Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J

Slides:



Advertisements
Similar presentations
PROJECT MANAGEMENT PROJECT MANAGER ENGINEERING MANAGER PROCUREMENT MANAGER CONSTRUCTION MANAGER.
Advertisements

GSMT Control Workshop Tucson, September 11-12, 2001 Pointing Control for a giant segmented mirror telescope Patrick Wallace Rutherford Appleton Laboratory.
CMSC 2006 Orlando Active Alignment System for the LSST William J. Gressler LSST Project National Optical Astronomy Observatory (NOAO) Scott Sandwith New.
1 Second Safety Council Meeting Tucson, AZ April 10-11, 2014 Name of Meeting Location Date - Change in Slide Master The Dome Project Bill Gressler Telescope.
NGAO Instrumentation Overview September 2008 Updated Sean Adkins.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
NGAO Alignment Plan See KAON 719 P. Wizinowich. 2 Introduction KAON 719 is intended to define & describe the alignments that will need to be performed.
PALM-3000 High-order Wavefront Sensor Update Christoph Baranec Team Meeting #9 10/22/2008.
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
HARPS-NEF PDR December 6 & 7, HARPS-NEF Program Project Manager Tim Norton.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
Integration and Test 14 October 2008 Martin Nordby.
Non-contact measurement of large format detectors and thermal blanket material surrounding the flight instruments of JWST Edwin Olaya 1, Agossa Segla 1,
Safety Council Meeting Tucson Arizona 10 – 11 April Safety Council Meeting Tucson Arizona 10 – 11 April 2014 LSST Project Status Victor L. Krabbendam.
1 Engineering the James Webb Space Telescope Paul Geithner JWST Deputy Project Manager - Technical March 26, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES As-Built Drawings and Commissioning Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional.
Technical manager’s report September Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
Framework for Compliance, Verification, and Non-Conformance George Angeli LSST All-Hands Meeting Bremerton August 17, 2015.
Dan Frasier, PE, CCP Successful Turnover of New and Renovation Construction Projects Successful Turnover of New and Renovation Construction.
The Field Camera Unit Project definition, organization, planning S. Scuderi INAF – Catania.
Magellan F/5 System Status A.Szentgyorgyi/SAO/30 Apr 2005.
Monday Morning J. Sebag T&S Systems Engineer. Close Past… 2 M1M3 acceptance and transportation to storage Reviews and RFPs (Dome, Software, Coating Plant,
Presentation EddiCam consortium, FF, Madrid 13/06/2002 Eddington programmatic status Fully approved by SPC as part of ESA’s science program as project.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
Sandrine Thomas (T&S Project Scientist) & Telescope and Site Team.
Magellan F/5 System Status A.Szentgyorgyi/SAO/25 Sept 2004.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
Telescope Integration and Tests Tuesday Afternoon.
LSST Camera CD-3 Review Brookhaven National Laboratory, Brookhaven, NY LSST Safety Council Camera Review Bremerton, WA 2015 LSST Camera Environment,
FLAO system test plan in solar tower S. Esposito, G. Brusa, L. Busoni FLAO system external review, Florence, 30/31 March 2009.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
3.1 Optomechanical systems (1) Scientific and engineering resources are available to carry out the optomechanical work on DECam. The highly distributed.
The Active Optics System S. Thomas and the AO team.
Managing Construction Chapter 16. Contractor Projects are overseen by a contractor who owns and operates a construction company. Projects are overseen.
FLAO_08 FLAO System Shipping Plan Document 646f010a Richard Demers, Guido Brusa, Armando Riccardi, Daniele Galieni FLAO system external review, Florence,
FourStar Status SAC Meeting 13mar2010 Persson, Murphy, Birk, Monson, Kelson, Uomoto.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 1 The DECam Project Closeout, Action Items Hexapod Optical Lenses CCD Readout Filters Shutter 2008.
Commissioning Alistair Walker NOAO/CTIO 9/30/ DES Collaboration Meeting October
1 Board Telescope & Site Tucson, Arizona July 18-20, 2011 LLST Control Software Review Resources Tucson, January
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
1 OBSERVATORY CONTROL SYSTEM (OCS) FRANCISCO DELGADO OCS CAM.
Commissioning Planning
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
LSST Commissioning Status Update & Overview Charles (Chuck) Claver LSST System Scientist SAC Meeting March 5, 2017.
Constraints Space Load Capacity Costs Operating hours.
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
Agenda ComCam planning and scheduling (James & Jacques) CCS & CCS-TCS Interface (Tony) Software to use ComCam Software to get data out of ComCam (Mike)
Systems Engineering, Verification, and Commissioning for LSST George Z
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
LSST Commissioning: FY18 Planning
LSST Commissioning Kevin Reil LSST Commissioning Camera Rep
Integration & Commissioning
Chuck F Claver LSST System Scientist & Commissioning Lead
Camera to Top End Assembly Integration Travis Lange Camera I&T M. E
GLAST Large Area Telescope:
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
GLAST Large Area Telescope: Cost/Schedule Review September 1, 2005
Management Breakout: MREFC Budget Summary Victor L
Launch and On-orbit Checkout
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Integration and Test Organization Chart
Introduction and Overview
PSS verification and validation
Instrument Overview Larry Springer HMI Program Manager
NSS integrated installation plan workshop Introduction
MAORY Status of the project
Presentation transcript:

Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J Telescope Assembly, Integration and Verification (AIV) WBS 04C.14 J. Sebag August 2016

Maximize vendor testing and verification Telescope AIV Summary Maximize vendor testing and verification Work with contractors on Factory Acceptance Tests and On-Site Acceptance Tests Include Handling and Safety Hazard from the start to ensure safe and efficient AIV Surrogate masses and Handling procedures verified Rely on Intimate knowledge of Telescope subsystem designs for faster AIV Fully integrated AIV Team Optimize overlap between sequenced activities to avoid schedule conflicts Regular reviews to keep track of construction progress Demonstrate most telescope performances before commissioning Coordination with commissioning and operations

Telescope AIV Documentation/Verification Process Telescope AIV Plan (LTS-104) Verification Matrix (in progress) LSST T&S AIV Plan and Verification Matrix LSST T&S Inspection/Test Plan Inspection/Test Procedures Inspection/Test Reports Compliance Matrix

Robust AIV Sequence in Phase with Subsystem Delivery Three Major Phases Organized for efficient and Safe integration and test: Phase 1 (P1): Dome/Mount/Coating Plant (“Heavy Construction”) Phase 2 (P2): Mirror Coating and Mirror Assemblies Integration Phase 3 (P3): Alignment and Testing Phase 1 (P1) ~2years until end of 2018 Phase 2 (P2) ~1year until April 2019 Phase 3 (P3) ~6 months until Sept 2019 START END P1 P3 P2 From LTS-104 AIV Plan

Telescope AIV is Ramping Up AIV sequence has started with preparation of PFlow platform lift tower installation on the summit AIV Equipment is being selected and purchased AIV Integration instrumentation is being designed and contracted AIV team is being consolidated AIV sequence is being updated Example of Assembled Frame Example of Crane being investigated Filter exchanger for commissioning camera PFlow platform lift tower

PFlow Tower Installation Procedure Work with Platform Lift vendor PFlow to define tower installation procedure on site Work with subcontractor to install tower and to verify installation

In the Process of Building Telescope AIV Team Build core AIV team in Chile that will continue during commissioning and operations Include as much as possible current team members into AIV team Some LSST Team members are already present in Chile (Site Manager, Admin, Engineering, Software) Continuing the process of identifying/hiring AIV team Recent Hiring includes Freddy Munoz, Mechanical/Integration engineer (in Chile) James Howard, Mechanical/Integration Instrumentation engineer (in Tucson) Interviews and more job openings this year

Envisioned Roles Needed for Telescope AIV Team Project Roles: Telescope Team Management, Summit Site Manager, Resource Allocation (PMCS-EV), Safety Coordinators (2), Administration, Facility Operations Deputy Project Manager for AIV, System Engineer, Documentation Specialist, Data Analyst Scientific Roles (Telescope, Calibration, Scheduler) Engineering Roles: Mechanical (5), Electrical (4), Software (7), Optical (2), Coating, Network, IT, Computer, Calibration/Site Monitoring Technician Roles: Mechanical (4), Electrical/Electronics (3), Optical, Coating, Network/IT, Calibration, Telescope Assistants (2)

AIV Team Chart Integrated Within T&S Org Chart Work in Progress to complete the AIV Team

Subsystems Delivered with Handling Equipment and Surrogates Masses Vendors are responsible for design, fabrication and tests of handling equipment and surrogate masses for their subsystem These are delivered with the subsystem Camera Assembly Lifter M2 Surrogate Mirror M1M3 Surrogate Mirror M1M3 Cell Assembly Cart Camera Assembly Surrogate Mass

Surrogates Masses used during testing at Vendor M2 hexapod test payloads for different load tests M2 Hexapod system testing at Moog CSA

Sufficient summit facility floor space and clearance for M1M3 Cell and Surrogate Mirror Assembly M1M3 Mirror Cart 1 M1M3 Cell Reception 2 4 3 M1M3 Surrogate Mirror Cell Installed on Cart From Integration and Test Plan (LTS-104)

Demonstrate Most Telescope Performances Before Commissioning On-axis Image Quality Performance Image Quality Degradation with Zenith Slewing, Pointing and Tracking Performance Throughput Early System Commissioning with Commissioning Camera to continue AOS testing: Guiding using CCDs in camera Active Optics using focal plane as wavefront sensor Final System Commissioning with Science Camera to finalize AOS testing: Guiding using Guiders in camera Active Optics using full focal plane Active Optics using WFS in camera

Cross section of M1M3 cell showing laser tracker in center Tools Included For On-Axis Alignment and Testing Before Delivery of Science Camera Portable Laser tracker for initial alignment Cross section of M1M3 cell showing laser tracker in center M3 Interferometer to test M1M3 mirror support system Hexapod Rotator Camera Support Assembly with Shack-Hartmann Wavefront Sensor to Measure Wavefront On-Axis

Commissioning camera (ComCam) for initial off-axis alignment 3-Lenses FOV Corrector (2 lenses + dewar window) 40-arcmin Focal Plane Composed of one CCD raft (3x3 CCD Detectors) Intra and Extra focal images used for Wavefront Analysis (on and off-axis) Filters Window 374 mm 309 mm Hexapod Rotator Camera Support Assembly with ComCam