Mark Garrett – Direct Energy Clayton Greer – J Aron

Slides:



Advertisements
Similar presentations
Additional CREs to address Stability Limits Beth Garza TAC June 26, 2008.
Advertisements

October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Critique of Proposal to Designate SAPS-Shrew as CRE Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) June 4, 2009.
Connection of Wind Farms to Weak AC networks – ERCOT Experience and Challenges Shun-Hsien (Fred) Huang ERCOT System Planning CIGRE WG B4.62 Meeting June.
EIUG – Wheeling Methodologies
West Texas Congestion Chad Thompson Congestion Management Working Group August
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Completed projects totaling 43,409 MW New Electric Generating Plants in Texas Since 1995 (excluding.
IMPERIAL VALLEY CONFERENCE July 21, SOLICITATION RENEWABLES PORTFOLIO STANDARD.
Potential Transmission Construction Scheduling In Southern Minnesota--- Fall Spring 2006 Xcel Energy has posted Significant Transmission construction.
March 2003 Operations Summary Bill Blevins Manager Operations Engineering.
Managing West Texas Wind SWEDE 2008 Conference May 2, 2008 Presented by Paul Hassink AEPSC Texas Transmission Planning.
ERCOT 2009 CSC Proposal 3h Mark Garrett – Direct Energy Clayton Greer – J Aron.
NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
Compiled by Load Profiling ERCOT Energy Analysis & Aggregation
1 WMS Report To TAC September In Brief Four Working Group Reports Four Working Group Reports One Task Force Report One Task Force Report Three.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
West to North CSC Location Scenario 3b WMS August 20, 2008.
VRT Study Update José Conto ERCOT System Planning.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
RPRS ERCOT System Wide Insufficiency Charge Presented at the Technical Advisory Committee June 1, 2006.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
CRR Model Building Process Bradley Bell CRR Engineer.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
July 10, 2008 ROS Early Delivery Systems Status – R6.3 2 Hour Test John Dumas and Jeff Gilbertson.
1 RPRS Market the issue of capacity inadequacy solved by the Local Congestion procurements ERCOT Feb 19, 2004.
2003 State of the Market Report ERCOT Wholesale Electricity Markets.
2010 CSC & Zone Selection: 6 Lines W-N & 4 Zones (WN2_SN0-4Z) Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) August 19,
efficient capacity allocation method
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
ERCOT CSC – Vote “Yes” to 3b Jan A. Bagnall Sr. Director Transmission, Reliability & Compliance October 2008.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
Technical Advisory Committee Presentation to the ERCOT Board of Directors September 16, 2008.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Panhandle Renewable Energy Zone (PREZ) Study
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
October, 2009 Congestion Report Isabel Flores. 2 October, 2009 Background Provide trend of local congestion costs for last 13 months Costs shown in millions.
2009 ERCOT CSCs and Congestion Zones (10/8/08) C. Richard Ross American Electric Power Service Corporation.
CMWG Update to WMS Met 4/24 & 5/11 Continued Work on PRR 801 –Discussed outages as related to TCR Cases –ERCOT evaluates various outage combinations.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Report to TAC June In Brief Working Group Reports Working Group Reports CMWG CMWG MCWG MCWG QMWG QMWG VCWG VCWG Other Reports Other Reports NOGRR.
ERCOT – LP&L Study Status Update For Regional Planning Group Ben Richardson March 22, 2016.
Proposed Market Solution for Bates RMR Exit Strategy Frontera Power Station.
TAC RELIABILITY AND OPERATIONS SUBCOMMITTEE CMWG/PLWG Planning Criteria Review/Update Report to ROS Austin, TX August 11, 2011 Kenneth A. Donohoo, P.E.
Market Trials Update NATF March 2,
Principal Load Profiling and Modeling
Freeport Area Master Plan Project -
Protocol Revision Subcommittee
CSC DETERMINATION PROCESS
Barrilla Junction Area Transmission Improvements Project
NPRRs 815NPRR Revise the Limitation of Load Resources Providing Responsive Reserve (RRS) Service.  This Nodal Protocol Revision Request (NPRR) revises.
GSR022: Review of Security and Economy Required Transfer Conditions
Initial ERCOT Parking Deck Prioritization Recommendation
John Dumas Director, Wholesale Market Operations
2011 Prioritization Update to Market Subcommittees
Initial ERCOT Parking Deck Prioritization Recommendation
Review of Abnormal MCPEs
Modifications to Planning Charter
ISO New England System R&D Needs
Texas Nodal Load Frequency Control (LFC) EDS 3 R6
The Joint Accounting Conference 2018
DEC System Voltage Planning - June 2018
efficient capacity allocation method
The Network Model Management System
Problems identified by NRAs that may lead to new infrastructure needs
Presentation transcript:

Mark Garrett – Direct Energy Clayton Greer – J Aron ERCOT 2009 CSC Proposal 3h Mark Garrett – Direct Energy Clayton Greer – J Aron

Opening points W-N transmission topology for 2009 was reconfigured on June 3, 2008 with the completion of the Long Creek substation, significantly changing flows on both the east side & west side of Long Creek. Thermal congestion since June 3 was primarily on Abilene Mulberry Creek – Long Creek as a result of this topology change. CSC selection process should give generators correct price signals to reduce total congestion cost by locating generators in the correct congestion zone. Abilene Mulberry Creek – Long Creek CSC in Scenario 3h will reduce congestion costs more than Scenarios 3b or 3g.

