PROCEDURE OF SKYTOP AC-SCR RIG HANDLING COMPOSED BY A. BARUAH
MAJOR DEPARTMENTS INVOLVED MAJOR DEPARTMENTS INVOLVED ARE DRILLING 1. RIGBUILDING 2. DRILLING 3. TS DRILLING TRANSPORT ELECTRICAL CIVIL
STEPS THE MAIN STEPS OF HANDLING THE AC-SCR SKYTOP RIG ARE GENERAL RIG DOWN DISASSEMBLY OF RIG SYETEM ILM OF RIG COMPONENTS RIG –UP OPERATION SPUD IN
GENERAL RIG DOWN PROCEDURES OPERATIONS REMOVE DRILL PIPES CASING RUNNERS V-RAMP CAT WALKS PLACE DROLLEY BOARD REMOVE JUNCTION MANIFOLD REMOVE STANDPIPE DEPARTMENTS INVOLVED TRANSPORT RIG BUILDING TS DRILLING
GENERAL RIG DOWN PROCEDURES OPERATIONS REMOVE DERRICK FLOOR RAILINGS REMOVE DOG HOUSE FLOOR PLATES LADDERS MUD NULLAH & STANDS REMOVE 4 NOS MAST PINS DEPARTMENT INVOLVED RIG BUILDING TRANSPORT
GENERAL RIG DOWN PROCEDURES OPERATIONS MAST LOWER DOWN AND KEPT ON HIGH STAND REMOVE DOUBLE BOARD REMOVE THRIBBLE BOARD REMOVE MAST RAILINGS REMOVE OUT LINE BOOM REMOVE SAFETY BOXES REMOVE ALL SERVICE LINES DEPARTMENTS NVOLVED RIG BUILDING TRANSPORT
GENERAL RIG DOWN PROCEDURES DEPARTMENTS INVOLVED RIG BUILDING TRANSPORT DRILLING OPERATIONS KEEP THE MAST ON TRUCK BY DRAW WORK POWER DETACH MAST BULL LINES LOWER TRAVELLING BLOCK ON DROLLEY BOARD REMOVE MAST BULL LINE AND COIL USE ONE CRANE TO LIFT TRAVELLING BLOCK AND OTHER CRANE TO PULL MAST BULL LINE FREE END
GENERAL RIG DOWN PROCEDURE OPERATIONS REMOVE TWO NOS “A” FRAME PINS SWING “A” FRAME REMOVE BOTH SIDES OUT RIGGERS UN PINNED 16 NOS CROSS BRACES AND REMOVE 8 NOS CROSS BRACES DEAPRTMENTS INVOLVED RIG BUILDING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATION REEVE UP FRONT FLOOR BULL LINE PULL BACK BLOCK &DROLLEY BOARD HOOK UP BULL LINE WITH TRAVELLING BLOCK DEPARTMENTS INVOLVED DRILLING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATION LOWER FRONT FLOOR DEPARTMENTS INVOLVED RIG BUILDING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATION REMOVE FRONT BULL LINE PULL BACK BLOCK & DROLLEY BOARD REEVE REAR FLOOR BULL LINE DEPARTMENTS INVOLVED DRILLING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATION LOWER REAR FLOR DEPARTMENT INVOLVED RIG BUILDING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATION MAST PLACED ON LOW STAND BY CRANE DEPARTMENTS INVOLVED TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATIONS REMOVE MAST LADDERS REMOVE FLOOR BULL LINES REMOVE ROTARY HOSES DEPARTMENTS INVOLVED RIG BUILDING