INSTALLATION OF STANDBY GENERATORS PRESENTATION TO PORTFOLIO COMMITTEE ON POLICE DATE: 19 AUGUST 2015.

Slides:



Advertisements
Similar presentations
BUCKET ERADICATION PROGRESS SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS HEARINGS 22 & 23 February 2007 Presented by Ms. T. Mpotulo Department of.
Advertisements

PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
DPW ENERGY EFFICIENCY PROGRAMME BRIEFING THE PORTFOLIO COMMITTEE ON ENERGY – 31 JANUARY 2013.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON POLICE 14 August 2012.
Periodical Purchasing Julie V. Rivera. Brownsville ISD Procurement Guidelines Following established policies and administrative guidelines, the following.
PERFORMANCE AUDIT REPORT ON MANAGEMENT OF PRIMARY HEALTH CARE (A CASE STUDY ON HEALTH CENTERS) 8/16/20151 Dr. Anna Nswilla CDHSMoHSW.
DPW ENERGY EFFICIENCY PROGRAMME SELECT COMMITTEE ECONOMIC DEVELOPMENT.
ANALYSIS OF THE NCERA FARMS INVESTIGATION REPORT AND RECOMMENDATIONS TO THE PORTFOLIO COMMITTEE 1.PURPOSE T O INFORM THE PORTFOLIO COMMITTEE ON THE STEPS.
STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February Briefing by Department of Water Affairs.
Department of Arts and Culture Presentation to the Select Committee on Appropriations: 08 May 2013 Community Library Services Grant Mr Sibusiso Xaba Director.
1 Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 18 August 2010.
1 DPW Presentation to the Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 24 November 2010.
Limpopo - Health1 Report to the Select Committee on Finance on the Provincial Budgets and Expenditure Review 2001/ /08 and Conditional Grants and.
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
NATIONAL RECTIFICATION PROGRAMME SELECT COMMITTEE ON APPROPRIATIONS 11 SEPTEMBER 2012 NATIONAL RECTIFICATION PROGRAMME SELECT COMMITTEE ON APPROPRIATIONS.
Presentation to Portfolio Committee on Police on SAPS Communication Projects By: Mr Sithembiso Freeman Nomvalo
Criminal Justice System Modernization Project: DPW’s Infrastructure Projects 24 June
Click to edit Master subtitle style 2/16/12 LEASE MANAGEMENT 2011/12 Financial year PRESENTATION TO THE PORTFOLIO COMMITTEE ON POLICE
Province of the EASTERN CAPE DEPARTMENT OF PUBLIC WORKS DOH REVITALISATION PROGRAM EASTERN CAPE PROVINCE PRESENTATION TO SELECT COMMITTEE ON APPROPRIATIONS.
DEPARTMENT OF EDUCATION EDUCATION INFRASTRUCTURE PROGRAMME OF ACTION Portfolio Committee Presentation Cape Town 15 February 2005.
Integrated National Electrification Programme (INEP): Overall Performance (End of January 2012) Dr Wolsey Barnard.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
DPW PRESENTATION TO PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES 09 FEBRUARY 2010.
Hospital Revitalisation Joint Budget Committee 23 May 2005.
Joint Report to Select Committee on Appropriations by Northern Cape Department of Health Northern Cape Department of Roads & Public Works supported by.
NATIONAL DEPARTMENT OF HEALTH National Health Insurance Grant Select Committee on Appropriations Hearing on 3 rd and 4 th Quarter Expenditure 4 th June.
In September of 2012 the RA Government made amendments in the Resolution No 168 on ‘Regulation of Procurement Procedures". 1. It is the responsibility.
DEPARTMENT OF PUBLIC WORKS Presentation to Portfolio Committee on SAPS PROVISION OF INFRASTRUCTURE AT LEBOMBO LAND PORT OF ENTRY 17 June
DEPARTMENT OF HEALTH SEPTEMBER 2012 Briefing of the Portfolio Committee on Health by MEC For Health and Social Development the state of readiness for implementing.
Cidb Presentation for 1 st and 2 nd quarter Performance Reporting 2010/11 Portfolio Committee on Public Works 8 November 2011 development through partnership.
Morelli Park Reconstruction and Expansion Project Public Hearing and Award of Construction Contract Stockton City Council and Stockton Redevelopment Agency.
MENTAL HEALTH CLINIC Siting Process and Analysis.
1 Standards and Construction Specifications Manual Orange County Utilities February 13, 2007.
DEPARTMENT OF EDUCATION NORTH WEST
OVERVIEW OF DEPARTMENT OF ARTS AND CULTURE SERVICES INFRASTRUCTURE PORTFOLIO DATE: 06 SEPTEMBER 2016.
Presentation to the Portfolio Committee 25 MAY 2011
INFRASTRUCTURE PROGRAMME FOR DCS PRESENTATION TO PORTFOLIO COMMITTEE ON JUSTICE AND CORRECTIONAL SERVICES DATE: 04 AUGUST 2015.
E305, 3rd Floor New Wing, Parliament
Eastern Cape :2016/17 Stopping Considerations
PRESENTATION TO PORTFOLIO COMMITTEE ON PUBLIC WORKS Medium Term Budget Policy Statement 9 November 2005.
REPORT ON MATTERS IDENTIFIED BY THE COMMITTEE
Portfolio Committee- Trade and Industry – 11 March 2015
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
PRESENTATION TO PORTFOLIO COMMITTEE AG REPORT ON CONSULTANTS
PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE
PORTFOLIO COMMITTE PRESENTATION
PROGRESS REPORT ON IMPLEMENTATION OF THE PUBLIC FINANCE MANAGEMENT ACT
North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 June 2008.
PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC AND BUSINESS DEVELOPMENT ANNUAL PERFORMANCE REPORT OF THE COMPENSATION FUND FOR THE FINANCIAL YEAR
Gauteng Department of Health
South Africa Works because of Public Works
Mr Ntandazo Vimba and Henri Marais
SELECT COMMITTEE ON PUBLIC SERVICE: REPORT ON QUALITY SANITATION TO HOUSEHOLDS PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP)
Completion Report Summary
Introduction DEFINATION :-
WASTEWATER MANAGEMENT 19 September 2018
PRESENTATION ON THE FINANCIAL MANAGEMENT INFORMATION 3rd QUARTER IRO 2007/ FEBRUARY 2008.
Portfolio Committee Presentation DCS and NDPW Facilities
South Africa Works because of Public Works
BLOEMFONTEIN SANDF: TEMPE MILITARY BASE: 3 MILITARY HOSPITAL: INFRASTRUCTURE REFURBISHMENT AND MAINTENANCE CHALLENGES Date: SEPTEMBER 2018 BRANCH HEAD:
Sport and Recreation Infrastructure Programme
24 JANUARY 2019 NORTHERN CAPE PROVINCE
DEPARTMENT OF EDUCATION NORTH WEST MID-TERM PROVINCIAL BUDGET REPORT
PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL.
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 13 MARCH 2019
National Department of Public Works Immovable Asset Management
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
HOSPITAL REVITALISATION PROJECTS REPORT TO THE SELECT COMMITTEE ON APPROPRIATIONS AUGUST 2012 Northern Cape Department of Health & Department of Roads.
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
IYM PRESENTATION UP TO 31 DECEMBER 2011 PRESENTATION 24 April 2012
Presentation transcript:

