ABT-EC EYETS Activities 2nd reports

Slides:



Advertisements
Similar presentations
“LHC Controls for Sector Test” Planning SPS Extraction Kicker and Septa LHC Injection Kicker and other equipment (beam stoppers, dumps,...) Etienne CARLIER.
Advertisements

Multi-Turn Extraction / L.Ducimetière / Kicker options for MTE Prepared by L.Ducimetière, L.Sermeus Outline: Reminder : Present MTE dedicated.
PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
Magnet Controls Group LCLS Magnet Controls August 16, Status of the LCLS Magnet PS Controls Needed for First Injection.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Maciej Ostręga Michal Zimny IBL CO 2 cooling progress meeting
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
This document is the property of Firelec. No copy, even partial, allowed without prior writen authorization. FIRELEC Migration Solution Don't let wiring.
ABT Consolidation Review Electronics & Controls Etienne Carlier
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
YETS LHC 2015/16 - ABT Group TCM Francesco castronuovo.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
Replacement of Obsolete/Old Hardware L. Ducimetière SPS Consolidation Review Luc Sermeus, Mike Barnes, Viliam Senaj, Thomas Kramer, Luis Feliciano, Vasco.
1 J. Mourao (TE/MPE/CP) Enhanced DQHDS functionality  Status for 2011  Increase Magnet diagnostic capabilities  Our proposals.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Field Replaceable Units, Common Problems, and Flowcharts.
E.Sbrissa EP/TA3 - IC ATLAS EDR_MAG Magnet Project Fault analysis, QA & Failure rate.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
YETS & LS2 Works EN-EL / Power distribution
Linac4-PSB 160 MeV connection readiness review
PS / Booster septa control
Update on BISW EYETS activities
LBDS TSU & AS-I failure report (Sept. 2016)
Test bench for active bases for SATLAS Photomultipliers
EYETS David Hay EN-OSS.
Injector De-cabling Project
EC Activities Status for LIU September 2017
EC Activities Status for the LIU
# 56- FIRE PREVENTION (Decision Needed)
TE-ABT Activities for LS2
prepared by R.A.Barlow 30/056/2016
TE-ABT PLC and SCADA usage
Installations, modifications, consolidation in 2005:
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
J. Uythoven for the MPE-MI & MS Teams
EN-HE SPS works during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
MPE main activities planned for LS2
SPS Planning for the EYETS Meeting 8 (07/12/2016)
352MHz Klystron Control for the 3MeV Linac test stand
the CERN Electrical network protection system
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
SPS activities during LS2 TE-EPC (Power Converter Group)
EN-CV interventions during EYETS for PS and PSB
YETS & LS2 Works EN-EL / Power distribution
James Ridewood BE-OP-SPS
EYETS septa status Septa activities TE/ABT Thierry Masson
EYETS septa status Septa activities TE/ABT Thierry Masson
K. Foraz on behalf of OSS members
PS and SPS hydraulics convergence
GIS Portal Racks Project
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
FIRELEC Migration Solution
FIRELEC Migration Solution
KFA10 status 03/06/2019 Currently:
Presentation transcript:

ABT-EC EYETS Activities 2nd reports Christophe Boucly – TE/ABT 31/01/17

PS Complex During Week 2  Week 4 PSB de-cabling campaign in progress Issue … Three pick-up cables cut by accidentally during campaign, Repairing and reflector measure will be done by EN (on going), New cables in replacement can be installed during W11 by EN CPS de-cabling campaign (identification) : 1st phase done ~200 cables found and identified for the de-cabling, ~400 cables checked and 15% of new cables identified as obsolete. Hydraulic Maintenance Study new power and control carte for the cooling system of LEIR New design on going

PS Complex

PS Complex During Week 5  Week 8 2nd phase of CPS de-cabling campaign (identification) : MTE and FAK identification … KFA28 and KFA45 none cables listed LEIR Maintenance : New power and control unit of hydraulic system KFA71-79 Maintenance : Corrective maintenance of hydraulic system SEPTA – SEH26: Installation and commissioning of new control system

SPS Complex During Week 2  Week 4 SBDS New cables installed and infrastructure done Installation of Fast interlock detection system MKP/MKQ/MKD Preventive maintenance filter/fan and capacitor change in heater supplies done SPS – MKP – Fire protection system (overpressure) Production and installation of new control cabinet done Safety AS-interface bus cabling and pressure switch detection connected.

SPS Complex

SPS Complex During Week 5  Week 8 MKP Fire protection system commissioning New termination resistor rework control part and installation on site on the PFN7 Cabling and upgrade of control software. SDBS Electrical discharge switch maintenance Hardware and software upgrade MKP Installation of new fast interlock detection system

LHC Complex During Week 2  Week 4 LBDS - MKD/MKB Beam 1 only : Hardware and software upgrade of slow control part, New safety AS-Interface solution dedicated for the powering distribution – Modification and test done. Beam 1 & 2 : Software and hardware upgrade for all power trigger controller cards (PTC) done and reinstalled. MKI – Supply Voltage Monitoring : EN/MME modification cards received All cards replaced and test in MKI point 2 Hardware and software upgrade of slow control part All cards removed in MKI point 8 to checked and hardware modification.

LHC Complex

LHC Complex During Week 5  Week 8 LDBS : Slow control software update on PLCs Beam 2 Deployment of AS-interface on powering distributor of Beam 2 24V power supplies diagnostic Objective : determinate if the capacitors of power line IN/OUT are out of tolerance and schedule the replacement (30 power supplies by beam). MKI : Slow control software update on MKI point 8 Supply Voltage Monitoring cards upgrade with reinstallation and commission on site point 8.

RESUME Issue during the PSB de-cabling campaign with the cutting of PU cables  In waiting reflectometry by EN. KFA71-79 hydraulic unit – New corrective maintenance issue – Must be schedule … CPS De-cabling campaign – more cables no connected, no identified and take more time for the identification with EN. SPS – No supplied on fire protection system before the end of February. Temporally supply to commission will be installed … Schedule a time for the commission with the global system (2 or 3 days) begin March. New terminator resistor of MKP (Magnet issue) – Interlocks/Warning protection definition not defined. LDBS – Upgrade on Beam 1 must be finished this week. Wait the availability of the Beam 2 (approximatively needs two week for the upgrade). AD-HORN test bench – First new cubicle installed on site end of February

REFERENCE EDMS-1747796 v0.1 – ABT-EC EYETS Activities schedule TE-ABT-EC Maintenance JIRA TE-ABT-EC Production JIRA ABT-Activities-Schedule by Francesco Castronuovo.