Barrilla Junction Area Transmission Improvements Project

Slides:



Advertisements
Similar presentations
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Advertisements

Jan 22, 2013 RPG Meeting Sharyland Atlas-Driver Load Integration Project – EIR update.
2004 Congestion Costs. 2 Transmission Congestion Occurs when analysis shows a given outage of a transmission element (contingency) will result in the.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Oncor Electric Delivery Company LLC TOGETHER WE DELIVER ODESSA UPDATE Jan 22, 2013 Presentation to ERCOT Regional Planning Group Austin, TX Mike Juricek.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Outage Coordination Overview D.W. Rickerson ERCOT Outage Supervisor 12/1/2008.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
TAC RELIABILITY AND OPERATIONS SUBCOMMITTEE CMWG/PLWG Planning Criteria Review/Update Report to WMS Austin, TX August 10, 2011 Kenneth A. Donohoo, P.E.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
March 2003 Operations Summary Bill Blevins Manager Operations Engineering.
Managing West Texas Wind SWEDE 2008 Conference May 2, 2008 Presented by Paul Hassink AEPSC Texas Transmission Planning.
2015 RTP – Study Scope of Short Circuit Analysis RPG Meeting May 19,
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
Page 1© 2009 Quanta Technology LLCPage 1 November 2007 BGE January 4, 2008 Strategic Midwest Area Renewable Transmission (SMART) Study October 06, 2009.
ERCOT PUBLIC 5/20/ RTP Inputs and Assumptions May 20, 2014.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
AEPSC Live Oak County Transmission Project – ERCOT Independent Review TAC September 24, 2015.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
Transmission Voltage Management Ross Owen Oncor Electric Delivery.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
ERCOT PUBLIC November RPG Meeting RTP – Study Scope November 20, 2015.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
ERCOT PUBLIC 3/25/ RTP Inputs and Assumptions March 25, 2014.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
Local Area Planning Update – TRANSAC Base Case Status Base case study models representing the base scenarios will be completed as follows for.
ERCOT – LP&L Study Status Update For Regional Planning Group Ben Richardson March 22, 2016.
Information Needed By All Market Participants To Facilitate Transmission Congestion Studies In ERCOT Presented to the ERCOT ROS by Shannon Caraway, P.E.
TAC RELIABILITY AND OPERATIONS SUBCOMMITTEE CMWG/PLWG Planning Criteria Review/Update Report to ROS Austin, TX August 11, 2011 Kenneth A. Donohoo, P.E.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Announcements Please read Chapter 6
Freeport Area Master Plan Project -
2016 RTP Update June, 2016 RPG Meeting.
Transmission Planning in ERCOT- Overview
2016 RTP Update November, 2016 RPG Meeting.
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
ECEN 460 Power System Operation and Control
Reliability and Operations Subcommittee Report
I-5 Corridor Reinforcement Project
Project WECC-0100 Update Load Modeling Task Force
Planning Tools Overview
Local Area Planning Update – TRANSAC
DEC System Voltage Planning - June 2018
ECEN 460 Power System Operation and Control
ECEN 460 Power System Operation and Control
Review of Distribution Network Protection
Planning Tools Overview
TONBRIDGE POWER GREEN LINE
Palo Verde-COI RAS Retirement
Project WECC-0100 Update Load Modeling Task Force
Palo Verde-COI RAS Retirement
Presentation transcript:

Barrilla Junction Area Transmission Improvements Project ERCOT Regional Planning Group March 22nd. 2016 (Prepared by AEPSC)

One line of the existing Barrilla Junction Area transmission system with future loads

Study Drivers New Direct interconnection load requests and increased load forecast at existing points of delivery Increased solar generation interconnections in the area Maintain NERC, ERCOT, Oncor and AEP reliability criteria Bus Name Bus Number 2016 2017 2018 2019 2020 Pig Creek 38375 25.00 County Road 101 6657 24.60 34.30 36.80 37.40 Gas Pad 11112 21.90 Musquiz 38305 15.38 27.50 28.90 34.20 34.10 Lotebush 6656 0.00 5.75 23.33 23.41 Hackberry Draw 38370 6.64  Total   86.88 114.45 133.43 141.31 141.81

Study Methodology Case preparation West Texas Study 2020 case modified with the latest load projections from customer requests Dispatch assumption given flows on the north and east of Barrilla Junction are heavily impacted by the generation at Permian Basin, Barrilla Junction and Ft. Stockton Study zone comprised of the West and Far West zones Branch loading and bus voltages monitored for 69 kV and above facilities Contingency events Contingency Event NERC Event Description N-0 P0 System normal, Zero elements out of service. N-1 P1 Forced outage of a single Transmission line, Transformer, Generating unit, Common tower outage, Shunt or FACTS device. N-G-1 P3 Loss of a generating unit followed by an N-1 event defined above.

Study Methodology Generation Dispatch Assumptions In the Low Wind (LW) dispatch, all the area wind generators were dispatched at 20% with the exception of the two Woodward units that were dispatched to 0%. In the High Wind (HW) dispatch, all area wind generators including the Woodward units were dispatched at 100% of Pmax. In the Low Solar (LS) dispatch, all the solar generators in the study area were dispatched to 0%. In the High Solar (HS) dispatch, all solar generators in the study area were dispatched at 100% of Pmax. In the Low Gas (LG) dispatch, all the area gas generators were dispatched at 20% with the exception of the Permian gas units that were dispatched at 0%. In the High Gas (HG) dispatch, all the area gas generators were dispatched at 100% of Pmax.   2020 HS/LW/HG 2020 HS/HW/LG 2020 LS/LW/LG 2020 LS/LW/HG Solar 100% 0% Wind 20% Woodward Gas Permian

Existing System Performance Existing system cannot support the projected load growth in the area and the export of renewable (solar) generation outside the area Most Limiting Contingency: Loss of either end of the line System Limitation: Post Contingency Voltages in the Barrilla Junction area drop below 0.92 p.u. Overload of the existing line beyond emergency rating Reasons Why Additional Facilities Will Be Required By Jan. 2020 Load connecting to Permian Basin – Barrilla Junction line is projected to be at 150 MW Solar generation requests in the area – 1,950 MW Improvements are Required to Maintain NERC Compliance

One line of the existing Barrilla Junction Area transmission system showing overloaded facilities

AEP and Oncor Recommendation Recommended Solution: Rebuild the existing Barrilla Junction/Solstice to Permian Basin AEP-TNC/Oncor 138 kV transmission line – approximately 54 miles Hackberry Tap (Lotebush)– Build a new station near the existing tap location and install a dynamic reactive device. Ft. Stockton Plant – Rebuild existing Ft. Stockton plant to a multi bus configuration and install dynamic reactive device. Benefits: Improves Load Serving Capability of the Permian Basin – Barrilla Junction 138 kV line Relieves congestion in the Barrilla Junction Area Recommended in the 2015 RTP plan and passed the economic test Estimated Cost: $111.91 M

Rebuild Solstice to Permian Basin 138 kV Lotebush/Hackberry Tap – Add dynamic reactive device Rebuild Solstice to Permian Basin 138 kV Pig Creek Rio Pecos Barrilla Junction / Solstice Ft. Stockton Plant- Add dynamic reactive device

One line of the Barrilla Junction Area Transmission System Improvements