LHC commissioning experience at 6.5 TeV

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHCC 3rd June 2015 Mike Lamont for the LHC team
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
LHC Scrubbing Runs Overview H. Bartosik, G. Iadarola, K. Li, L. Mether, A. Romano, G. Rumolo, M. Schenk, G. Arduini ABP information meeting 03/09/2015.
First measurements of longitudinal impedance and single-bunch effects in LHC E. Shaposhnikova for BE/RF Thanks: P. Baudrenghien, A. Butterworth, T. Bohl,
Thursday 21/4 07:30: End of fill #1727. Beam dumped. ALICE compensator magnet fault. Delivered ~6.7 pb -1 in 7.5 h. 11:30 Stable beam # bunches/beam.
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Benchmarking Headtail with e-cloud observations with LHC 25ns beam H. Bartosik, W. Höfle, G. Iadarola, Y. Papaphilippou, G. Rumolo.
Fabio Follin Delphine Jacquet For the LHC operation team
Luminosity monitor and LHC operation
LHC Wire Scanner Calibration
Electron Cloud Effects
Beam Instability in High Energy Hadron Accelerators and its Challenge for SPPC Liu Yu Dong.
Joint LIU / HLLHC day -15 October 2015
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
LHC Machine Status report
Beam-beam effects in eRHIC and MeRHIC
Longitudinal beam parameters and stability
MD2036: UFO dynamics studies and UFO fast detection
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Beam-beam Effects in Hadron Colliders
Summary Friday h38: Ramp down and pre-cycle.
Follow-up of HL-LHC Annual meeting
Lecture 2 Live Feed – CERN Control Centre
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Emittance Measurements and Preservation
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
The Status of the LHC machine
MD25 ns - 14/12/2012 G. Arduini, H. Bartosik, G. Iadarola, G. Rumolo
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Scrubbing progress - 10/12/2012
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
LHC (SSC) Byung Yunn CASA.
Wire almost entirely through beam before BLM triggers dump
Finally.... We had to wait a long time.... We had many problems....
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
LHC Beam Operations Past, Present and Future
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Machine Tolerances in Cleaning Insertions
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Beam dynamics requirements after LS2
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Scrubbing progress - 08/12/2012
Thursday 26th July 13:21 Fill 2880 beam dumped
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Feedbacks & Stabilization Getting them going
Summary – what we discussed and learned (accelerator)
Cryogenic management of the LHC Run 2 dynamic heat loads
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

LHC commissioning experience at 6.5 TeV Eucard Workshop - Firenze November 2015 Jörg Wenninger CERN Beams Department Operation group / LHC For the LHC commissioning and operation teams

Outline Introduction Re-commissioning of LHC E-cloud control & diagnostics Diagnostics examples Summary Eucard WS - Firenze 05.11.2015

The Large Hadron Collider LHC Installed in 26.7 km LEP tunnel Depth of 70-140 m Lake of Geneva LHC ring Eucard WS - Firenze Control Room SPS ring 05.11.2015

The Large Hadron Collider LHC Installed in 26.7 km LEP tunnel Depth of 70-140 m Lake of Geneva LHC ring LHCb CMS LHC ring Eucard WS - Firenze Control Room SPS ring ALICE ATLAS 05.11.2015

The LHC can be operated with protons and ions (so far Pb208). LHC ring layout Total length 26.66 km, in the former LEP tunnel. 8 arcs (sectors), ~3 km each. 8 straight sections of 700 m. beams cross in 4 points. 2-in-1 magnet design with separate vacuum chambers. 2 COUPLED rings. Eucard WS - Firenze The LHC can be operated with protons and ions (so far Pb208). 05.11.2015

LHC energy evolution Long Shutdown 1 (LS1) Energy (TeV) 6.5 TeV Consolidation of all interconnections 7 TeV Design 5 TeV Magnet de-training after installation Energy increase  no quench at 3.5 TeV Eucard WS - Firenze 4 TeV 3.5 TeV Issues on Interconnection, incident 3.5 TeV Long Shutdown 1 (LS1) 1.18 TeV Consolidation delays 2007 2008 2009 2010 2011 2012 2013 2014 2015 05.11.2015

Outline Introduction Re-commissioning of LHC E-cloud control & diagnostics Diagnostics examples Summary Eucard WS - Firenze 05.11.2015