DRILLING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATIONS PULL OUT CASING LINES FROM DRAW WORKS REEVE IT ON BULL LINE SPOOL DEPARTMENTS INVOLVED DRILLING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATIONS POWER CUT OFF REMOVE DRILLING CONSOLE AIR DUCTINGS REMOVE CABLES AND CABLE TRAY DEPARTMENTS INVOLVED TS DRILLING ELECTRICAL TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATIONS REMOVE DRAW WORKS CHAIN REMOVE MOTOR PART & DRILLOMETER SEPARATE COUNTER PART & DRAWWORKS PIPINGS FROM ECBRAKE DEPARTMENTS INVOLVED RIGBUILDING CEMENTING TRANSPORT TS DRILLING
GENERAL RIG DOWN PROCEDURE OPERATIONS LOWER DRAW WORKS DEPARTMENTS INVOLVED RIG BUILDING TRANSPORT
GENERAL RIG DOWN PROCEDURE OPERATION MAST DISMENTLING BEGINS DEPARTMENTS INVOLVED RIGBUILDING TRANSPORT
PARRALLELLY ELECTRICAL DISMANTLES VARIOUS ELECTRICAL CONNECTIONS AND BOX UP CABLES TS DRILLING (IC)BOX UP POWER PACKS TS DRILLING DISCONNECTS VARIOUS FLOW LINES ,PUMP FITTINGS AND RING LINES FIELDS ENGINEERING REMOVES WATER LINES CIVIL REMOVES SHADES (CONTD.)
PARRALLELLY CEMENTING REMOVES HOPPERS AND SILOS RIG BUILDING AND CARPENTER GANG BOX UP TANKS,MUD MIXTURES ,BARYTESE RACKS ETC TS DRILLING (PUMP) BOX UP RIG PUMPS AND EMPTY WATER TANKS TRANSPORT PROVIDE S CRANE & OFT SERVICE TO ALL THE DEPARTMENTS FOR HANDLING AND TAKING OUT .
PARRALLELLY TRANSPORT AND RIG BUILDING CLEARS SUB BASES ,BOPS, CELLER PUMP ETC TO HAND OVER WELL TO PRODUCTION. VARIOUS TANKS, PUMPS ,AND ALL OTHER EQUIPMENTS ARE TAKEN OUT AND MADE READY FOR TRANSFER BY TRANSPORT DEPARTMENT
PARRALLELLY CEMENTING REMOVES HOPPERS AND SILOS RIG BUILDING AND CARPENTER GANG BOX UP TANKS,MUD MIXTURES ,BARYTESE RACKS ETC TS DRILLING (PUMP) BOX UP RIG PUMPS AND EMPTY WATER TANKS TRANSPORT PROVIDE S CRANE & OFT SERVICE TO ALL THE DEPARTMENTS FOR HANDLING AND TAKING OUT .
ILM OPERATIONS TRANSFER SECURITY HUT,RIG BUILDING AND CARPENTER AND ERRECTOR HUTS ETC DEPARTMENT INVOLVED TRANSPORT
ILM DEAPARTMENTS INVOLVED TRANSPORT OPERATIONS TRANSFER WATER TANKS AND SKID TRANSFER BARYTESE RACKS TRANSFER MUD MIXTURES AND SUPER CHARGER REMOVE RIG PUMPS AND TRANSFER PULL OUT MUD TANKS AND TRANSFER DEAPARTMENTS INVOLVED TRANSPORT
ILM DEPARTMENTS INVOLVED OPERATIONS TRANSFER POWERPACK .TRANSPORT ELECTRICAL & TRANSPORT (FOR PCR) TRANSPORT OPERATIONS TRANSFER POWERPACK TRANSFER PCRS TRANSFER CREW HUTS -TS DRILLING TRANSFER CREW HUT TRANSFER CABLE BOXES TRANSFER CABLE TRAYS TRANSFER VARIOUS MOTOR DRIVEN AND ENGINE DRIVEN PUMPS