INSTALLATION OF STANDBY GENERATORS PRESENTATION TO PORTFOLIO COMMITTEE ON POLICE DATE: 19 AUGUST 2015

CONTENT PURPOSE BACKGROUND FINANCIAL IMPLICATION PROJECTS STATUS SUMMARY REPORT PER PROJECTS CHALLENGES INTERVETIONS UNDERTAKEN CONCLUSION

1. PURPOSE To appraise the Portfolio Committee on Police about progress made by the Department of Public Works (DPW) with regard to installation of standby power generators in various SAPS facilities including Police Stations across the country.

3. BACKGROUND SAPS submitted funded list of projects to DPW to install emergency power generators in May 2014. Upon receipt of the list, the department subjected the request to the following processes: Site clearance processes (to comply with the National Environment Management Act) Appointment of professionals to conduct site inspections and develop designs. This includes an electrical power needs assessment for the process and the facilities involved. This process also determines the electrical loads required by any essential supporting services for effective operation. Compliance with requirements of the local authority to be determined before design i.e. noise limitations, sans requirements, etc.

3. BACKGROUND Standby Generator installation is designed to ensure that the following minimum areas are catered for in line with SAPS requirements : • Control room • Charge office/CSC • Office of the Station Commander • Certain limited demand kitchen equipment • Armouring Security • Access gate for public • Security perimeter lighting • SAPS Blue light • Cell Blocks

3. BACKGROUND There are also installations of standby power generators that are attached or coupled to installation of water tanks, sewer treatment plant and storm water drainage system as one service for some facilities in order to improve service to the user client and public. After the design process, the department resumed a process to source contractors to execute projects. This includes purchasing and installation of generator sets (wiring of engine and control panel). Lastly the department had to ensure compliance with Occupational Health and Safety Act (OHSA) during installation and operation of the units

4. FINANCIAL IMPLICATION Budget allocated for installation of standby power generators in the current financial is R23,161,338.00 (Contractors = R21,792,616.00 and Professional Fees = R1,368,722.00) Expenditure as at end of July 2015 was R171,785.00, representing fees paid to consultants.