LHC Run 2 goals (2015 - 2018) Operate the LHC at 6.5 TeV (or higher). Operate with 25 ns bunch spacing. For Run 1 we operated with 50 ns spacing (e-cloud). Maximize the integrated luminosity & collect ≥ 100 fb-1. Eucard WS - Firenze Objectives for 2015: Learning year of Run 2 (6.5 TeV, 25 ns spacing), Achieving reliable operation with 25 ns spacing is top priority. b* at the IPs were relaxed to ease operation: b* = 80 cm was selected while 60-40 cm was in reach. We plan to move to 40-50 cm in 2016. 05.11.2015

2015 operation October 28, Record no. bunches June 24, 50 ns e-cloud scrubbing run April 3, End of powering tests – 150 quenches April 10 First beam at April May June July August Sept Oct Easter, Beam circulating June 3, Start of physics operation for run 2 August 7 End of 25 ns e-cloud scrubbing run September 16, Chili 8.3M earthquake shakes LHC rings

 R. Jones on Thursday morning Machine status in 2015 We could rely on a solid experience from run 1 (2010-2013) to startup the LHC – back in business in 2 months, followed by intensity ramp up since early summer. Status: Excellent magnetic reproducibility, Optics well corrected, 5-10% b-beating, Aperture is good and compatible a further reduction of b*, Magnets behaving well at 6.5 TeV (just 3 additional quenches since beam operation started), Good & improved instrumentation, Excellent operation control: Injection, ramp, squeeze etc.  R. Tomas on Thursday m. Eucard WS - Firenze  R. Jones on Thursday morning The main point of concern is called e-clouds. 05.11.2015

LHC operation evolution ‘Serious’ operation started with 50 ns beams (~ no e-cloud), this period was limited to 2 weeks due to start-up delays. The intensity ramp up stopped at 480 bunches (max. 1380). Operation with 25 ns beam spacing started mid-August, we have now reached 2244 bunches per beam (nominal ~2750 bunches – 82% full). Operating at the cryogenics cooling power limit (e-cloud heat load). E-clouds are the main limitation for operation, intensity follows conditioning. Eucard WS - Firenze 05.11.2015

Integrated luminosity The initial projections of integrated luminosity for 2015 were ~5-15 fb-1. We finally achieved > 4 fb-1. The main reasons for the lower value: Start-up delays (~6 weeks), Availability issues (radiation failures on the quench protection tunnel electronics – solved now), Difficulties to master electron clouds. Eucard WS - Firenze The 2015 proton run is finished now, this year will close with a 4 week lead ion run. 05.11.2015

Performance 2010-2015 The start-up of Run 2 was relatively fast, we are ~40% below the Run 1 luminosity performance. We are still in the learning & ramp up phase. Operation with 50ns beams – no e-clouds – was a lot easier ! Peak luminosity: Run 1: 7.61033 cm-2s-1 Run 2: 5.11033 cm-2s-1 Eucard WS - Firenze 4 TeV Design: 11034 cm-2s-1 6.5 TeV 3.5 TeV 05.11.2015

Outline Introduction Re-commissioning of LHC E-cloud control & diagnostics Diagnostics examples Summary Eucard WS - Firenze 05.11.2015

Instrumentation challenges for LHC After LHC Run 1 most of the instrumentation was in good shape, with improvements in the pipeline for Run 2. Some improvements: Lower BPM systematics (crate temperature), Gated tune system for compatibility with transverse feedback system, New synchrotron radiation monitor mirrors (heating by beam) and optics, Local very high resolution BPMs, … For Run 2 some of the main challenges are: (Almost) Everything bunch-by-bunch (up to 2800), E-cloud diagnostics, Instability diagnostics. Eucard WS - Firenze I will concentrate here mainly on diagnostics around electron clouds since this is our main issue at the moment. 05.11.2015

Electron cloud challenge The LHC with its tightly packet bunches spaced by 25ns is subject to a very strong electron clouds. The key parameter for e-clouds is the Secondary Emission Yield (SEY) of electrons from the vacuum chamber surface. N+1 e- Bunch N+1 accelerates e-, multiplication at impact ++++++ N+2 e- Process repeats for Bunch N+2 … ++++++ N e- Bunch N liberates e- ++++++ Eucard WS - Firenze The e-cloud triggers vacuum pressure increases and beam instabilities. It may deposit excessive heat on the vacuum chamber walls  cryogenic cooling capacity and stability. 05.11.2015

Electron cloud mitigation There is a strong dependence of e-clouds on bunch spacing (at fixed SEY). Vacuum chamber in 2012 run With 50 ns spacing e-clouds are much weaker than for the design spacing of 25 ns.  To ease life during Run 1, the bunch spacing was reduced to 50 ns Eucard WS - Firenze Conditioning of the vacuum chamber by beam-induced electron bombardment (“scrubbing”) leads to a progressive reduction of the SEY: e-clouds are produced deliberately with the beams to bombard the surface of the chamber to reduce the SEY until the cloud ‘disappears’ (self-destruction). Conditioning is performed at 450 GeV where fresh beams can be injected easily. Conditioning requires with a beam that is more powerful ( more electron could generation) that the beam one plans to use for operation ! 05.11.2015