ILM DEPARTMENT INVOLVED TRANSPORT OPERATIONS TRANSFER RING LINES, FLOW LINES AND ALL OTHER CONNECTIONS TRANSFER HUTS,SILOS ,HOPPER ETC DEPARTMENT INVOLVED TRANSPORT
ILM DEAPRTMENTS INVOLVED TRANSPORT OPERATIONS TRANSFER SUB BASES 4 NOS TRANSFER CROSS BRACES TRANSFER FLOORS TRANSFER MAST PARTS & LADDERS TRANSFER LOW & HIGH STANDS DEAPRTMENTS INVOLVED TRANSPORT
ILM DEPARTMENTS INVOLVED TRANSPORT OPERATIONS TRANSFER BOARDS DOUBLE & THRIBBLE TRANSFER CROWN TRANSFER DROLLEY BOARD TRANSFER BLOCK TRANSFER STAND PIPES TRANSFER CAT WALKS,VV RAMP ETC DEPARTMENTS INVOLVED TRANSPORT
ILM DEPARTMENTS INVOLVED TRANSPORT OPERATIONS TRANSFER LDO TANK STAND TRANSFER HSD TANKS TRANSFER AIR COMPRESSOR TRANSFER DRAW WORKS RAMP TRANSFER DRAW WORKS,COUNTER PART AND MOTOR PART DEPARTMENTS INVOLVED TRANSPORT
RIG UP DEPARTMENTS INVOLVED OPERATIONS TRANSPORT & TS DRILLING TRANSPORT/RIGBUILDING/TS DRILLING TRANSPORT/CARPENTER GANG OPERATIONS PLACE AND ALLIGN WATER PUMP SKID, TANKS & PUMPS PLACE & ALIGN MUD STORAGE TANKS AND ALIGN PLACE MUD MIXTURE AND HOPPER SKID
RIG UP OPERATIONS PLACE AND ALIGN SUPER CHARGER PLACE AND ALIGN RIG PUMPS FIX CONNECTIONS DEPARTMENTS INVOLVED TRANSPORT AND TS DRILLING
RIG UP OPERATIONS PLACE AND ALIGN PCRS PLACE AND ALIGN POWER PACKS PLACE CREW HUTS DEPTS. INVOLVED TRANSPORT & ELECTRICAL TRANSPORT & TS DRILLING(IC) TRANSPORT
RIG UP DEPTS. INVOLVED TRANSPORT AND RIG BUILDING(ERRECTOR GANG) OPERATIONS PLACE AND ALIGN 4 NOS SUB BASES FIX CROSS BRACES FIX REAR AND FRONT FLOORS PLACE DROLLEY BOARD AND T/BLOCK FIX MAST MEMEBERS & MAST LADDERS FIX CROWN DEPTS. INVOLVED TRANSPORT AND RIG BUILDING(ERRECTOR GANG)
RIG UP DEPTS. INVOLVED TRANSPORT AND RIGBUILDING OPERATIONS PLACE AND ALIGN COUNTER PART PLACE AND ALIGN DRAW WORKS PLACE AND ALIGN MOTOR PART PLACE AND ALIGN DESILTER AND DESANDER TANK DEPTS. INVOLVED TRANSPORT AND RIGBUILDING
RIG UP DEPTS. INVOLVED TRANSPORT TS DRILLING OPERATIONS PLACE AND ALIGN LDO TANK STANS AND TANKS PLACE AND ALIGN AIR COMPRESSOR PLACE AND ALIGN HSD TANKS DEPTS. INVOLVED TRANSPORT TS DRILLING
PARRALLALLY OPERATIONS CABLE LAYING & CONNECTIONS FIXING RING LINES AND SINKING TUBE WELLS FIXING VARIOUS PIPINGS AND CONNECTIONS SHEDA OVER PCR AND RIG PUMPS DEPTS. INVOLVED ELECTRICAL FIELDS ENGINEERING TS DRILLING AND TRANSPORT CIVIL
