Is Reactive Power Worth Anything?

Slides:



Advertisements
Similar presentations
T&D Losses Reflecting Losses in DR within ERCOT August 22, 2012.
Advertisements

Demand Resource Operable Capacity Analysis – Assumptions for FCA 5.
INSULATING PRICE RESPONSIVE LOAD FROM RUC CAPACITY SHORT CHARGE Mark W. Smith J. Kay Trostle August 2008 DSWG.
1 Generation Adequacy Task Force Report to TAC April 7, 2005.
A Partial Interim Report To WMS Guidance on Implementing Protocol Implementation Plan (PIP) 102 Reactive Power Task Force.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
Houston Area Dynamic Reactive Project March 11,
1 Non-Transmission Alternatives to Reduce Local Congestion Costs Bill Bojorquez June 3, 2004.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
April 15, TAC Report to the ERCOT Board April 15, 2003.
1 How does ERCOT Review, Verify and Approve RMR Costs? (In response to questions that were asked during PRR 632 discussions) Prepared for the
PRR835 – Reactive Power Capability Requirement
Is Reactive Power Worth Anything? The sun sets on a lightless New York City – August 14th Reactive & Voltage Maintenance Joint Proposal by TexGenCo/Calpine.
Distributed Generation Task Force November 29, 2007 TAC Report.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
ISO Comparison – CAISO Alex Lee (ERCOT)
ERCOT Wind Survey Leo Villanueva. Abilene Mc Camey Big Spring.
© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest.
RMR Task Force Decision Points for ERCOT Technical Advisory Committee April 3, 2003.
09/17/2006 Ken Donohoo ERCOT Peak Day August Initial Settlement Data by Fuel Type.
ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) August 8, 2012 PDCWG August 9, 2012 ETWG/QMWG.
Floyd Trefny, P.E. Director of Wholesale Market Design Nodal Market Tools to Manage Wind Generation January 29, 2009 Presentation to the Renewables Technology.
Report to TAC July In Brief Working Group Reports Working Group Reports CMWG CMWG DSWG DSWG MCWG MCWG MWG MWG QMWG QMWG VCWG VCWG Task Forces Task.
Demand Response Task Force. 2 2 Outline  Overview of ERCOT’s role in the CCET Pilot  Overview of Stakeholder Process – What’s been done to date?  Questions.
DSWG Update to WMS 12/2/2015. NPRR738 ERS Performance Calculations During TDSP Outages A utility outage can prevent ERS Generators from exporting to the.
Nodal Planning Model Process and Data Set A case use June 28, 2010 Planning Working Group.
October 13, 2009 NOIE DRG Settlements TF update to COPS Settlement Discussion for ALL DG < or = 1 MW Don Tucker on behalf of the NOIE DRG Settlements Task.
Overview of Governing Document for Weather-Sensitive ERS Pilot Project Stakeholder Workshop Mark Patterson, ERCOT Staff March 1, 2013.
1 New MO Projects June COMS Extract, Report & Web Services Monitoring & Usage Statistics Jackie Ashbaugh.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Verifiable Costs for Nodal WMS Meeting.
1 PRR #409 Voltage Support Service from Generating Resources Timeline Date Received 4/25/2003 Date Posted 4/28/2003 Comments Due 5/19/2003 PRS Review Date.
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
Overview of FIP Issues in the RUC, Verifiable Cost, and other Nodal Market Processes November 12, 2008 VCWG Meeting.
Reliability-Must-Run (RMR) Cost Evaluation and Settlement Basis Ino González ERCOT RMR Workshop May 24, 2016.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Abilene Mc Camey Big Spring. Far West Abilene Area All the values are based on returned ERCOT survey results Total number of Wind Powered Generation.
TAC Update Kyle Patrick. 2 Nodal ERCOT Program Update –Nodal Market Go-Live (Vote)- vote passed in which TAC certified full nodal systems for Dec 1, 2010.
Technical Advisory Committee Presentation to the ERCOT Board of Directors April 18, 2007.
Project WECC-0100 Standards Briefing WECC-0100 SDT April 7, 2016 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Commercial Operations Subcommittee (COPS) Update to TAC 4/28/2016
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Background / Introduction
Principal Load Profiling and Modeling
Distributed Generation Task Force
TAC Report to the ERCOT Board
Fuel Cost Components in the Fuel Adder
Barrilla Junction Area Transmission Improvements Project
TAC Report to the ERCOT Board
Nodal COMS Additional Items Update
Resource Cost Working Group
General Overview Of Resource Costs
ERCOT Pilot Project for Fast Responding Regulation Service (FRRS)
RTDF Overview of Data Analysis & Status of “Consesus Items”
Fuel Cost Components in the Fuel Adder
UFLS Workshop Discussion #3
RMR Update November 6, /05/2002.
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
Reactive Power Task Force
Reflecting Losses in DR within ERCOT August 22, 2012
Oncor Electric Delivery Company LLC
Updates to the Path Rating Process for Approval by the PCC
ECE 476 POWER SYSTEM ANALYSIS
ECEN 460 Power System Operation and Control
Project WECC-0100 Update Load Modeling Task Force
DEC System Voltage Planning - June 2018
ECEN 460 Power System Operation and Control
Project WECC-0100 Update Load Modeling Task Force
Presentation transcript:

