IEVMC Lesson 8 FY14 Analysis Case Study Performance Management Analysis Tools Student guide page 8-5.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

Module 8: Government Required Reports
N O T E “CLICK” TO CONTINUE… If the slide show is not launched, click on View  Slide Show in the menu bar at the top of the Power Point window. When the.
1 Estimating Costs At Completion Review this tutorial and the Project Pyramid Exercise until you are fully comfortable with how to calculate an estimate.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Chapter 10: Monitoring and Controlling Change
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Chapter 10 Project Monitoring and Control
Project Management 6e..
CPM-400: xxx Lesson B: EV Data Analysis I Instructor Ellen Udell
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Management Methodology Project monitoring and control.
Chapter 13: Progress and Performance Measurement and Evaluation
EARNED VALUE MANAGEMENT (EVM)
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
Microsoft Project – Tutorial 4 Leveling Overallocations In some cases, a resource could be assigned more work in a given time period than it has working.
Mohawk Vehicle - MEGA HERZ ELEC & VEN - MOH-2 F C-0050 J:\CS40\Data Analysis\- Standard Analysis Package/Sample Standard Analysis Package.
Mohawk Vehicle - MOH-2 - F C EVM Quick-Look Report.
Project Management 6e..
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Department of CS & Eng. MSSE Program, © Fissure 1 SOFTWARE PROJECT MANAGEMENT COURSE Executing, Monitoring and Controlling Session #7.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EVM Home Page = Address: DAU POC: (703) (DSN 655) Revised December 2006 TERMINOLOGY.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Earned Value Management EVM. 03/06/2013 Earned Value Management Planned Value (PV): –Budget of the planned work.
MISUSE OF EARNED VALUE MANAGEMENT RESULTS IN ERRONEOUS CONCLUSIONS
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
TOPIC-8B- PROJECT COST CONTROL
Project COST Management
Budget Planning.
Earned Value Management
ENGR 281 Engineering Scholars Program Project Management Life Cycle Overview K. F. Reinschmidt J. L. Frank / Marathon Ashland Petroleum LLC Chair in.
Project Communication, Tracking, and Reporting
Performance Measurement Baseline Contract Price (Project Price)
5. Cost resources & PLAN DURATION
Earned Value Management
EVM 202—Lesson 7 Tools Analysis Case Study
Lesson 4 Responsibility Assignment Matrix Exercise
September 2016 EVM 202—Lesson 8 Integrated Product Team (IPT) Analysis and Performance Case.
Earned Value - What is it
Dave Bachman DAU / CDSC September 9, 2004
Integrated Program Management Case Study Briefing
EVM 202—Lesson 7 Tools Analysis Case Study
September 2016 EVM 202—Lesson 6 Integrated Program Management Analysis Tools and Techniques (Part 1)
An Introduction to Earned Value Performance Measurement
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
Monitoring and Reporting Project Progress
“Earned Schedule and Earned Value Management” The trend mentioned in PMBOK Guide 6 -th edition Presented by Mikayel Nshanyan, PMP®
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
Project Evaluation and Control
Earned Value Management
5. Cost resources & PLAN DURATION
MGT 605: CH-13 Progress and Performance Measurement and Evaluation
5. Project PLAN & cost estimation
Fine-Tuning your plan and obtaining approval
Missile Defense Agency EVM Update
Project Management Life Cycle
Monitoring and Controlling
Managing Project Work, Scope, Schedules, and Cost
Project Evaluation and Control
Presentation transcript:

IEVMC Lesson 8 FY14 Analysis Case Study Performance Management Analysis Tools Student guide page 8-5

Analysis Case Study Objective: Understand the basic operations of EVM tools. wInsight: LAR EMD 2003 MS Project: LAR DEC03 Answer the questions contained in the following viewgraphs. Document your answers on the viewgraphs. Copy from wInsight or Project as necessary to document your answers using Sniping tool. Save under your name in the A Student file folder on the I: drive. Snipping tool can be grabbed from the accessories menu or by typing snip in the search box in the start button if you don’t already have it on your desktop. Once you find it, drag to your bottom toolbar Instructions for use: Click on the snipping tool (will cause a white filter on your screen) Use right mouse click to select the area you want to copy Paste into the chart

WBS Reports: Question 1 Reference the top level Executive Summary. What is the contract number? What is the contract period of performance? What is the contract budget base? What is the performance measurement baseline? What is the target fee in $ & %? What is the difference between CBB & PMB?

WBS Reports: Question 2 Select the engine element, select the AI Narrative Report. What percent of the contract is the engine? Based on wInsight data, is the work in process ahead or behind schedule? What is the cumulative cost variance in $?

WBS Reports: Question 3 Select engine, select the Six Period Summary Report. What are the cumulative cost and schedule variances in dollars & percent? Is the contractor projecting an overrun or underrun? What does the comparison of the percent complete versus the percent spent reveal? How does the Contractor EAC TCPI compare to the CPIcum? What does this comparison tell you about the estimate?

WBS Reports: Question 4 Select engine, select the Six Period Summary Report. What is the EAC based on CPIcur? Compare this with the EAC based on CPIcum and CPI*SPI. Is the EAC (CPIcur) within a reasonable estimate range? Why or why not? What does this imply about using current CPI for EAC calculations? Normally the EAC based CPI*SPI is the worst case. Why is EAC (CPI*SPI) not the worst case estimate here?

