City of Orinda 2017 Annual and Measure J &L Pavement Rehabilitation Projects City Projects No. 4114 & 4115
2017 Orinda Paving Project Measure J & L Repairs – approximately $8.5M Residential Streets are funded by City’s 2014 Measure J Funds ($20 million general obligation bond) & 2012 Measure L ½ cent sale tax increase that provides approximately $1 million each year Annual Pavement Repairs – approximately $1M Work on Collector & Arterial Streets are funded by Gas Tax and Countywide Transportation Sales Tax Return-to- Source (RTS) funds Streets selected through City’s Pavement Management Program and recommended for construction by the Citizen’s Infrastructure Oversight Commission and approved by the City Council
2017 Orinda Paving Project 88 48
2017 Orinda Paving Project 65 Streets all over the City Split into 5 Packages Work includes: Drainage improvements – ditches, inlet & pipe work Full Depth Reclamation of Roadways (FDR) New Pavement Construction Re-installation of Pavement Delineation Preliminary Utility Relocations, prior to FDR Work Home Owner Responsibilities Prior to Construction: Verification of Sewer Lateral – Notices Sent Check / Clean Drainage Systems Trim Vegetation back from edge of roadway Only a rough schedule is known at this time Two more years of Roadway Improvements scheduled for the summers of 2018 & 2019 Maps are available
2017 Orinda Paving Project Drainage Improvements will be performed first Work will follow a geographical order Work Includes Full and Partial Replacement of: Storm Drain Pipes Concrete Curbs & Lined Ditches Asphalt Dikes & Curbs
2017 Orinda Paving Project What is Full Depth Reclamation? 2 Week Notice Posted and a 3-day Notice by a Door Hanger Complete Drainage Improvements and any Utility Relocations first Pulverize existing roadway to a 12- inch depth, half the roadway width at a time to maintain access Remove approximately 3-inches of pulverized material Treat with cement, add water & mix Grade and compact Cure for 3-7 days with temporary driveway ramps in place 3-inch of AC Paving to complete VIDEO NEXT SLIDE
2017 Orinda Paving Project Schedule – when will the work take place on my street? Current tentative schedule will be to start in Package 4 & 5, provided PG&E work meets their current schedule Most traffic in these areas Miner Road Closure Then move to Packages 1 through 3 Generic Schedule Information: April/May/June: start-up, pothole utilities, survey May/June/July: drainage improvements June/July: FDR work for Package 4 July/Aug: FDR work for Package 5 Aug/Sept: FDR work for Package 3 Sept/Oct: FDR work for Package 2 Oct/Nov: FDR work for Package 1
Why Replace My Lateral? Root intrusion can quickly clog your sewer. Sags allow grease & debris to settle & accumulate forming a blockage. Most homeowners insurance plans don’t cover the costs of a sewer backup. Not sure if you have a problem… - Get a video inspection of your lateral.
Side Sewer Replacement Call multiple plumbing contractors for quotes. Get a permit from Central San.
2017 Orinda Paving Project Who should I contact if I have questions? Steve Patterson at 510-701-0319 or spatterson@park-eng.com Farah Khorashadi at 925-253-4282 or fkhorashadi@cityoforinda.org Schedule updates will be available on the City’s Webpage: www.cityoforinda.org We will also use Next Door for neighborhood notifications