Scrubbing strategy 50 ns: scrubbing with 25 ns, then revert to 50 ns for operation. 25 ns: try the same strategy  we have invented a new doublet beam to enhance the e-cloud further. The doublet beam violates all LHC beam instrumentation specs ! …but in the end it could be accommodated Eucard WS - Firenze Cryogenics limit  Doublet beam 20 ns 5 ns  05.11.2015

E-cloud diagnostics: heat load Cryogenic cell Eucard WS - Firenze Cooling channels The heat load QBS deposited in the vacuum chamber beam screen (cooled to 4-30 K with He gas) is the KEY observable for e-cloud. The heat load reflects the strength of the e-cloud. QBS can be reconstructed from cryogenic temperature and pressure measurements (+ some modelling as missing some observables). Online heat-load measurements that became available in 2015 were essential to monitor the evolution of e-cloud during scrubbing and operation. 05.11.2015

E-cloud diagnostics: heat load Energy Eucard WS - Firenze Example of heat load evolution during filling and ramp. During transient phases the heat load is not accurate (~10 mins delays). The large spread of heat load from one arc to the next is real and not understood ! If all arcs would be at the level of the lowest one, we would have already reached design intensity. 05.11.2015

E-cloud diagnostics - RF The amount of e-cloud affecting a given bunch is reflected in its energy loss on each turn observable on the RF stable phase. Stable phase information is used to monitor the e-cloud on a bunch-by- bunch level – very powerful diagnostics. RF phase shift Eucard WS - Firenze 25 ns beam – strong electron cloud 100 ns beam – no electron cloud B1 B1 05.11.2015 Bunch no.

Scrubbing runs Two scrubbing run for 50 ns and later 25 ns operation. Eucard WS - Firenze Two scrubbing run for 50 ns and later 25 ns operation. SEY inferred from heat load measurements, confirmed by beam stability. Doublet beam could not be used, too unstable beam (!!) – SEY too high. We came out of the scrubbing runs with an important residual e-cloud activity. 05.11.2015

Heat load evolution Courtesy K. Brodzinski QBS [W/half cell] Number of injected bunches Installed capacity limit for 4.5 -20 K including existing margin recovered from lower HL@1.9 K Margin from lower HL@1.9 K Limit for s2-3 116 Installed capacity limit for 4.5 -20 K Eucard WS - Firenze As the number of bunches was increased the LHC was operated closer and closer to the heat load capacity of the cryogenic system. The intensity in the LHC is currently limited by the cryogenics, we can only step up intensity when we gain on the e-cloud front. 05.11.2015

Emittances The wire scanners, our reference instrument, are limited to ~12 bunches at top energy – unusable for any physics operation. Limited by magnet quenches & damage to the wire. Our emittance workhorse is therefore the synchrotron light monitor that also delivers bunch by bunch emittances (30 b / sec). Absolute calibration is delicate, relative calibration is good. Eucard WS - Firenze Essential instrument to track emittance blow up from beam- beam, e-cloud or instabilities Difficult to compare injection and flat top measurements (source change) 05.11.2015

Instability observation Diagnostics of instabilities proved to be difficult at LHC during Run 1. Improved diagnostics (head-tail monitors, bunch-by-bunch transverse feedback data, etc) is in place or will be in place soon. Instability recorded by head-tail monitor A triggering network put in place to be able to trigger all instruments of interest from one or multiple source devices. Eucard WS - Firenze  presentation by T. Levens on Thursday afternoon 05.11.2015

Outline Introduction Re-commissioning of LHC E-cloud control & diagnostics Diagnostics examples Summary Eucard WS - Firenze 05.11.2015

Emittance cross-calibration With colliding beams the convoluted emittances can be reconstructed from the absolute luminosity or from beam separation scans. With one experiment (CMS) providing real-time bunch- by-bunch luminosity one can perform bunch-by-bunch cross-calibrations – agreement at the level of  5%. Eucard WS - Firenze BSRT = synchrotron light mon. 05.11.2015

Synchrotron radiation damping Bunch length Synchrotron radiation damping at 6.5 TeV is sufficient to overcome collective effects (IBS) and noise and damp the proton emittances ! After ~22 hours the bunches become longitudinally (slightly) unstable  growth tSR ~ 18 hours teff ~ 85 hours Eucard WS - Firenze In collision the horizontal emittance is ≈ stable, the vertical emittance shrinks ! 05.11.2015 BSRT = synchrotron light mon.

