W extracted at 1.9 K: Extreme thermal insulation is a must! Thermal contraction of stainless steel ~3 mm/m length i.e. 45 mm over a 15 m dipole magnet; ~80 m over the whole LHC! Precise and stable alignement of large and heavy structures: tight fabrication tolerances

Some guidelines for the design and construction Issue Solution Some requirements/ specifications Convection heat transfer Vacuum (~10-6 mbar) Leak tightness is critical, especially on large cryostats like the LHC Qualification of welding procedures and welders Material compatibility Cleanliness Conduction heat transfer Insulating support materials (ex. GFRE) Stifness and strength Repeatability of material properties and dimensions Layout taking into account thermal displacements Thermal radiation Reflective surfaces (Multi-layer insulation) Avoid openings Low compactness Proper assembly techniques to prevent thermal bridges Film material and coating properties Thermodynamic efficiency Intercept heat at intermediate temperatures (ex. thermal shield at 50-65 K) High conductivity materials Avoid poor thermal contacts

For installation in 2019-2020: 11 T magnets First Nb3Sn high field magnets in a particle accelerator will create space for installation of new collimators LBH LBH LEN On-going integration study for trim current leads Specification drawings for bottom trays being prepared Drawings controlled Procurement started Prototype under fabrication QA documents being prepared Tooling design nearly finished Overal integration length: 15660 mm

For installation in 2019-2020: Connection cryostats New collimators installed in a location without magnets but new cryostats needed Same bypass cryostat as for 11T in IR7 LEP LEN LEP Two connection cryostat units Detailed calculations and 3D modeling on-going Main challenge: alignment and stability of the beam lines w.r.t. interconnect forces Details on alignment and stability of beam lines being studied by simluations and tests Overal integration length: 12774.7 mm

For installation in 2024-2025: Insertion regions Nb3Sn quadrupoles, separation dipoles and others Larger magnet diameters but cryostat of same diameter because of tunnel size restrictions: compact design New support system Complex interconnect and pipework Under design

For installation in 2024-2025: Cryostats for interfaces with cold powering + Supporting structure + Safety devices + Instrumentation + tooling + expansion joints DFMJ DFXJ Superconducting link Circuits in 4.5-20K GHe Electrical connection between the circuits in gaseous helium and the superconducting magnet circuits in superfluid helium Prototype and tooling by Q1 2018 8 unis + 2 spares for production in 2019-2020 Cold powering cable

In a few numbers 77 cryostat units | 70 procured by CERN, incl. prototypes and spares Diameter ~1 m Unit lenghts vary from 2 m up to 15 m Roughly 500 m of new cryostats to be installed in the LHC Carbon steel, stainless steel, aluminium, glass fiber composites… Production from now until 2025 Assembly schedule at CERN

Strategy for construction Design done at CERN (internal design office with service contractor) Procurement of components in industry, mostly as “build-to-print” supplies according to CERN drawings and detailed specifications Assembly at CERN with on-site support of industrial contractors (ex.: mechanical assembly, welding, quality control)

Vacuum vessels Cylindrical sections in carbon steel (certified for pressure applications at -50ºC) with flanges in stainless steel Precisely machined interfaces (large milling machines needed) Qualified welders and welding procedures Leak detection, welding NDT, 3D metrology Full traceability

Multi-layer insulation Reflective sheets made from polyester film with aluminium thin coating on both sides Supplied in blankets of 10 or 15 reflective layers interleaved with insulating spacer layers made from polyester net Blankets joined with Velcro® tape Shape and size of the blankets to be designed by the manufacturer About 50’000 m2 of reflective layer!

Thermal shields Aluminium extrusions or roled sheets as structural elements Up to 14 m long Precise machining of support interfaces and extremities Aluminium to stainles steel transitons Leak tigth aluminium welds

Cold supports Designed for stifness and strength with minimum heat load Glass fibre reinforced epoxy Tight control of packing factor Equal and repeatable thermal contraction Finish machining after moulding

Expansion joints Compensation for thermal contraction during cooldown Reliability, leak tightness over the machine lifetime From vacuum to 20 bar EJMA, EN 13445 Strict material specifications Full traceability of materials, manufacturing and QC ~500 units

Piping and ancilliaries Required inside most cryostats for helium distribution and routing of superconducting cables Pressurised up to 20 bar EN 13480 Qualified welders and welding procedures Extensive welding QC

Cold mass for connection cryostats Used in cold parts of the accelerator without magnets, to route cryogenic services and superconducting cables Precise alignment Uniformity of temperature Pressure vessel 20 bar EN 13458, EN 13445 Stainless steel with cobalt content < 0.10% 4 units plus 2 spares Assembly in 2018

Upcoming procurement contracts (main items) Quantity Milestones Status Bypass proto vacuum vessel 1 unit Order issued Oct 2016 Delivery April 2017 Contract adjudication 11T and Connection Cryostat series vacuum vessels 13 + 6 optional Tendering process started Sep 2016 Finance committe and order issued June 2017 Delivery of first unit Nov 2017 Delivery of last unit end 2018 Market survey docs under preparation Bypass series vacuum vessels 6 units Tendering process starts Oct 2016 Order issued Jan 2017 Delivery of first unit June 2017 Delivery of last unit June 2018 Preparation of PE docs Q1/3 proto, Q2 proto 1, Q2 proto 2 3 units + 1 optional Start procurement procedure Mar 2017 Order issued Mar 2018 Delivery first unit Sep 2018 Delivery last unit Aug 2019 Planning Q4 and Q10 8 + 2 optional Start procurement procedure June 2017 Order issued Jun 2018 Delivery first unit Dec 2018 Delivery last unit Dec 2019 Q1/3 series, Q2 series, all CP, all D2 Start procurement procedure June 2018 Order issued May 2019 Delivery first unit Nov 2019 Delivery last unit Dec 2022

Thank you for your attention!