Interstate Transmission system

Slides:



Advertisements
Similar presentations
Definition of Firm Energy and Interruptible Transmission Two Issues Causing Problems for Business in the Western Interconnection.
Advertisements

Contract and Grant Provisions and Administration Section 105 (Page 30) Title I The Act.
Sharing of ISTS Charges & Losses Regulation
Open Access Pune Power Development Pvt. Ltd.. Contents:  Terminology  Open Access  Requirements for Open Access  Provisions made in Electricity Act.
OPEN ACCESS IN INTER-STATE TRANSMISSION. DEFINITION OF “ OPEN ACCESS ” IN THE ELECTRICITY ACT, 2003 “The non-discriminatory provision for the use of transmission.
Maharashtra State Load Despatch Centre Role of SLDC in RRF Implementation & Issues By MSLDC.
Congestion When transmission demand >capability When Voltage levels in a corridor beyond operable limits When Real time line flow exceeds the TTC Most.
MAIN PREMISES TO THE FINANCIAL SECURITY RULES USED BY THE GAS TRANSMISSION OPERATOR GAZ-SYSTEM S.A. IN TRANSMISSION CONTRACTS AND NETWORK CONNECTION AGREEMENTS.
Net Metering and Interconnection Stakeholder Discussion Net Metering and Interconnection Stakeholder Meeting September 21, 2012 Discussion of.
RRF Mechanism ENERGY ACCOUNTING Western Regional Power Committee
Central Electricity Regulatory Commission (Grant of Regulatory Approval for execution of Inter-State Transmission Scheme to Central Transmission Utility)
Settlement system of Bilateral transactions under Open Access
GENFLEX TARIFF AND INCOPORATION OF THE MEC INTO THE NMD RULES
INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.
Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of Transmission Licence and other related matters) Regulations, 2009.
Largest sized hydro unit (180 MW at Chamera) in the country Salient Features Northern Regional Power System Welcome Reforms Within The State, Trading And.
Service Tax Voluntary Compliance Encouragement Scheme, 2013 [Chapter VI of Finance Act, 2013] Amnesty Scheme – Updated with Department Clarification.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 Network Operating Committee (NOC) June 12 th, 2014.
Grant of Connectivity,LTA, MTOA Interstate Transmission system
IEGC PROVOSIONS FOR RENEWABLE GENERATION SCHEDULING & UI SETTLEMENT 1.
Billing, Collection and Disbursement Procedures
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
With amendments w.e.f  (1) In these regulations, unless the context otherwise requires,-  (a) ‘Act’ means the Electricity Act, 2003 (36.
Section 7.5 –4 – ii of Indian Electricity Grid code (IEGC): “The summation of station-wise ex-power plant drawal schedules for all ISGS after deducting.
1 Bilateral Interconnection Agreement Model Presented to HAPUA Working Group 5 (ESI Services), Project 6 By Power Purchase Agreement Division Electricity.
THE RIGHT TO INFORMATION ACT, SECTION 3 Subject to the provisions of this Act, all citizens shall have the right to information.
1 Application Process Process of Seeking Information Day 5.
11/3/2015 NRLDC: POSOCO 1 Grant of Connectivity,LTA, MTOA In Interstate Transmission system CERC Regulation 2009 D.K.JAIN, DGM NRLDC, POSOCO.
Open Access for Renewables New initiatives. Scheduling and OA of RE Open Access through LTA/ MTOA/ STOA route envisaged Applicable to Wind and Solar without.