RIG UP OPERATIONS POWER TO DRAW WORKS REAVING OF CASING LINE REAVING OF REAR FLOOR BULL LINE DEPTS INVOLVED ELECTRICAL & TS DRILLING TRANSPORT AND DRILLING DRILLING
RIG UP DEPTS INVOLVED RIG BUILDING AND TRANSPORT RIGBUILDING OPERATIONS FIX STAND PIPE & ROTARY HOSE RAISE REAR FLOOR FIX 12 NOS PINS & 4 N0S CROSS BRACES PULL BACK DROLLEY BOARD DEPTS INVOLVED RIG BUILDING AND TRANSPORT RIGBUILDING RIG BUILDING &TRANSPORT TRANSPORT
RIG UP OPERATIONS REMOVE REAR FLOOR BULL LINE AND REEVE FRONT FLOOR BULL LINE DEPTS INVOLVED DRILLING AND TRANSPORT
RIG UP OPERATIONS FIX UP 12 NOS PINS OF REAR FLOOR FIX 4 NOS CROSS BRACE BY PINNING 8 NOS PINS DEPTS. INVOLVED RIG BUILDING & TRANSPORT
RIG UP OPERATIONS PULL BACK DOLLY BOARD REMOVE REAR FLOOR BULL LINES. REEVE FRONT FLOOR BULL LINE DEPTS. INVOLVED RIG BUILDING & TRANSPORT
RIG UP OPERATIONS PLACE MAST CROWN ON OFT BY CRANE FIX UP 16 N0S PINS,4 NOS CROSS BRACES BY PINNING 8 NOS PINS DEPTS. INVOLVED TRANSPORT RIG BUILDING
RIGUP OPERATIONS PULL BACK DOLLY BOARD REMOVE FRONT FLOOR BULL LINE RIG UP STAND PIPES BELOW DERRICK FLOOR DEPTS. INVOLVED TRANSPORT RIG BUILDING
RIGUP OPERATIONS SWING “A” FRAME FIX 4 NOS PINS KEEP MAST ON HIGH STAND BY DRAW WORKS POWER DEPTS INVOLVED TRANSPORT RIG BUILDING
RIG UP OPERATIONS LIFT TRAVELLING BLOCK BY ONE CRANE PULL BULL LINE FEMALE END BY 2ND CRANE FIX MAST PIN OF BULL LINE DEPTS INVOLVED RIG BUILDING TRANSPORT
RIG UP DEPTS. INVOLVED TRANSPORT RIG BUILDING OPERATIONS FIX UP DOUBLE BOARD FISX UP THRIBBLE BOARD OUT RIGGERS,CAT LINE ETC SAFETY CAGES,TARPOULINE ETC DEPTS. INVOLVED TRANSPORT RIG BUILDING
RIG UP OPERATIONS FIX UP CROWN BLOCK SIDE SAFETY PLAT FORM,LADDER ETC RIG UP OUT LINE,SERVICE LINES DEPTS. INVOLVED RIG BUILDING TRANSPORT DRILLING
RIG UP OPERATIONS RAISE MAST FIX UP 4 NOS PINS WITH REAR FLOOR (ON THE “A” FRAME ) DEPTS. INVOLVED TRANSPORT RIG BUILDING
RIG UP DEPTS. INVOLVED RIG BUILDING TRANSPORT OPERATIONS RIG UP STAND PIPE RIG UP JUNTION MANIFOLD RIG UP FLOOR OUT RIGGERS 8 NOS RIG UP 12 NOS OF BRACES DEPTS. INVOLVED RIG BUILDING TRANSPORT
RIG UP OPWERATIONS RIG UP BOTH SIDES LADDERS RIG UP DOG HOUSE RIG UP V RAMP RIG UP CAT WALKS & RUNNERS DEPTS. INVOLVED RIG BUILDING TRANSPORT
SPUD IN OPERATIONS RIG UP FALSE CONDUCTOR PLACE SPUD IN MATERIALS ON RUNNERS TRANSFER LDO DEPTS. INVOLVED RIG BUILDING TRANSPORT
THANK YOU