CRAIOVA INTERNATIONAL AIRPORT AEROPORTUL INTERNATIONAL CRAIOVA
THE REHABILITATION OF THE MOVEMENT INFRASTRUCTURE 7 km distance from the Craiova city center Regional impact – the only airport in the southwestern part of Romania, northwestern part of Bulgaria and southeastern part of Serbia and Montenegro 3.500.000 people served AEROPORTUL INTERNATIONAL CRAIOVA
AIMS COMMERCIALS - NEW AIR OPERATORS - NEW ROUTES - INCREASED NUMBER OF PASSENGERS CLOSING NONCONFORMITIES - RELATED TO ICAO ANNEX14/RACR-AD-PETA EASA REGULATIONS REQUIREMENTS - COMPLIANCE
CHALLENGES LARGE VOLUME OF WORK MANDATORY DEADLINES TIMELY IMPLEMENTED CORRECTIVE ACTIONS CERTIFICATION BASIS (TARGETED)
THE REHABILITATION OF CRAIOVA AIRPORT’S MOVEMENT INFRASTRUCTRE Project funded by FEDR, GOV and Beneficiary Funds Project details 1.1. The denomination of the investitions’ objective that represented the financing aplication’s aim. TP development, technical assistance from the designer and execution of the works for the rehabilitation of Craiova Airport’s movement infrastructure 1.2. The investition’s holder R.A. CRAIOVA AIRPORT 1.3. The investition’s beneficiary 1.4. Entrepreneur AZVI S.A. 1.5. Supervision consultant Association S.C. CONSITRANS S.R.L. S.C. PRIMACONS GROUP S.R.L. 1.6.The project’s developer (main designer) 3TI PROGETTI S.p. A. AEROPORTUL INTERNATIONAL CRAIOVA
The state of the works’ contract On June 10 2015, Craiova Airport Autonomous Administration signed the public auction contract no. 3050/10.06.2015, for „Technical Project elaboration, technical assistance from the designer and works execution for the rehabilitation of the movement infrastructure of Craiova Airport”, with AZVI S.A. as entrepreneur. The total value of the project is 50.627.052,47 RON, at which is added the VAT value of 12.150.492,59 RON The construction authorization no. 21/06.08.2015, was issued by Dolj City Council for the execution of the construction works. On 19.10.2015, with the letter no. OUT221/19.10.2015, the entreprenour submitted the engineer and the beneficiary a copy of the principle notice, issued by the Romanian CAA, no. 27924/27881/26179/110 SI from 16.10.2015, for the rehabilitation of the movement infrastructure of Craiova Airport, in stages. AEROPORTUL INTERNATIONAL CRAIOVA
REHABILITATION OF MOVEMENT AREA INFRASTRUCTURE AEROPORTUL INTERNATIONAL CRAIOVA
REHABILITATION OF MOVEMENT AREA INFRASTRUCTURE CRAIOVA AIRPORT PROJECT THE PROJECT HAD OBJECTIVE THE EXECUTION OF THE WORKS IN 2 STAGES STAGE I: RWY REHABILITATION WORK( REPAIRS AND REINFORCEMENT FOR INCREASED PAVEMENT STRENGHT) RWY REHABILITATION WORK AND EXTENSION BRAVO TWY C CODE RWY REHABILITATION WORK AND EXTENSION OF AIRPORT APRON STAGE II: MARKINGS LIGHTING SYSTEM ELECTRICAL SYSTEM AND APRON FLOOD LIGHTS AEROPORTUL INTERNATIONAL CRAIOVA
Safety of Runway Operations During Construction Works The execution of the project performed only by authorized civil aeronautical agents Work activity was made only under Craiova Airport and ROMATSA coordination – for assuring the necessary conditions for SAFETY Issuing NOTAM for closing the movement area due to work in progress Issuing NOTAM for the resulted changes following the outgoing works The implementation of the management plan of risk mitigation by works under air traffic Assessment of movement area operation ( Runway 09/27, Bravo TWY, Apron) AEROPORTUL INTERNATIONAL CRAIOVA