5. PROJECTS STATUS Item Stage Description Number of projects 1 Projects on Design stage (4)   8 2 Projects on Design and estimate approved stage (4A) 5 3 Projects on Tender stage (4B) 9 4 Projects on Tender Adjudication Stage(5) Projects on Tender Award Stage (5A) 6 Projects on Construction Stage (5B)

6. PROJECT DESCRIPTION Western Cape: No. DESCRIPTION 1. Western Cape: Installation of generator sets at non-devolved facilities. (24 Sites that include fully fledged and satellites police stations) 2 KZN: Installation of generator set at various police stations (23 Allocated but three were removed due to ongoing construction. (22 Sites that include fully fledged and satellites police stations). Colenso; Melmoth and Cato Manor were removed 3 NW: installation of generator sets at non-devolved police stations: Cyferskuil, Huhudi, Mothutlung, Dinokana satellite, Tigane satellite and Tshing detectives services 4 NC: installation of generator sets at police stations: Kakamas, Kenhardt, Marydale and Van Wyksvlei 5 installation of generator sets at police stations : Deben, Danielskuil, Dingleton, Postmasburg and Wrenchville 6 installation of generator sets at police stations: Douglas, Griekwastad, Hopetown, Jan Kempdorp, Moderivier, Pampierstad , Warrenton and Koopmansfontein 7 MP installation of generator sets at Colesburg, Sunrise, Petrusville, Nonzwakazi, Vosburg and Calvinia 8 Nelspruit: installation of a generator set at various police stations 9 Phalaborwa: upgrading of existing generator set

6. PROJECT DESCRIPTION No. DESCRIPTION 10 installation of generator set at non-devolved police station: Sekhukhune 11 Installation of generator set at non-devolved police station: Siloam 12 Upgrading of generator set at non-devolved: Seshego 13 Installation of generator set at non-devolved: Musowdi 14 supply, delivery and complete installation of generator set: Gonubie, East London 15 Port Elizabeth: Various Areas installation of generator set at various police stations (11 sites) 16 Pretoria: repairs and renovations including cell block & generator 17 Pretoria: placement of generator and upgrading of power 18 Bizana Police Station: installation of water tanks and a generator set 19 EC: installation of water tanks, generator set and a sewerage treatment plant 20 21 EC: installation of new generator set, connection of water to offices and residences and repairing of borehole 22 EC: installation of water tanks, generator set, sewer treatment plant and storm water drainage system 23 EC: drilling and testing for water, installation of septic tank, two standby generators 24 EC: installation of septic tank and repairs & renovations of the burnt generator room 25 EC: installation of water tanks, generator set and upgrade of existing sewer system 26 27 28 Ntabankulu PS: installation of borehole pump; upgrading of generator set; connection of conservancy tanks to sewer ponds

7. CHALLENGES The following challenges led to delays in the implementation of the programme: Assessments of facilities listed took longer than anticipated due geographical location of sites (scattered). Another delaying factor is that some of the consultants nominated were declining appointment and the process had to be re-done. New instructions had to be issued out after failure to attract responsive bids due to the magnitude and geographical location of sites to be serviced.

8. INTERVENTIONS UNDERTAKEN The following interventions have been devised to address challenges in implementation of the programme: Appointments of consultants is done per location and assessments of facilities are fast tracked to reduce turnaround time for planning.  Projects have all been unbundled in order to attract responsive bids and procurement process will be fast tracked.

9. CONCLUSION The department acknowledges delays experienced in implementing these projects due to design and industry response to bids. In line with implementing its Turn Around Plan the department has entered the efficiency enhancement phase, which focuses more on streamlining service delivery processes and work flow for greater responsiveness to client’s needs. This includes strengthening project management capabilities through establishment of Project Management Office (PMO) and utilization of Public Works entities. In line with the project execution actions outlined per project in the report the department projects to complete the installation of generators in all sites by end of the second quarter in the financial year 2016/17 in line with anticipated budget allocations from SAPS. The Ministerial Joint Task Team has been established to effect close monitoring of projects under implementation. The report is submitted to the Portfolio Committee on Police for consideration.

End of Presentation