Scenarios for 2017 and 2018 Thanks to Gianni, Fanouria, Gianluigi, Dario, Stephane, Elias, Michi, Jamie, Christoph, Rogelio, Mirko, Riccardo, Hannes,

Slides:



Advertisements
Similar presentations
Collimation with retracted TCSGs R. Bruce, R. Kwee, S. Redaelli.
Advertisements

REPHASING TESTS DURING THE TWO BEAM IMPEDANCE MD P. Baudrenghien, J. Noirjean, T. Mastoridis 10/26/2012LSWG meeting 1 Oct 7 th,18:00 – Oct 8 th, 04:00.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
* IP5 IP1 IP2 IP8 vertical crossing angle at IP8 R. Bruce, W. Herr, B. Holzer Acknowledgement: S. Fartoukh, M. Giovannozzi, S. Redaelli, J. Wenninger.
Where did all the protons go? Mike Lamont LBOC 20 th January 2015.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LHC Scrubbing Runs Overview H. Bartosik, G. Iadarola, K. Li, L. Mether, A. Romano, G. Rumolo, M. Schenk, G. Arduini ABP information meeting 03/09/2015.
G. Rumolo, G. Iadarola, H. Bartosik, G. Arduini for CMAC#6, 16 August 2012 Many thanks to: V. Baglin, G. Bregliozzi, S. Claudet, O. Dominguez, J. Esteban-
Thursday 21/4 07:30: End of fill #1727. Beam dumped. ALICE compensator magnet fault. Delivered ~6.7 pb -1 in 7.5 h. 11:30 Stable beam # bunches/beam.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
HL-LHC/LIU Joint workshop Goal: Progressing towards an agreed set of 450 GeV beam parameters for High Luminosity operation in LHC after LS2 & LS3. Slides.
Evian 2014 historical perspective run 1: 2010: L peak >10 32 cm -2 s -1  2x10 32 cm -2 s : produce >1 fb -1  delivered.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,
Criteria for dynamic aperture limits and impact of the multipolar errors: summary of the simulations with beam-beam for levelling scenarios at 5 and 7.5x10.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Overview of Wire Compensation for the LHC Jean-Pierre Koutchouk CARE-HHH Meeting on beam-beam effects and beam-beam compensation CERN 08/28/2008.
Linear optics - I Low beta* at injection –Reduction of injection could potentially reduce time to collisions and allow for a more relaxed ramp&squeeze,
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
Mike Lamont An attempt at synthesis Acknowledgements all round
Fabio Follin Delphine Jacquet For the LHC operation team
INTRODUCTION FOR THIS (2nd) REVIEW ON LPL (LHC PERFORMANCE LIMITATIONS) => DURING RUN II ( ) E. Métral Follow-up of (1st) review on LPL during.
Y.Papaphilippou Thanks to
Luminosity monitor and LHC operation
Operating IP8 at high luminosity in the HL-LHC era
Joint LIU / HLLHC day -15 October 2015
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
M.Fitterer, A.Patapenka, A.Valishev (FNAL)
Transverse Damping Requirements
Task 2. 5: Beam-beam studies D. Banfi, J. Barranco, T. Pieloni, A
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Machine Coordinators: G. Arduini, J. Wenninger
Wire, flat beams and beam-beam MDs in 2017
Proposals for 2015 impedance-related MD requests for PSB and SPS
MD2490 Measurement of the TMCI threshold at flat-top
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Β*-reach in 2017 R. Bruce, S. Redaelli, R. De Maria, M. Giovannozzi, A. Mereghetti, D. Mirarchi Acknowledgement: collimation and optics teams, BE/ABP,
MD2490: Measurement of the TMCI Threshold at Flat-Top
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
MD25 ns - 14/12/2012 G. Arduini, H. Bartosik, G. Iadarola, G. Rumolo
Status of LHC Operations
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tuesday TOTEM and transverse loss map (1) OK
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Mike Lamont, Jorg Wenninger
Wednesday 8th August & night
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Chromaticity can make a difference…
Saturday – Morning 7:36 beams dumped
Saturday 7th May Sat – Sun night
Collimation margins and *
HL-LHC operations with LHCb at high luminosity
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Pushing the LHC nominal luminosity with flat beams
Thursday – Morning Energy matching at injection with H CODs
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday :15 fill 3523 dumped by BPMs IP6
Another Immortal Fill….
Large emittance scenario for the Phase II Upgrade of the LHC
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Scenarios for 2017 and 2018 Thanks to Gianni, Fanouria, Gianluigi, Dario, Stephane, Elias, Michi, Jamie, Christoph, Rogelio, Mirko, Riccardo, Hannes, Roderick, Stefano, Xavier,Massimo,…

BCMS versus nominal – performance; x-­‐angle, LRBB, beta BCMS versus nominal – performance; x-­‐angle, LRBB, beta*, intensity, emittance, octupole, chromaticity, TOTEM bump. Nominal optics Vs ATS. Flat optics for 2018?