11/27/2015 NRLDC: POSOCO 1 Open Access In Interstate Transmission system Principal Regulation 2008( 25 th Jan’2008) Amendment Regulation 2009(20 th May’2009)
SCHEDULING METHODOLOGY The station-wise (Ex-bus) capability would be submitted by the ISGSs in the specified format. ISGSs would declare the capability.
ABT / IEGC CLAUSES While making or revising their declaration of capability, the generator shall ensure that their declared capability during peak hours.
Grant of Connectivity,LTA, MTOA In Interstate Transmission system Regulation 2009.
Workshop on State-Level Electricity Reforms: Firm Choices, Emerging Generation Markets and Externalities “Open Access: Experiences” ALOK ROY General Manager,
Congestion regulations. Definitions and Interpretation “Available Transfer Capability (ATC)” means the transfer capability of the inter- control area.
OPEN ACCESS IN INTER STATE TRANSMISSION. Gazette Notification of Open Access in inter state transmission systemGazette Notification of Open Access in.
1 INTRA – STATE AVAILABILITY BASED TARIFF (ABT) A Presentation on INTRA – STATE AVAILABILITY BASED TARIFF (ABT)
Power Trading Corporation Of India Ltd. Mahendra Kumar Director, Power Trading Corporation of India Ltd. Power Trade Perspective.
Philippine Feed-In Tariff System Implementation 1.
Renewable Energy Act of 2008
Transmission Tariff V.Balaji Chief Manager SRLDC.
Open Access In Interstate Transmission system Principal Regulation 2008( 25 th Jan’2008) Amendment Regulation 2009(20 th May’2009) Order-Removal of difficulties,(28.
NORTHERN REGIONAL LOAD DISPATCH CENTER 1.Revision Of Ceiling Of UI Rates and slope. 2.Revision Of Schedule after a Transmission Constraint is over. 4.RLDC’s.
Demarcation of responsibilities (as per IEGC) 1. REGIONAL GRID SHALL BE OPERATED AS LOOSE POWER POOLS WITH STATES HAVING FULL OPERATIONAL AUTONOMY. 2.SYSTEM.
Southern Regional Power Committee Central Electricity Authority.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
Point of connection Mechanism
Sharing of Inter-State Transmission Charges and Losses Abbhimanyu Gartia, Dy General Manager, WRLDC, MUMBAI.
OPEN ACCESS IN INTER STATE TRANSMISSION 29 TH MARCH TH MARCH 2004.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
Transmission Tariff Regulations. 1. ‘Applicant’ means a generating company or transmission licensee who has made an application for determination of tariff.
OPEN ACCESS IN INTER-STATE TRANSMISSION. INTRODUCTION Open Access is necessary for utilization of short time surpluses. Open Access will also create options.
Operationalizing One Nation One Grid
Open Access.
Administration of a FIDIC Contract - Financial Management
Open Access.
INTERCONNECTION GUIDELINES
Scheduling of Collective Transactions Through Power Exchange
MANAGING BUDGET FUNDS IN THE REPUIBLIC OF KAZAKHSTAN
Massachusetts Electric Restructuring Roundtable
Congestion regulations
Flexibility in Utilization of Domestic Coal
IN INTER-STATE TRANSMISSION
Pseudo-tie business procedure
Current as of 12/12/2017 RES-BCT.
Discussion of Isolated Small Scale Electrical Power Enterprise Regulations Nay Pyi Taw, March 2018 Jakob Schmidt-Reindahl.
Grant of Connectivity,LTA, MTOA Interstate Transmission system
COGAIN Kick-Off 5-6 September, 2004 FINANCIAL GUIDELINES
Main S+D Provisions of the WTO-Agreement on Trade Facilitation
Pseudo-tie business procedure
Presentation transcript:

Interstate Transmission system Grant of MTOA In Interstate Transmission system Regulation 2009

Regulatory frame work - August 2009 Who can apply Connectivity Generating station incl captive with installed capacity – 250 MW & above ( Modified in Sept 2010 to 50MW above for hydro/renewables) Bulk Consumer – 100 MW and above for hydro/renewables < 50 MW individually collectively aggregated to > 50Mw through lead generator Medium Term Open Access (MTOA) and Long Term Access (LTA) a generating station including captive, a consumer an Electricity Trader or a distribution licensee

Chapter I: Definitions Applicant A Generating station of installed capacity >= 250MW A Captive Plant of exportable capacity >= 250MW A Bulk Consumer : minimum of 100 MW load A Distribution Licensee An Electricity Trader Connectivity: for a generating station, including a captive generating plant, a bulk consumer or an inter-State transmission licensee means the state of getting connected to the inter-State transmission system Long Term Access: Right to use the inter-State transmission system for a period exceeding 12 years but not exceeding 25 years;

Definitions….. continued Long-term customer: means a person who has been granted long-term access and includes a person who has been allocated central sector generation that is electricity supply from a generating station owned or controlled by the Central Government; Medium-term open access: means the right to use the inter-State transmission system for a period exceeding 3 months but not exceeding 3 years; Medium-term customer means a person who has been granted medium-term open access;

Definitions….. continued Nodal agency: means the Central Transmission Utility referred to in regulation 4 hereof Regional entity means a person whose metering and energy accounting are done at the regional level; Short-term open access has the meaning ascribed thereto in the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2008;

Chapter 2: General Provisions Scope Provided that a generating station, including captive generating plant or a bulk consumer, seeking connectivity to the inter-State transmission system cannot apply for long-term access or medium-term open access without applying for connectivity: Provided further that a person may apply for connectivity and long-term access or medium-term open access simultaneously. Nodal Agency The nodal agency for grant of connectivity, long-term access and medium term open access to the inter-State transmission system shall be the Central Transmission Utility.

General provisions….. contd Filing of Application Applications for grant of connectivity or long-term access or medium-term open access shall be made to the nodal agency an application for connectivity is not required to be made by any transmission licensee, since transmission system planning is carried out in a coordinated manner by the Central Transmission Utility and the Central Electricity Authority an inter-State transmission licensee other than Central Transmission Utility, nevertheless, shall sign a connection agreement with the Central Transmission Utility, as provided for in Clause (5) of regulation 8 of these Regulations.

General provisions …contd Application Fees Sl No Quantum of power to be injected/off taken into/from ISTS Application fees ` lakhs for for for Connectivity LTA MTOA 1 Up to 100MW 2 2 1 2 More than 100MW and up to 500MW 3 3 2 3 More than 500MW and upto 1000MW 6 6 3 4 More than 1000MW 9 9 4

General provisions …contd Time frame for processing

Chapter 4 : LTA & MTOA Criteria for Grant: CTU to consider augmentation of ISTS proposed under the plans made by the Central Electricity Authority. MTOA shall be granted if the resultant power flow can be accommodated in the existing transmission system or the transmission system under execution: no augmentation shall be carried out to the transmission system for the sole purpose of granting medium-term open access: Construction of a dedicated transmission line shall not be construed as augmentation of the transmission system for the purpose

LTA & MTOA…. contd Relative priority Applications for long-term access or medium-term open access shall be processed First-come-first-served basis separately for each of the aforesaid types of access: Applications received during a month shall be construed to have arrived concurrently. While processing applications for medium-term open access received during a month, the application seeking access for a longer term shall have higher priority. In the case of applications for long-term access requiring planning or augmentation of transmission system, such planning or augmentation, as the case may be, shall be considered on 30th of June and 31st of December in each year in order to develop a coordinated transmission plan, in accordance with the perspective transmission plans if an intra-State entity is applying for long-term access or medium-term open access, concurrence of the State Load Despatch Centre shall be obtained in advance and submitted along with the application to the nodal agency.. State Load Despatch Centre shall convey its concurrence to the applicant within ten working days Where necessary infrastructure required for energy metering and time-blockwise accounting already exists and required transmission capacity in the State network 3. In case SLDC decides not to give concurrence, the same shall be communicated to the applicant in writing, giving the reason for refusal within the above stipulated period.

Chapter 6: MTOA Application for Medium-term Open Access The application for grant of medium-term open access shall contain the point of injection into the grid, point of drawal from the grid and the quantum of power for which medium-term open access has been applied for. The start date of the medium-term open access shall not be earlier than 5 months and not later than 1 year from the last day of the month in which application has been made. System Studies by the Nodal Agency On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in inter-State transmission system to be used, including State Transmission Utility, if the State network is likely to be used, process the application and carry out the necessary system studies as expeditiously as possible so as to ensure that the decision to grant or refuse medium-term open access is made within the timeframe

MTOA…… contd Grant of MTOA The applicant shall sign an agreement for MTOA with the CTU. shall sign a tripartite MTOA with the Central Transmission Utility and the inter-State transmission licensee The MTOA shall contain the date of commencement of long-term access the point of injection of power into the grid point of drawal from the grid the details of dedicated transmission lines, if any Immediately after grant of MTOA, the nodal agency shall inform the RLDCs and the SLDCs concerned so that they can consider the same while processing requests for grant of short-term open access

