Preparing your transport programmes for the next NLTP

Slides:



Advertisements
Similar presentations
Examples of good practice. Examples of Good Practice Use of external UK and/or international external organisations as non-funded partners (target country.
Advertisements

PQF Induction: Small group delivery or 1-1 session.
Service Definer Roles NHS e-Referral Service
HRB Webinar Health Research Awards Content Objective of the call Scope and Panels Principal Investigator Response to peer-reviewers (rebuttal) Some.
Making Strategic Transport Infrastructure Planning and Investment Real in the Regions SUBTITLE HERE PRESENTER’S NAME (TITLE OR DIVISION)
Westminster City Council and Westminster Primary Care Trust Voluntary Sector Funding 2009/10 Voluntary Sector Funding Eligibility, Application Form Funding,
The Education Adjustment Program Profile – Revised.
1 Expressions of Interest Workshop Michelle Targett ERDF Priority Axis 2 Manager ERDF TEAM.
Community Services Programme Strand 1 & 3 Business Planning Re-contracting April 2014.
IN YEAR MONITORING & BUDGET PREPARATION WORKSHOP PREPARED BY BUDGET OFFICE MAY
Mid Wales LTP Stakeholder Workshop 3 rd October Presentation by Ann Elias and Janice Hughes.
OCNLR arrangements for final external moderation and the AVA awards board Summer 2010.
UK Wide Core Skills & Training Framework Findings of 2 nd Stage Consultation and Implications for Development of the Framework.
Community Response Fund Community Response Fund Overview of Application Process.
STEWARDSHIP OF OUR ROADS Regional Presentation - Auckland 22 July 2014.
For Corporate and Regional Office sites Guidelines for Developing a Simplified Purchase Recommendation.
SIF II Briefing Session 21 st September Briefing Session Content SIF Cycle I – overview Funding and arising issues SIF Cycle II – Process for evaluation.
Rural & Regional Water Business Expenditure Review Briefing for Businesses 4 October 2005.
July/August 2014 How the ONRC links with… Lynley Hutton.
A project funded by the European UnionImplemented by a consortium led by Get ready for the call! Next steps for building partnerships and developing a.
2018/21 NLTP - Improvements Extremely brief opening on what TIO is and does Looking to improve customer satisfaction by 10%
Small Charities Challenge Fund (SCCF) Guidance Webinar
Low Cost/Low Risk Improvements
Community Services Programme Re-Contracting
Apprenticeship Funding
Data sharing practices in the region
Compatible with the latest browsers; Chrome, Safari, Firefox, Opera and Internet Explorer 9 and above.
York, North Yorkshire & East Riding Local Enterprise Partnership Bio-economy Growth Fund Application process September 2016.
Maintenance BC - NZTA assessment in TIO
Continuous programmes
RST Coaching Services Community Sport and Coaching Conference
New Zealand Disability Strategy
Investment Logic Mapping – An Evaluative Tool with Zing
The Investment Assessment Framework
Demand Management Overview Title Slide
Prepared by Rand E Winters, Jr. ASR Senior Auditor October 2014
Presentation on the Application Process
Conducting the performance appraisal
Road Safety Promotion – detail for takeaway
Quality Workshop The Local Council Award Scheme is a great guide for good practice in our sector and a way for councils to build confidence in their.
Florida International University Student Government Association
9/16/2018 The ACT Government’s commitment to Performance and Accountability – the role of Evaluation Presentation to the Canberra Evaluation Forum Thursday,
Annual Assessment of Progress 2017/18 Briefing for Research Students Research Student Registry Mar/Apr 2018.
Conducting the performance appraisal
Small Charities Challenge Fund (SCCF) Guidance Webinar
WELCOME TO TETA SDF ROADSHOW FEBRUARY 2018.
Get ready for the new Grants Scheme! Click the picture to continue
Orders & Shipment Tracking
Improvements– detail for takeaway
Guidance notes for Project Manager
End of Year Performance Review Meetings and objective setting for 2018/19 This briefing pack is designed to be used by line managers to brief their teams.
Webinar: ESSA Improvement Planning Requirements
Our new quality framework and methodology:
MMU Project Management Community of Practice
Warfarin Prescribing.
CHIPS for schools NSW Education Complaint Handling Improvement Program
Safety Management System Implementation
Process Reforms for Session 1, 2018
What would improve the RAG status when amber or red
DSC Governance Sub Group Recommendations
Research funding application process
Scheme for Growth Pilot
Applying for Apprenticeships
[Group Name].
Expenditure Management
Wellcome Post-Award Webinar
Department of Higher Education and Training
Notes: Rapid assessments.
Co. Cork VEC 17th May 2011 (c)2011, Further Education Support Service.
World-Changing Glasgow Transformation Programme Board Summary
Presentation transcript:

Preparing your transport programmes for the next NLTP The RLTP/NLTP Preparing your transport programmes for the next NLTP Note that: LTMA hasn’t changed, so same process as last time Should be part way through a 6-year RLTP, so we would expect Transport Programmes to be building on this The “Transport Programme Development” user manual in TIO provides a good description of the process and what you do in TIO.

NLTP Objective Achieve best outcomes for NZ transport system: by optimising allocation of anticipated revenue to ensure value for money when investing in the transport system; through a collaborative process the Transport Agency will provide certainty for Investment Partner; within GPS activity class funding ranges set by the Minister; by following a cash-flow plan that recognises risk and NZTA’s debt limits. Published NLTP is a snap shot of a dynamic & continuous process. The Transport Agency work within boundaries, so have to focus spend on best VfM The Transport Agency needs good, evidence-based information to assess activities against these objectives. But we will also provide feedback and work with Investment Partners to help develop their Transport Programmes. The 2018-21 NLTP will be published July 2018, but it is recognised that it will evolve. Priorities change, new opportunities are identified. BUT same process applies regardless of whether activity is submitted for inclusion before or during the 2018-21 NLTP.

Timeframe for creating transport programme How to get from here to a Draft RLTP Now – end July Continuous Programme Templates launched Improvement Templates launched TIO migration Draft RLTPs Development of new TIO templates Improvement activities can continue to use old templates End July 2017 End July 2017 Only need to add missing information & submit to RTC Deadline for submission in TIO published by your RTC Can’t input Continuous Programmes until the templates are ready (but can still work on them). We will prioritise continuous programmes templates to make them available ASAP, but end of year processing will impact the exact date. Migration will allow Investment Partners to create Programme Business Cases and Improvement activities now. RTCs have to work back from the NLTP deadlines to set the RLTP dates (allowing for processing before presenting to the RTC for review and sign-off).

NLTP development process From RLTP to NLTP Review RLTPs Reviewed RLTPs Moderate NLTP Indicative Programmes Board adopts NLTP From late 2017 Review updated RLTPs & consult if required Must be revised by end April 2018 Quarter1 2018 Overlap with RLTP update Consider levels of funding in activity classes Mid-April 2018 Maximise allocation within GPS range(s) Special meeting June 2018 Draft RLTP deadline = organisations will be locked out of their Transport Programmes. Contact RTC to unlock. Currently part way through the 6 year RLTP, consultation on RLTPs will only be if there are significant changes. Transport Agency will take and file extracts from TIO at key points to record development of the Transport Programmes.

Key stages to getting funding The information required at each stage RLTP first – a requirement of the LTMA Continuous programmes – need to clear both gateways when NLTP is approved (Maintenance, PT services, Road safety promotion) Improvement activities – only need to clear the first gateway (results alignment crucial) Funding approvals process remains the same as do delegations – no short cuts Chart represents amount of information required at key stages. Continuous programmes will require the full amount of information. Please don’t place holder activities which don’t have their NZTA Assessment fields completed, e.g. resilience improvements. Only activities which can be properly assessed will be included in the NLTP. The automated snapshots are being developed for the Improvements template and will be available in TIO: At the first New Approval Every Cost-Scope adjustment > $1,000 (Total Cost – TBC ?)