WBS Charts: Question 1 Reference the top level management chart, C/S Variance Trends. What are the cumulative cost and schedule variances? Are they within the 10% thresholds? How much Management Reserve (MR) is available at this time? What is the historical trend of the Management Reserve? What does this mean?

WBS Charts: Question 2 Reference the top level management chart, Contract Performance. What is the CBB? What is the Government Program Manager’s Estimate? What is the Contractor Program Manager’s Estimate? Why would they be different?

WBS Charts: Question 3 Reference the top level SPI chart. What is the cumulative SPI for Increda? How would you explain the cumulative SPI in terms of a dollar of work scheduled? What has been the recent trend of the cumulative SPI for Increda If the trend continues, do you believe the cumulative SPI for Increda will be above 1.0, equal to 1.0 or less than 1.0 at the end of the contract? Does the cumulative SPI tell you how many days the contract end date will slip?

WBS Charts: Question 4 Reference the top level CPI chart. What is the cumulative CPI for Increda? How would you explain the cumulative CPI in terms of a dollar spent? What has been the recent trend of the cumulative CPI for Increda? If the trend continues, do you believe the cumulative CPI for Increda will be above 1.0, equal to 1.0 or less than 1.0 at the end of the contract? Compare the cumulative CPI to the TCPI for Increda’s EAC. What do you conclude?

WBS Charts: Question 5 Reference the top level EAC chart: BAC, Increda’s EAC and the CPI Cum forecast. Is the contractor projecting an overrun or underrun? Is the CPI Cum forecast projecting an overrun or under run? Why is the contractor EAC reasonable or unreasonable?

WBS Charts: Question 6 Reference the top level Cumulative Variance chart: COST, SCHED, and VAC. Is the contractor projecting an overrun or underrun? If the cost and schedule trends continue what would you predict about this contract (overrun – underrun? finish on schedule or late?) What can you determine about the contractor’s EAC and the contracts BAC? Is the Contractor’s EAC reasonable or unreasonable; and why?

WBS Sort Windows: Question 1 Reference the Cumulative Cost Variance $ and Cumulative Cost Variance %, in the sort windows only. What are the three worst, lowest level, WBS elements in terms of Cumulative Cost Variance in dollars? What are the three worst, lowest level, WBS elements in terms of Cumulative Cost Variance in percent?

WBS Sort Windows: Question 2 Reference the Schedule Variance, in the sort windows only. What are the three worst, lowest level, WBS elements in terms of Cumulative Schedule Variance in dollars? What are the three worst, lowest level, WBS elements in terms of Cumulative Schedule Variance percentage? What other information do you need to determine if these are schedule drivers?

WBS Sort Windows: Question 3 Compare the three worst, lowest level, WBS elements for Cumulative Cost Variance with their Variance at Completions, in the sort windows only. Based on the current status, how reasonable are the contractor’s EACs?

OBS Charts: Question 1 Select the wInsight OBS Structure and the Program Control Organization. Review and compare the cumulative variance chart and the manpower chart and answer the following questions: What earned value technique is being used by the Program Control? Using the actual line from manpower chart, explain the DEC 03 cumulative CV and SV metrics. Using the EAC (or LRE) and BAC lines on the manpower chart, predict the current cost and schedule variance percents for Jan 04, Feb 04, Mar 04, Apr04, and May 04.

IPT Sort Question: Question 1 Select the wInsight IPT Structure and the “indent” button. Also add the “WbsNum” column to the sort database. What are the sub-elements of the VEHICLE IPT What are the WBS levels of the VEHICLE IPT sub-elements and how do these levels compare to the WBS levels in the wInsight WBS Structure What are the sub-elements of the DRIVE TRAIN IPT What are the WBS levels of the DRIVE TRAIN IPT sub-elements and how do these levels compare to the WBS levels in the wInsight WBS Structure

IPT Sort Question: Question 2 Sort the wInsight IPT Structure for Sort By “ElemLevel” and Then By “CvCum”. Copy the level 1 and 2 IPT element metrics from wInsight into this presentation (hint you should copy 13 lines). After accomplishing this task return to the WBS structure.

Schedule Correlation: Question 1 Reference MSProject LAR DEC03, filter for the Critical Path. What tasks are identified on the critical path from now until the CDR? Do these correspond with those obtained from the schedule variance dollar sort in wInsight? Do these correspond with those obtained from the schedule variance percent sort in wInsight?

Schedule Correlation: Question 2 Reference MSProject, LAR Dec 03 filter for the Milestones. When is the PDR scheduled? When is the CDR scheduled? When is the Production Prototype Scheduled for delivery.

Schedule Correlation: Question 3 Reference MSProject for LAR Dec 03, filter for the Slipping Tasks (in more filters). Which five preliminary designs have slipped? What is the status of the Secondary Armament's Sub System Trades & Analysis? Stated in terms of task duration, slip from baseline, current schedule status. Are any of the five Preliminary Design tasks on the critical path? If not, how much float time (or slack) time does each have.

Schedule Health: Question 1 Open Steelray with the Dec 03 schedule and scorecard then select the analyze button. What Percentage of the LAR schedule are Summary Tasks? What does Baseline Execution Index mean? (Hint select the information button for definitions) Reference MSProject, LAR Dec 03 How many tasks should have been completed, but are still in progress? Which tasks have not finished?