MTOA ….. contd Execution of Dedicated Transmission Line Medium-term customer may arrange for execution of the dedicated transmission line at its own risk and cost before the start date of the mediumterm open access. No overriding preference On the expiry of period of the medium-term open access, the medium-term customer shall not be entitled to any overriding preference for renewal of the term. Exit option for medium-term customers A medium-term customer may relinquish rights, fully or partly, by giving at east 30 days prior notice to the nodal agency: Provided that the medium-term customer relinquishing its rights shall pay applicable transmission charges for the period of relinquishment or 30 days which ever is lesser.

Chapter 7: Conditions of LTA & MTOA Curtailment Transmission constraints or in the interest of grid security - transactions already scheduled may be curtailed by the Regional Load Despatch Centre. Subject to provisions of the Grid Code and any other regulation specified by the Commission, the short-term customer shall be curtailed first followed by the medium-term customers, which shall be followed by the long term customers and amongst the customers of a particular category, curtailment shall be carried out on pro rata basis.

Conditions of LTA & MTOA Transmission Charges The transmission charges for use of the inter-State transmission system shall be recovered from the long-term customers and the medium-term customers in accordance with terms and conditions of tariff specified by the Commission from time to time Provided that if the State network is also being used in the access as a part of inter-State transmission system for the conveyance of electricity across the territory of an intervening State as well as conveyance within the State which is incidental to such inter-State transmission of electricity, recovery of charges for such State network and terms and conditions thereof shall be in accordance with the regulation as may be specified by the Commission under 25 section 36 of the Act for intervening transmission facilities, if such charges and terms and conditions cannot be mutually agreed upon by the licensees; Provided that any disagreement on transmission charges for such State network as specified above, shall not be the sole reason for denying access and either party may approach the Commission for determination of transmission charges for such State network.

Conditions of LTA & MTOA Fees and charges for the Regional Load Despatch Centre and the State Load Despatch Centre The fees and charges for the Regional Load Despatch Centre including charges for the Unified Load Despatch and Communication Scheme shall be payable by the long-term customer and medium-term customer as may be specified by the Commission. The fees and charges for the State Load Despatch Centre shall be payable as applicable.

Conditions of LTA & MTOA Payment of transmission charges and Fees and Charges for the Regional Load Despatch Centre The transmission charges in respect of the LTA and MTOA customer payable directly to the transmission licensee: CTU may be designated by the Commission as agency for the purpose of collecting and disbursing the transmission charges for ISTS CTU shall enter into agreements with the long-term customers and medium-term customers for collection of transmission charges and with the transmission licensees whose inter-State transmission system is being used disbursement of transmission charges: pro rata to the transmission charges payable to the transmission licensees and to the Central Transmission Utility Provided also that the CTU shall be entitled to reimbursement of reasonable costs incurred by it in collecting the transmission charges 3. The fees and charges for RLDCs (including the charges for Unified Load Despatch Scheme) and SLDCs shall be payable by the long-term customer and medium-term customer directly to the RLDCs or the SLDCs concerned.

Conditions of LTA & MTOA Unscheduled Inter-change (UI) Charges Scheduling of all transactions pursuant to grant of long-term access and medium-term open access shall be carried out on day-ahead basis in accordance with the Grid Code. Based on net metering on the periphery of each regional entity, composite accounts for Unscheduled Interchanges shall be issued for each regional entity on a weekly cycle. The State utility designated for the purpose of collection or disbursement of the Unscheduled Interchanges charges from or to the intra- State entities shall be responsible for timely payment of the State’s composite dues to the regional Unscheduled Interchanges Pool Account Fund.

Conditions of LTA & MTOA Any mismatch between the actual drawal and schedule for the intra- State entities shall be determined by the concerned State Load Despatch Centre and covered in the intra-State Unscheduled Interchanges accounting scheme. Unless specified otherwise by the State Commission concerned, the Unscheduled Interchanges rate for intra-State entity shall be 105% (for overdrawals or under generation) and 95% (for under-drawals or over generation) of the Unscheduled Interchanges rate at the periphery of regional entity. Transmission Losses The buyers of electricity shall bear apportioned losses in the transmission system as estimated by the Regional Power Committee. Redressal Mechanism All disputes arising out of or under these regulations shall be decided by the Commission on an application made in this behalf by the person aggrieved.