Is Reactive Power Worth Anything? Reactive & Voltage Maintenance Joint Proposal by TexGenCo/Calpine Is Reactive Power Worth Anything? The sun sets on a lightless New York City – August 14th

GenReaTF Directive from WMS 1) Develop a method similar to the one found in the EPRI study that compensates for heating losses in generator equipment and GSU 2) Develop a method and Protocols language to pay for “as delivered” Mvarhs under PIP 102 for reactive beyond a machine’s URL 3) Determine if the trigger point for settlements of reactive power delivered can be different from what’s in the Interim Standard and if so, what should it be?

TF’s Areas of Focus “Heating Loss” type component, PIP 102 method for payment for Mvars beyond unit’s URL “Opportunity Cost” component (solved problem - OOM-E Down paid for reduction in MWs)

Key Issues That Lead to This Proposal The Task Force Learned the Following: 1) The number and complexity of facility metering scenarios are enormous making individual Mvar flow calculations impossible if gaming possibilities are to be avoided, 2) The calculations for equipment heating loss are very involved and the assumed variables are hard to defend or refute; subject to site-specific gaming opportunities 3) Voltage at the transmission injection point metering is the objective function in assigning criteria for reactive delivery; whatever method is used for compensation must be shaped by voltage maintenance performance

4) From anecdotal comments there appear to be significant inequities in some areas of ERCOT in the dispatch of Mvars and the alignment of a financial incentive with voltage support is needed to compensate the true providers and keep score so that “loafers” don’t go unnoticed.

Conceptual Layout of This Proposal ERCOT Summer Base Case 2004 15,954 MVars Needed from 399 Gens. turned on Each of the 527 units has a prorated 30 Mvar “compensation component” assigned. Next slide provides assumptions for this assignment. 527 total Units in case

Compensation Component (“CC”) Assumptions All units in base case have a “CC” whether turned on or not because of uncertainty between planning case and actual operations that can arise during peak season (unit outages of “turned on” units causing “turned off” units to operate, etc.) Units that go COD during the year and were not in the base case are not eligible for a “CC” assignment until subsequent year The base case provides the pool of dynamic Mvars that the system expects resources to provide at peak

Calculating Each Interval’s Possible Compensation Amount (based on given assumptions) $20/Kvar Installed Capital Cost assumed for a transmission level shunt device chosen as a ‘proxy device cost’ (as noted in PIP 102) 20 years term assumed for capital expense payout $1K/year assumed for 20 years as O&M costs for device 30 Mvar Compensation Component per Resource as per 2004 Base Case results ((30 Mvar * $20/Kvar) + $20K) / 35,040 intervals/year)) = $0.88 / 15 minute interval

Criteria for an Interval’s Payment Unit must be on line with AVR in Automatic (unless dispatched otherwise by ISO) Injection Point voltage must be within +- 2% of ERCOT-posted voltage profile value Payment amount is conditioned on whether Mvar flow is helping or hurting voltage relative to posted profile value

Dispatch Becomes Simpler Under this Proposal Entire range of machine’s reactive capability in lead and lag directions are available to the system with no additional payment calculated b) No payment necessary for dispatch beyond URL; URL is only used as a transmission planning and compliance threshold

The “D” Curve and the URL Area

Determining the URL The Resource owner should determine the machine’s URL The Resource owner would provide the “Area within the Unit’s URL” to the ISO for approval The ISO would advise the TDSPs of the current URLs for resources in their footprint

Helping or Hurting Voltage Harry Holloway of TexGenCo Voltage Maintenance Performance Spreadsheet

Compelling Features of this Proposal Bus voltage maintenance is the objective and the performance criteria in proposal aligns incentives with that, Per interval payment based on fixed base case value sets an annual cap of potential payments, Method is not complex with a minimum of variables for ISO to manage/collect from telemetry Full range of machine’s capability is available without additional payments Gaming opportunities are virtually nonexistent, Potential compensation is nominal compared to OOM-C and RMR payments with similar objectives

? Questions Issue to Consider for Motion/s: If this combined proposal is accepted as the direction WMS wants the TF to proceed, then the work on PIP 102 can be stopped.

These Guys Would Say……YES! The “Pucker Factor” sets in – Aug. 14th

Answers the TF Expects from WMS Does WMS approve of this joint proposal’s methodology in order that the TF can proceed to develop Protocol language around it? [Motion] (If YES, disregard Item #2) 2) If the answer to Item #1 is NO, then does WMS approve of the Protocol language proposed for PIP 102’s treatment of Mvars beyond the URL so that language can be crafted into a PRR for submission to PRS? [Motion] (If NO, then how does WMS want the TF to proceed? And who will the new Chair be? )