Jefferson Lab High Power Beam Dump Refurbishment

Slides:



Advertisements
Similar presentations
12GeV Project CD-4 Leigh Harwood Associate Project Manager Accelerator Systems.
Advertisements

New Radiation Safety Interlock System for the SPring-8 Accelerator Complex C. Saji, M. Toko, T. Matsushita, R. Furuta, H. Hanaki, S. Hashimoto 1), Y. Hashimoto,
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Chris Tennant Jefferson Laboratory March 15, 2013 “Workshop to Explore Physics Opportunities with Intense, Polarized Electron Beams up to 300 MeV”
February 17-18, 2010 R&D ERL Ady Hershcovitch R&D ERL Beam Dump Ady Hershcovitch February 17-18, 2010 Beam Dump.
PEP-II Ramp Down to a Minimum Maintenance State J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Approved Labyrinth Fresh air pulled through “chicken wire” gate.
Thomas Jefferson National Accelerator Facility Page 1 23 rd Annual HUGS Program June 2-20, 2008 CEBAF Overview HUGS08 June 3 CEBAF Overview HUGS08 June.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
Integration, Installation & Infrastructure Ans Pardons, with input from the WP4 members September 2014.
Beam Dump Upgrade Planning Keith Welch 2/5/13. Drivers for Upgrade Historical Problems – Hardware failures Helium system Windows, diffusers Dehumidifiers.
Contractor Assurance System Peer Review April Page 1 NSTAR 2011 May 16, 2011 Jefferson Lab Hugh Montgomery.
Thomas Jefferson National Accelerator Facility
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
Welcome to Jefferson Lab R. D. McKeown Jefferson Lab Hypernuclear Workshop May 27, 2014.
Machine Protection at the 1MW CEBAF Electron Accelerator and Free Electron Laser Facility Kelly Mahoney Presented at the Workshop for.
1 Target Station Design for Neutrino Superbeams Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory NBI 2012, CERN.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
Extraction Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
Y. R. Roblin Hall A beamline and accelerator status.
Thomas Jefferson National Accelerator Facility SensL 6-Oct CHL-2 12 GeV CEBAF Upgrade magnets and power supplies Two 1.1GV linacs Enhanced capabilities.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
Communication Tools Used For Commissioning the 12 GeV CEBAF Accelerator Brian Freeman WAO (Mainz, Germany) October 2014.
June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.
Science and Technology Briefing Sept
SRF Operating Experience at JLab
Cost Optimization Models for SRF Linacs
Preliminary Decommissioning Plan for the Canadian Light Source
Shielding Design for LCLS Injector Operation – Phase one
CBETA Technical Review
Page Headline Beam Commissioning Adam Bartnik.
FRIB Cryogenic Support
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Jefferson Lab Reliability Task Force and Initiatives
News and brief overview of Beamline plans for the next few months
Hosting Orsay Walid KAABI
N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal S. Girod EN-EA.
UK RFD Pre-Series cryomodule
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
CEBAF Injector Overview
The Fermi National Accelerator Laboratory is a U. S
12 GeV CEBAF.
Cost Optimization Models for SRF Linacs
Introduction to Jefferson Lab
Operations Department
Mathew C. Wright January 26, 2009
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
Anthony DiPette Installation / Vacuum Group Leader 7/17/2015
Extract from today’s talk given to DCB
Upgraded Injector Test Facility
Performance Recovery at CEBAF
J. Seeman Assistant Director for PPA/LCLS
Electron Beam Systems ETC and Methodology
Hall C Dump Status Beam Resuscitation Review
Extraction Michael Bevins May 17, 2007
SOLID Collaboration Meeting
Comparison between 4K and 2K operation performance of CEBAF injector cryomodules Grigory Eremeev Monday, August 19, 2019.
Presentation transcript:

Jefferson Lab High Power Beam Dump Refurbishment David Hamlette, RRPT RadCon Field Operations Manager

Welcome to Jefferson Lab Managed and operated for the DOE by the Jefferson Science Associates, LLC (JSA) Continuous Electron Beam Accelerator Facility (CEBAF) 2 superconducting RF linacs, 2 arcs with four experimental halls Low Energy Recirculation Facility (LERF) 120 MeV energy-recovery linac

12 Jefferson Lab Layout 11 6 GeV CEBAF CHL-2 Upgrade magnets and power supplies 12 11 6 GeV CEBAF Two 0.6 GeV linacs 1.1 For years we supported physics experiments by providing 6GeV accelerator operations at various currents. In 2012 we began a roughly 2 year energy upgrade. Roughly 7/8 of a mile, at that time, the CEBAF linacs housed 20 cryomodules each, capable of 0.6GeV per pass. We added 5 C100 cryomodules to each linac. Upgraded 100’s of magnets, and increased our cryogenics capacity by adding CHL-2( central helium liquefier building). At the same time ground was broke for Hall D, which actually consists of two buildings; Hall Tagger and Hall D proper). Those additions enable us to deliver 11GeV beam to the high power experimental halls A & C, which were designed to take the full design power of 1MW. The dump refirb applies to these halls. To increase beam energy to 12 Gev and transport beam to Hall D an additional arc and transport line were added. I am not sure how many how many of you have visited our campus, or how many were signed up to take the tour, so I wanted to give you a VERY brief virtual tour… When going through this, use it to introduce power levels available to each hall – A and C can take the full design power of 1 MW (operations limit of 0.9). Dump refirb applies to these two halls. Enhanced capabilities in existing Halls Lower pass beam energies still available

Our first stop is the Injector Our first stop is the Injector. What you are looking at here is our polarized electron gun. Recent modifications, to include a 4-laser system, gives us the ability to delivery beam to all four halls simultaneously.