Luminosity imbalance As soon as the luminosity increases the 2 main LHC experiments watch each others luminosity… In 2015 we observed an imbalance ranging from ~10% (start of fill) and ~4% (end of fill). Roughly ~3% of the change is explained by the emittance evolution (due to the crossing angles at the IPs), we are missing 5-6% that is not understood. Challenging to dis-entangle – precision knowledge of the parameters at the IP in collision is missing (b*, dispersion, crossing angles, errors on L measurements…). Hot off the press: the exp. with the lower luminosity fixed a firmware problem – the luminosity imbalance is now smaller and inverted ! Eucard WS - Firenze Luminosity 05.11.2015 Time

Aperture restriction A position with anomalous beam losses was located on beam 2 in the arc between LHCb and ATLAS only few days after commissioning. An aperture restriction due to an was found by scanning the beam position. Shifted beam orbit Clear for beam The object outline could be mapped accurately with our BLMs and BPMs. The reference beam orbit was shifted upward and sideways to avoid the object. So far operation – even at high intensity – does not suffer from this object. Opening the magnet to remove this object would take 2-3 months ! Vacuum chamber Eucard WS - Firenze Edge of the object 05.11.2015

Unidentified Falling Objects - UFOs Dust particles falling into the beam – ‘UFOs’ – have interfered with operation since Run 1. If the induced losses are too high, the beams are dumped to avoid a magnet quench (20 times / year in Run 1). UFOs have also present at 6.5 TeV – 17 beams were dumped by UFOs and 2 magnets were quenched. Vacuum chamber Eucard WS - Firenze 2015 25ns scrubbing Fortunately the rate decreases with time – significant condition is observed (also in Run 1). Further fine tuning of the beam loss monitor thresholds for such short losses (millisecond scale) is possible.  number of quenches 05.11.2015

Chile earthquake September 16th In the night of September 16th an earthquake of magnitude 8.3 in Chile struck the LHC for ~1 hour. The machine was at injection, and the main effect was a significant radius change (2x largest tides). The radial amplitude was sufficient to make a very good chromaticity measurement. The OP crews through the radial feedback had gone crazy… Eucard WS - Firenze T ~ 20 s 05.11.2015

Thank you for your attention! Outlook After a few month of commissioning and after curing some initial teething problems, operation at 6.5 TeV is now stable and quite robust. The LHC is currently operating with high intensity beams of 25 ns spacing, limited by the available cryogenics power due to strong electron cloud activity. On the instrumentation side bunch-by-bunch information is essential and is steadily improving. A related issue is the collection, filtering and storage of high frequency bbb data. Our controls group, despite pre-warnings, is lagging behind… With the improvements that are anticipated for 2016 we should reach the required performance for Run 2 in the coming year. Eucard WS - Firenze Thank you for your attention! 05.11.2015

Eucard WS - Firenze 05.11.2015

Magnetic model Like most super-conducting machines the LHC is subject to decay and snapback of persistent currents at injection / start of the ramp. Q excursions up to 0.06, Q’ excursions of ±20 units. Decay time constant ~30 mins, snapback over 1 min. Both decay and snapback are parametrized with a model that is played back during injection and fed into the start of the ramp. Quality of the model: ±0.01 (Q), ±2-4 (Q’). For Q’ we rely ~ entirely on reproducibility (one check at start of injection) Eucard WS - Firenze Tune snapback Run1 05.11.2015 Tune decay model

Tune and transverse feedbacks At high intensity the LHC can only be operated with a transverse feedback (damper). In some phases the damper gain is so high that it is impossible to measure a tune… ‘Poisoned’ LHC run1 – fortunately the tune is reproducible! Since 2015, 450 out of 35’640 RF buckets are dedicated to tune measurements: the damper gain can be set independently to lower value – accept some emittance blow up but get a better (gated) tune signal. Eucard WS - Firenze 05.11.2015

Dipole training campaign The 1232 main dipole magnets had to be trained for 6.5 TeV operation. 2-3 training quenches could be performed for each sector in 24 hours, limited by the recovery time of the cryogenic system. Just over150 training quenches were required to bring the LHC to 6.5 + e TeV. The large spread in number of quenches between the eight sectors (arcs) is due to the mixture of magnets from the 3 producers. 3 spontaneous (no beam loss!) quenches occurred in operation at 6.5 TeV. Eucard WS - Firenze 05.11.2015