PROCEDURES MTOA

PROCESSING TIMEFRAMES

MTOA PROCEDURES Nodal agency : CTU earlier than 5 months and later than 1 year from the last day of the month in which application has been made MTOA  > 3 mo & < 3yrs with exception cl. For delay in CTU construction MTOANo augmentation of transmission system is envisaged & Construction of dedicated transmission line shall not be construed as augmentation of the transmission system. A power transaction involving combination of both multiple injections and one drawl point in case the MTOA is sought by a single bulk consumer shall not require filing of separate applications. Eligibility for MTOAgenerating station/captive generating plant/ consumer/Electricity Trader/distribution licensee/State Government owning some quantum of power (like free power given to the State Government in which the hydro station is located, equity power given to a State for allowing a power station to be set up in the State), who desires to utilize ISTS for Inter state transfer of power, provided the power station from which the power is being sourced or the load, as the case may be, is already connected to the grid, whether the State grid or the inter-State grid, or is likely to get connected to the grid before the intended start date of MTOA Documentary evidences

MTOA PROCEDURES No application for medium-term open access without applying for connectivity(if not connected) Whether connectivity reqd. in case embedded in a control area? Correctness of Application info to affirmed vied affidavit MTOA-I Application  MTOA-II with SLDC clearances SLDC clearances  MTOA-III within 10days or reasons for refusal Application fees:

MTOA PROCEDURES MTOA timelines: All apps. In a month construed to have come together on last day of month(M0) Approval on FCFS basis CTU studies & circulation to SLDC/RLDCs 15th of M1 Calculation methodology for TTC , RM Comments on studies upto 25th of M1 Provisional decision to grant MTOA  10th of M3 Within a month, priority more for those seeking MTOA for longer duration CTU shall notify the following on 31st day of March of each year: Total Transfer Capability (TTC) for 4 (four) years. This may be revised by CTU due to change in anticipated network topology or change of anticipated generation or load at any of the nodes, giving reasons for such change. Transmission Reliability Margin considered along with basis. Available Transfer Capability (ATC) for MTOA will be worked out after allowing the already approved applications for Long-term access, Medium Term Open Access and Transmission reliability margin. The grant of MTOA shall be subject to ATC as per MTOA-IV Sharing of transmission charges agreement  MTOA-V-30days BG for 2 months transmission charges – 30days bi-annual review Informtion to RLDC/SLDCs Tripartite agreement for other ISTS licensee No over-riding preference for previous holder

MTOA SCHEDULING Priority Underutilization of corridor If request for scheduling is consistently (for more than 5 days) lower than the capacity granted by the Nodal Agency (i.e.; CTU), RLDC may issue a notice to such MTOA customer asking the reasons for such under-utilization. The MTOA customer shall furnish the reasons for such under-utilization and will provide such details like the reduced requirement, likely period, etc. by the following day. The un-utilized transfer capability will then be released for scheduling of Short-term open access transaction. No refund of transmission charges shall be made due to above curtailment Transmission charges as per Terms & conditions of Tariff-9-14 Billing/collection & disbursement by CTU & administrative charge payable STU charges as per SERC norms Irrevocable revolving LC for 105% of average monthly charges 15 days before MTOA commencement BG of 2mo also to be concurrently < 3mo prior to scheduled commencement date and > 1mo after expiry of MTOA period RLDC/ULDC fees & charges payable to RLDC BG encashed in case of default & to be recouped Downsizing of application BG adjusted after expiry of MTOA period

MTOA EXIT/DOWNSIZING At least 30 days notice Exit charges  minimum of [30 days of period of relinquishment] Exit charges used for reducing transmission charges payable by other long-term customers and medium-term customers in the year in which such compensation payment is due in the ratio of transmission charges payable for that year by such long term customers and medium-term For upward revision fresh application