High Power Dump Overview Vac Line Helium Beamline

High Power Dump Parameters Although engineering design assessment showed the existing Al water-cooled dump design was satisfactory for ~11 GeV beam delivered to halls A and C – provided power density design limits are not exceeded – after 15+ years of operation high power dump systems needed refurbishment and upgrade.

Dump Upgrade Project Scope The $1.5M project focused on the following: Inspection NDT dump window and piping Assessment of diagnostic hardware Upgrade beam transport hardware Replace helium tubes and upgrade helium blanket system Vacuum-to-helium interface modification Upgrade dump protection hardware Beam diffuser redesign for higher energy Ion chambers – CERN design, retrievable from outside Replace dump cave air treatment systems with dry nitrogen inerting systems N2 generator(s) Improved atmospheric isolation (wall integrity) Add diagnostics (flow, humidity, etc.) Upgrade beam transport diagnostics Viewer system with tune and CW operation capability Upgrade camera mechanical mounting and shielding package

Post run conditions 300 mR/h dump proper-whole body dose rates (w/ 3R/h near dump) Contamination ~5k dpm/100cm2 general area, up to 100k dpm/100cm2 (localized) Permit required confined space

Hall A Upgrade Phases Ultrasonic testing (UT) Demo of hardware Well coordinated with subcontractor Mock-up using spare dump Demo of hardware Remove beam diffuser, burn-thru detector, windows Remove old ion chambers and associated cabling Decontamination Machining of existing equipment Installation of new hardware

Estimated col. Dose (person-mrem) Dose received (person-mrem) Hall A Year Work phase Estimated col. Dose (person-mrem) Dose received (person-mrem)   2013 Survey/disassembly/Inspect 250 85 NDT 2227 367 Totals for 2013 2477 452 2014 Reassemble beamline(for short run) 1137 673 Demo/Weld/leak test/Install new components and diag hardware 3875 2825 Total  7489 3950 Radwaste – 7548lbs (mostly metal) Highest dose rates on waste 1700 mR/h contact; 100 mR/h @ 1 ft

Hall A (final Configuration) Vacuum Tube w/ internal Aperture Plate-water cooled Vacuum Window – water cooled Ion Chamber High Power Viewer Existing Corrugated Tube Tune-Mode Viewer Calibration Mechanism Isolation Wall Dual Camera Box

Hall A “Challenges” Although well briefed and planned between work groups, and was a great success; still some disconnects… Legacy drawing issues Work spaces proved to be challenging (tight) Decontamination hitches Unexpected material handling issues (leading to re-weld) Steep learning curve (working in HRA/CA not routine) Work planning Minor non-compliance (breach of radiological area) * These challenges addressed as “Lessons Learned” for Hall C project

Hall C Post run conditions Whole body dose rates 1.1 R/h (5x Hall A), req’d physical access controls (contact max 11 R/h six months after shutdown ) Contamination 100k dpm/100cm2 general area Permit required confined space Elevated platform Compact work space (7’x7’)

Hall C Upgrade Phases Identical to Hall A with the exception of overall beam layout… UT inspection Demo of hardware Decontamination attempts Installation of new hardware

Hall A “LL” Implemented Legacy drawings  Design review w/visual inspection Work spaces  Installed work platform Material handling issues  Jib cranes, intermodal in hall Decontamination  DeconGel Work planning  RadCon Task communicator

DeconGel Hydrogel polymer Apply-dry-peel Encapsulates and binds to prevent spreading Non-hazardous; OSHA /RCRA Meets environmental and regulatory requirements ~ 100 ft 1 3 2 1 - Blue shaded area to be cut up and removed 2 - Orange areas are labyrinth shield walls (8x8x16 concrete blocks to be removed and disposed) 3 - Green shaded area of tunnel to be decontaminated if possible

DeconGel (Hardware Removal)

DeconGel (area decon)

Hall C (final Configuration) High Power Viewer Transport Line Ion chambers Tune-Mode Viewer Calibration Mechanism Isolation Wall Dual Camera Box Iso-wall pushed back Camera/viewer diagnostics New concrete blocks

Estimated col. Dose (person-mrem) Dose received (person-mrem) Hall C Year Work phase Estimated col. Dose (person-mrem) Dose received (person-mrem)   2015 Tear-out, disassembly 1670 841 Inspect/test dump, reassemble beamline to be reused 2945 1728 Strip/decontaminate tunnel 468 76 Totals for 2015 5083 2645 2016 Install new components 642 289 Grand Total  5725 3034 This represents a significant ALARA achievement, considering the relative radiation levels in the Hall C dump (5 times higher on average than Hall A) Radwaste – 8740 lbs of metal; ~370 lbs compactables; 19170 lbs concrete blocks; Total 28280 lbs Highest dose rates on waste 3000 mR/h contact; 300 mR/h @ 1 ft

Hall C “Challenges” Daily brief w/ Task communicator was very effective, however, there were still areas that created re-work and/or minor delays Legacy Drawing issues cont’d Work spaces proved to be challenging (tighter) DeconGel learning curve Medical emergency in radiological area

Summary Slide What created the potential rad impact?  Both activation and contamination How many tons of material are affected?  ~30000 lbs steel, aluminum, concrete Evaluation approach: IFB What organizations provided assistance?  Multi-Divisional effort (Engineering, Industrial Hygiene, Installation, Physics) What percentages or tonnage were released as scrap, landfill waste, rad waste, reuse? Essentially all materials removed from dump were radwaste