REHABILITATION OF MOVEMENT AREA INFRASTRUCTURE RUNWAY REINFORCEMENT: 3 NEW LAYERS OVERLAY OF EXISTING SURFACE - 18 cm asphalt mixtures SURFACE PREPARATION USING STRESS RELIEF TECHNIQUE OF RUNWAY RIGID PAVEMENT: "Crack and Seat" "Rubblization" RUNWAY STRIP (RWY 09/27) 2620 X 300 M CONNECTED TO THE NEW RUNWAY ELEVATION CS.ADR-DSN. B. 155 LENGTH OF CS.ADR-DSN. B. 160 WIDTH OF AEROPORTUL INTERNATIONAL CRAIOVA
REHABILITATION OF MOVEMENT AREA INFRASTRUCTURE BRAVO TWY BEFORE WIDTH 15 M SURFACE – IRREGULARITIES, DEFORMATION, CRACKS SLOPES NONCOMPLIANCE AFTER WIDTH 25 M, INCLUDING SHOULDERS (18 M + 3,5 M + 3,5 M) REFERENCE CODE 4C. TWY REINFORCEMENT 18 CM OF OVERLAY LAYERS OF ASPHALTIC MIXTURE CS ADR-DSN.D.245 WIDTH OF TAXIWAYS AND GM1 ADR-DSN.D.245 WIDTH OF TAXIWAYS COMPLIANCE. AEROPORTUL INTERNATIONAL CRAIOVA
REHABILITATION OF MOVEMENT AREA INFRASTRUCTURE APRON EXTENSION 4 AIRCRFT STANDS CODE 3C, SIMULTANEOUS PARKING 2 AIRCRAFT STANDS FOR ALTERNATIVE PARKING 4C PCN 52/R/D/W/T BEARING CAPACITY : 31cm CONCRETE BcR5 polyethylene foil 313 g/mp 15 cm stabilized aggregate layers with cement 40 cm rocks ballast layer Separation layer of geotextile DIMENSIONS: 65.00 m x 227.00 m TOTAL AREA 24.000 mp EASA COMPLIANCE: CS ADR-DSN.E.355 STRENGTH OF APRONS . AEROPORTUL INTERNATIONAL CRAIOVA
EASA REGULATION COMPLIANCE CS ADR-DSN.B.060 Longitudinal slopes of runways & GM1 ADR-DSN.B.060 Longitudinal slopes on runways CS ADR-DSN.B.080 Transverse slopes on runways & GM1 ADR-DSN.B.080 Transverse slopes on runways CS ADR-DSN.E.360 Slopes on aprons & GM1 ADR-DSN.E.360 Slopes on aprons CS ADR-DSN.D.270 Longitudinal slope changes on taxiways & GM1 ADR-DSN.D.270 Longitudinal slope changes on taxiways CS ADR-DSN.D.265 Longitudinal slopes on taxiways & GM1 ADR-DSN.D.265 Longitudinal slopes on taxiways CS ADR-DSN.D.280 Transverse slopes on taxiways & GM1 ADR-DSN.D.280 Transverse slopes on taxiways AEROPORTUL INTERNATIONAL CRAIOVA
MARKINGS MARKINGS: RWY BRAVO TWY APRON and TAXILANE EASA COMPLIANCE: CHAPTER L — VISUAL AIDS FOR NAVIGATION (MARKINGS) CHAPTER R — VISUAL AIDS FOR DENOTING RESTRICTED USE AREAS AEROPORTUL INTERNATIONAL CRAIOVA
LIGHTS LIGHTS: - RWY - BRAVO TWY - APRON ALS - RWY 27 - CAT II/III - RWY 09 - SIMPLE APPROACH LIGHTING SYSTEM APRON - LIGHTING SYSTEM EQUIPPED WITH SPOTLIGHTS ON POLES, 4 PILLARS 20 m AND 1 PILLAR 16 m ELECTRICAL POWER SOURCE FOR THE LIGHTING SYSTEM EASA COMPLIANCE CHAPTER M — VISUAL AIDS FOR NAVIGATION (LIGHTS) AEROPORTUL INTERNATIONAL CRAIOVA
OPERATIONAL PAPI FOR - RWY 09 - RWY 27 CARGO HANGAR FUTURE OBJECTIVES ILS CAT II TURN PADS OPERATIONAL PAPI FOR - RWY 09 - RWY 27 CARGO HANGAR AEROPORTUL INTERNATIONAL CRAIOVA
AERODROME STATUS FULLY OPERATIONAL AERODROME CERTIFICATE AP 09/2014 CONVERSION OF CERTIFICATE WILL START IN THE LAST WEEK OF SEPTEMBER 2016 AEROPORTUL INTERNATIONAL CRAIOVA
PREPARATION FOR CONVERSION OF CERTIFICATE APPLICABLE CS NO ELOS OR AND OPS REQUIREMENTS COMPLIANCE PREPARATION OF THE APPLICATION AND PROOFS AEROPORTUL INTERNATIONAL CRAIOVA
TO DO LIST SAFETY AREAS IMPROVEMENT LVP for ILS CAT II UPDATE OF FLIGHT PROCEDURES AEROPORTUL INTERNATIONAL CRAIOVA