ERCOT Contour Plot – Proposal 3h

ERCOT Transmission Map – 3 CSC Proposals & 2008 CREs J.L. Bates Bates Frontera

June 3 onward is the only representative historical data… Long Creek Substation was looped into Sweetwater Cogen - Graham 345 kV line on June 3, 2008. This change 1) equalized flows on Graham – Long Creek circuits #1 and #2, 2) increased the flow on the Mulberry Creek – Long Creek, and 3) exacerbated the congestion on the Mulberry Creek – Long Creek. No major outages in 2009 are scheduled per TPIT or Outage Scheduler. If Clear Crossing work results in an outage on Tonkawa – Graham, then Mulberry Creek – Long Creek carries a heavier burden. Static wire replacement outages on Graham - Abilene - Morgan Creek double circuit 345kV path resulted in major W-N transmission congestion during period from 2/4 through 3/30 and is not expected to be repeated during 2009. February-March W-N zonal congestion cost totals $34,153,644. PRR 764 was implemented on June 9, 2008, removing non-CREs from the zonal solution. 2008 W-N Non-CRE zonal congestion cost totals $7,953,061 (excludes Feb-March)

What historical data will be representative of 2009 conditions What historical data will be representative of 2009 conditions? (continued) Exclude Feb-Mar 2008 due to static wire outage. Ignore Non-CRE congestion. W-N topology was significantly reconfigured on June 3 and will remain constant through 2009. THEREFORE, June 3 to date is the most representative historical data.

Flows on Mulberry Creek – Long Creek have increased Note flows equalize after June 3 Note increase after June 3 Configuration before June 3 Configuration after June 3

Electrical Flows on relevant lines – May 30 through June 5 Flows converge on June 3 after 2-day outage to tie-in Long Creek Bastrop Source: ERCOT real-time CRE postings

Historical congestion cost – June 3 to present Proposal 3h accounts for 75% of all congestion since June 3. Source: Congestion charges from ERCOT website

Historical congestion days – June 3 to present Thermal Constraint (3b) Thermal Constraint (3g) Thermal Constraint (3h) Dynamic Stability Only June 1 day 0 days 9 days 5 days (local) July 3 days 4 days 3 days (zonal) August 2 days Total 6 days 13 days 8 days Percent Total 21% 4% 46% 29% Percent Thermal 30% 5% 65% N/A

Proposal 3h is the most efficient outcome Importance of Making the Right Decision Zonal construct assumes average impact from generation in a zone Physics doesn’t match (hence the change to nodal) Generation sitting on constraint receiving wrong price signal has multiplicative effect due to shift factor difference Best Counterflow North Zone Zonal Average Counterflow West Zone Constraint

Result - Proposal 3h is the most efficient outcome Generator with highest beneficial shift factor receives negative price signal That generator reduces generation (to zero) That beneficial generation must be replaced by moving up the stack not only the amount of the generation, but by the shift factor difference For example, 400 MWs is located at Long Creek and has twice the positive impact on the constraint as the North Zone (shift factor difference is an estimate only) With Long Creek in West Zone, the North Zone must not only replace the 400MWs Long Creek moves down, but must also provide an additional 400MWs due to the solution being less efficient With Long Creek in the North Zone, this 800 MWs would not have to have been moved at all Result if decision is wrong is increased spreads and volatility The converse is also true, which is why we need to get this right Balancing Deployment with Right Decision Balancing Deployment with Wrong Decision = = =

June transmission flows were a result of high wind output 4/1-8/11 Avg=1,883MW June 4-8 Avg=3,649MW Source: ERCOT real-time flow postings.

More wind coming in 2009 in the west UPCOMING WIND PROJECTS in Western ERCOT JUNE 2008 – DEC 2009 2,808 MW : Interconnection Agreement 2,592 MW : Public Letter Total : 5,400 MW NOLAN Turkey Track Energy Center – 170MW – IA Buffalo Gap 4 – 131MW – PL Buffalo Gap 5 – 335MW – PL DICKENS McAdoo Energy Center 2 – 500MW – PL SCURRY Airtricity Inadale – 212MW – IA Pyron – 303MW – IA BORDEN Bull Creek – 180MW – IA Gray Wind – 141MW – PL Coyote Run – 225MW – IA Wind Tex (Stephens Wind Farm) – 141MW - PL Dickens MARTIN Lenorah – 350MW – PL Borden Scurry ANDREWS M Bar Wind – 194MW – PL Shackleford CSC Scenario #3H Abilene Mulberry Creek – Long Creek Sweetwater Cogen – Long Creek Andrews Nolan Howard Taylor Martin Coke ECTOR Pistol Hill – 300MW – PL Notrees – 151MW - IA Ector Sterling SHACKLEFORD Mesquite 4 (Cottonwood) – 100MW – IA Mesquite 5 (Cedar Elm) – 136MW – IA Hackberry – 165MW – IA STERLING Sterling Energy Center – 200MW – PL Sterling Energy Center 2 – 300MW – PL PECOS Sherbino Mesa Wind Farm 1 – 150MW – IA HOWARD Panther Creek – 150MW – IA Ocotillo – 59MW – IA Gunsight Mountain – 120MW – IA Panther Creek 2 – 220MW – IA Elbow Creek – 117MW – IA TAYLOR South Trent –101MW – IA COKE Capricorn Ridge 3 – 249MW – IA Pecos

Conclusions W-N transmission topology for 2009 was reconfigured on June 3, 2008. Thermal congestion since June 3 was primarily on Abilene Mulberry Creek – Long Creek : 13 out of 20 days. CSC selection process should give generators correct price signals to reduce total congestion cost by locating generators in the correct congestion zone. Abilene Mulberry Creek – Long Creek CSC in Scenario 3h will reduce congestion costs more than Scenarios 3b or 3g. WMS should select Scenario 3h.