10 Year forecast by activity class 2018-21 Halfway through 6 year RLTP, so update current forecast Actual expenditure/forecast for 2015-18 NLTP Existing forecasts from 2015-18 NLTP to be updated Updated forecasts from new programme activities Forecasts recognises that we are part way through a 6 year RLTP and will not extend beyond the current 10 year period. Hence will bring forward information from 2015-18 NLTP forecast to be reviewed and updated. First 3 years will reflect current expenditure and approvals (NB moving target, will update when ever the approved funds or programme forecasts update). Emergency works will pick up committed funding across the 10 years, no need to provide anything else. Continuous programmes (Maintenance, PT Services and Road Safety Promotion) will pick up the forecasts from these activities. Improvement activity forecasts will need to be reviewed and updated. NB Forecasts should reflect what is expected to be delivered, not the sum of the individual activities.

Getting activities into the NLTP Applications must be: Eligible, and Complete (green ticks) Extra help information has been added to TIO, see Refer to P&I Knowledge Base Checked by RTCs as part of RLTP test, with Transport Agency assistance BCR not required for improvements at this point – defaults to 1* rating Activities will be included as “Probable” or “Proposed” Probable: Funding has not yet been approved for the activity but, based on its profile and the robust evidence provided in developing the NLTP, funding approval is likely for an application made during the NLTP. Proposed: Based on its profile and the evidence provided in developing the NLTP, funding approval may be given when an application is during the NLTP. However, further evidence is required to confirm the assessment profile and provide confidence in the funding priority. For either funding priority, funding approval is subject to funds being available.

Funding approval Applications must: Be complete – all required TIO fields, including cost benefit appraisal Have required supporting information to appropriate standard Follow through the Transport Agency’s approvals process with approvals made under the delegations policy Since continuous programmes get funding approval at the start of the NLTP: there is a more detailed focus on assessment indicative allocations will optimise use of GPS funding, but may not fund requested allocation FARs recalculated for the 2018-21 NLTP using latest data Approved Organisations with changes will already have been informed Delegations Board approve Continuous Programmes mapping to new Transport Agency structure TBD GPS ranges limit how much we can allocate/approve, especially for Continuous Programmes. Any changes to transition or final Normal FARs will have already been communicated to the relevant Approved Organisations

All investment decisions Must be the result of applying the NZTA’s Assessment Framework Must be based on the evidence provided in TIO or as supporting (electronic) hard copy Must reflect the national view and will be based on objective assessments

Current Initiatives What MUST be completed this NLTP Enhanced FARs for accelerated LED activities 85% average FAR only available for the 2015-18 NLTP funds carried over will get Approved Organisation’s Normal FAR R-funds assigned to activities and get funding approval before 30 June 2018 future activities will use the “Regional Improvements” activity class Urban Cycleway Fund Crown funds MUST be claimed by end of the 2015-18 NLTP Claim Crown funds BEFORE NLTF funds LED: Note that the enhanced FAR is 85% across the 3-year programme, so can get higher FAR if work carried out during 2015/16 and claimed at Normal FAR. Also note the paragraph on completion by December 2018 in the general circular referring to pre-purchased luminaires. Any luminaires purchased using the enhanced FAR (i.e. by 30 June 2018) must be installed by 31 December 2018. UCF: Minister has agreed Crown funds can be claimed before NLTF claims. Please adjust cost profile to reflect this as it will help us approve requests for funding non-UCP walking & Cycling activities.

Use of TIO extract TIO extract under MORE tab Process: How to review your transport programme TIO extract under MORE tab Process: Select activities & status (when in doubt select all) Extract info from TIO to spreadsheet (available) Use PIVOT tables to select & summarise data

Summary and Help TIO Problems – use “Contact Us” in TIO Planning & Investment Knowledge Base – email heather.benwood@nzta.govt.nz douglas.robertson@nzta.govt.nz IAF help – IAF page on the NZTA website BCA online training