Reach in β* Assuming as last time a 0.5 σ safety margin on top of calculated aperture For BCMS: can go to β*=30 cm, 160 urad without CMS bump Separation plane limiting With CMS bump: limit goes up to 32 cm For nominal: can go to β*=32 cm, 185 urad Limitation is in crossing plane Even with CMS bump, crossing plane is still limiting, so no change in reach Caveats Aperture not measured in predicted bottleneck with CMS bump Large uncertainty applies! R. Bruce, S. Redaelli

Dario

Dario

BCMS vs Standard Smaller emittance comes with additional DA (beam sigma), by reducing the crossing angle we seem to pay some margin for chromaticity, with some extra margin required for the intensity increase. The fluctuations of the bands show some uncertainty in the study (~2 units of chroma). From experience: BCMS with reduced crossing caused comparable losses as Standard (slide 2).

Dario

Dario

If no non-colliding bunches Stable beam If no non-colliding bunches Ioct => Any value should be possible due to BBHO. Could be 0 or < 0 to optimise the lifetime Q’ => Should be possible to reduce it but it is limited by e-cloud effects… A goal of ~ 10 seems reasonable (after some time) ADT => Higher gain (lower bandwidth) could help to mitigate the emittance blow-up => Should try and optimise it If non-colliding bunches Ioct => Should be limited to the single-beam limit (~ 250 A). However, with the observed nonlinearities in 2016 it should be also possible to reduce and optimize it for lifetime Elias Métral, ABP discussions for Evian and Chamonix, CERN, 06/12/2016 /5

ATS vs nominal, intensity, Crossing angle ATS seems the choice (some potential gain in chromaticity and octupole reach) Nominal optics is able to reach the same beta* and potentially solve issues with CT-PPS Crossing angle and intensity For 1.25e11, 9σ seems aggressive limited by eventual need of high octupoles and chromaticity 10 σ is safe and maybe reduced during the run, when reduction of octupoles and chromaticity is proved possible (as in 2016) Keep the same geometrical crossing angle for nominal Maybe consider crossing angle levelling (2018?)

Nominal vs BCMS

Nominal vs BCMS

LHCb scenario Standard BCMS n1 7.02E+10 n2 f_rev 11270.3931578947 beta_x 5 7 beta_y e_x 3.50E-06 2.50E-06 e_y Energy 6500 s_z 0.08 Xing/2 2.50E-04 s_x 5.02532050259943E-05 s_y S 0.929121002796445 Lb [Hz/cm^2] 1.62724884018469E+029 Xsec [mB] 80 Xsec [cm2] 8E-26 Pile up 1.15506092281782 LHCb max 1.1

Standard vs BCMS Nominal configuration will give us important answers for the long term strategy Little conditioning observed in 2016  for HL-LHC we need to do better! We need to see if a period of operation with long trains can achieve significant further conditioning (~2 months could be a reasonable request) But it could take time (months) to fill the machine, especially if we stick to 1.25e11 288bpi, and S12 is slowing us down Instabilities in stable beams cannot be excluded (can we still increase Q’ to 22 if needed, even having ~9s separation?) BCMS provides better performance on the short-medium term (Run 2) – see Fanouria Even in absence of heat load limitations, integrated luminosity is slightly better for BCMS With the heat load limitations on number of bunches the difference becomes ~30% The difference in luminosity per bunch (20 %) defines a lower bound for the performance loss Intensity ramp-up will most likely be significantly faster (2016-like), and it will be easier to deal with S12 recovery if needed But most likely we will not see more conditioning than in 2016  not much impact on Run 2 performance, but heat loads will come back as a performance limitation for Run 3 and HL-LHC

Overhead of changing between the two Standard vs BCMS Nominal configuration will give us important answers for the long term strategy Little conditioning observed in 2016  for HL-LHC we need to do better! We need to see if a period of operation with long trains can achieve significant further conditioning (~2 months could be a reasonable request) But it could take time (months) to fill the machine, especially if we stick to 1.25e11 288bpi, and S12 is slowing us down Instabilities in stable beams cannot be excluded (can we still increase Q’ to 22 if needed, even having ~9s separation?) BCMS provides better performance on the short-medium term (Run 2) – see Fanouria Even in absence of heat load limitations, integrated luminosity is slightly better for BCMS With the heat load limitations on number of bunches the difference becomes ~30% The difference in luminosity per bunch (20 %) defines a lower bound for the performance loss Intensity ramp-up will most likely be significantly faster (2016-like), and it will be easier to deal with S12 recovery if needed But most likely we will not see more conditioning than in 2016  not much impact on Run 2 performance, but heat loads will come back as a performance limitation for Run 3 and HL-LHC Overhead of changing between the two It would be ideal to be able to change from one to the other “on the fly”, and probe both regimes. What forbids us to do it? Not the b* choice! (b*>=32 cm should be compatible with both, see Roderick) Abort gap keeper and MKI pulse settings, due to this we cannot even have 288bpi at 450 GeV if we go for BCMS!  but in 2016 change required ~1 shift, and used MD block as validation (to my memory, tbc.) Crossing angle setting  According to Jorg’s talk at LSWG “crossing angle knob” is proved in MD. The open question is whether we can have TCT settings compatible with both angle values? (e.g. 155 urad and 180 urad for b* = 33 cm) As discussed many times, this has other advantages (loss management at start of collision, adiabatic exploration of beam-beam limits, anti-leveling…) Did I forget something?

Scenario for 2018 Flat optics? Levelling crossing angle