Oleksiy Dolinskyy December 1st, 2014

Slides:



Advertisements
Similar presentations
Mitglied der Helmholtz-Gemeinschaft Beam Cooling at HESR in the FAIR Project 12 th September 2011 Dieter Prasuhn.
Advertisements

FAIR Synchrotrons SIS100/300
C. Dimopoulou A. Dolinskii, T. Katayama, D. Möhl, F. Nolden,
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Peter Spiller, IHEP, Protvino GSI, Peter Spiller IHEP FAIR in kind Contributions.
PLANS JINR PARTICIPATION for JINR PARTICIPATION FAIR PROJECT: in the FAIR PROJECT: - ACCELERATOR TECHNOLOGY A.Kovalenko 103 session of the JINR Scientific.
UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Sergey Kozub Institute for High Energy Physics Protvino, Russia SIS300 meeting 19 March, 2009 Sergey.
Bob Lill LCLS FAC June 16-18, 2008 RF BPM Status and Production Test Results.
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
BINP for FAIR Yu.Shatunov Moscow May Research and Development Contract between GSI and BINP 1. Kickers for synchrotrons and storage rings.
HIE-ISOLDE Design Study and the CATHI Project Richard Catherall EN-STI ISOLDE Technical Coordinator HIE-EBIS Workshop 16 th -17 th October CERN.
HESR 2 Electron Cooling Björn Gålnander The Svedberg Laboratory Uppsala University Midterm Review, DIRACsecondary-Beams December 8, 2006 GSI, Darmstadt.
Magnet designs for Super-FRS and CR
IHEP participation in SIS300 production UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Institute for High Energy Physics Protvino, Russia FAIR meeting.
Few slides from J. Fox’ talk in last November’s LARP meeting LARP CM
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
October 4-5, Electron Lens Beam Physics Overview Yun Luo for RHIC e-lens team October 4-5, 2010 Electron Lens.
TBL as a 12 GHz power source, overview and first results from commissioning IWLC 2010 workshopSteffen Döbert, BE-RF  Current status of TBL  Status of.
Peter Spiller, DIRAC Kick-off meeting Peter Spiller Design Study Group DIRAC kick-off meeting SIS100.
1 Flux concentrator for SuperKEKB Kamitani Takuya IWLC October.20.
SLHC Introduction to the “Workshop on Cryogenics and Vacuum Sectorization of the SPL” R. Garoby – 9/11/2009.
Development of the Room Temperature CH-DTL in the frame of the HIPPI-CARE Project Gianluigi Clemente,
Proposal for LHC Microwave Schottky Pickups Ralph J. Pasquinelli 3/9/2005.
Design and construction of Nuclotron-based Ion Collider fAcility (NICA) and Mixed Phase Detector (MPD) Design and construction of Nuclotron-based Ion Collider.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
Run II PMG 1/19/06 Pushpa Bhat 1 Run II Upgrades Status January 2006 Pushpa Bhat.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
 NICA is being constructed  For heavy ions we need very highluminosity level – 10 cm s  For keeping up such level we inevitably need cooling  Stochastic.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
Beam Diagnostics Seminar, Nov.05, 2009 Das Tune-Meßverfahren für das neue POSI am SIS-18 U. Rauch GSI - Strahldiagnose.
CR: status and activities at BINP I.Koop, BINP, Novosibirsk O.Dolinskyy, GSI,Darmstadt , MAC, GSI, Darmstadt.
Oleksiy Dolinskyy 23 rd October, FAIR layout of accelerators Collector Ring.
Contents: -GSI organization structures -Tasks of GSI (accelerator) -Status of evaluations / technical developments -Overview -Note : (only) accelerator.
1CEA/ Saclay/ SACM CARE/SRF/WP11 Development of a new Beam Position Monitor for FLASH, XFEL and ILC Cryomodules Claire Simon, Michel Luong, Stéphane Chel,
Peter Spiller, November 2012, Structure and Tasks of the Project Division Primary Beams Peter Spiller Machine Advisory Committee Meeting.
TBL experimental program, evolution to RF power testing in TBL ACE 2011, February 2-3Steffen Döbert, BE-RF  Current status of TBL  Experimental program.
The Collector Ring at FAIR Dmitriy Berkaev IWAPT 2015, BINP, Novosibirsk D. Berkaev. The Collector Ring at FAIR1.
Preparation Phase of the FAIR Project
Status of the FAIR Project
Oleksiy Dolinskyy 1st December, 2014
Stochastic cooling system: Start-up and project modes
High energy beam transport.
ESR Slow highly charged ions and antiprotons
Phase Feed-Forward Piotr Skowroński (CERN)
Schedule for the FAIR Antiproton Target
Beam diagnostics from GSI
Status of HESR 18th March Gießen Dieter Prasuhn.
Testing of SC Magnets Status - November 2010
Jorge Sánchez-Quesada BE-RF-FB
Test of Optical Stochastic Cooling in CESR
Complementary ISTC Projects #3888, 3889p
BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016
(Procurement, testing of magnets)
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Hosting Orsay Walid KAABI
Status of the PANDA Magnet
SIS100 quadrupole status S. Kostromin, H. Khodzhibagiyan, G. Trubnikov, FAIR 11th MAC, GSI, May,
A. Al-khateeb, O. Chorniy, R. Hasse, V. Kornilov, O. Boine-F
Planned measures for improving the SIS18 spill quality
Status of the PANDA Solenoid Magnet Production in BINP
    BEAM POSITION MONITORS USING A RE-ENTRANT CAVITY C. Simon1, S. Chel1, M. Luong1, P. Contrepois1, P. Girardot1, N. Baboi2 and N. Rouvière3.
HIE-LINAC status report
CLIC damping rings working plan towards the CDR
Status of the PANDA Solenoid Magnet Production in BINP
ILIMA Experiments in the CR
Undulator Cavity BPM System Status
HESR for SPARC 25th November FAIR MAC Dieter Prasuhn.
PANDA Forward Spectrometer Calorimeter (Shashlyk) status and plans
ELENA / AD Pick-ups and Schottky
Presentation transcript:

Oleksiy Dolinskyy December 1st, 2014 GSI activity at CR project Oleksiy Dolinskyy December 1st, 2014

Last main events The Collaboration Contract for technical coordination of Construction of CR machine between FAIR and BINP has been signed in August 2014. In frame of this contract the first two working meetings of BINP with GSI and FAIR experts took place last month

GSI activity after last workshop - Dipole magnet specifications - Optics simulations System design RF system construction - SC cooling construction - Beam diagnostic - Experimental devices

Dipole magnet specifications The final specifications prepared by GSI and BINP experts has been officially approved by all parties (FAIR, BINP and GSI) in September 2014. The contract between FAIR and BINP for the dipole production is under preparation by FAIR.

Optics simulations Ion optical simulations were performed together with BINP colleagues. Some results of simulations have been presented in the STORI14 Conference. Antiproton yield in the chain “target –separator-ring” has been proved for GSI and BINP optics (see the Dolinskyy’s talk) 2. Octupole correction in Isochronous mode was analyzed (see Litvinov’s talk) 3. Possible improvement of pbar-beam parameters for the HESR has been studied (see the special session “Stochastic cooling at CR”).

System Design present layout of the CR, RESR and building 3D CATIA model of the ring and building is continued and completed . the supply room for the RF cavities has been modified. Change Request has been prepared and submitted for approval. The MSV version of the CR machine shown in figure

System Design Thorsten Ziglasch gives the presentation After upgrade the following components must be added: RESR ring, 5 RF cavities; SC Pick-UP and Kicker; power supply, cables. The planning of these components is done now. Thorsten Ziglasch gives the presentation about building and cable planning. The MSV version of the building without RESR and its infrastructure is under preparation.

RF sytsem 5 RF cavities produced by GSI must be integrated into the CR. The space for the 5 additional RF cavities must be reserved

Status RF system Cavity, power amplifier, amplitude control - Contract with Research Instruments (Germany) is signed Final set of manufacturing documents has been reviewed. Minor modifications are required. Revised mechanical models of cavity and power amplifier included in CR DB DMU. Production of pre-series system is running Power supply units - Conceptual Design Report has been delivered to GSI - Procurement of 5 power supply units is started - Pre-series system is expected in the middle of 2015

Stochastic cooling 1 Kicker (2-4 GHz) 1 Pick-Up (2-4 GHz) MSV version 2 Pickup tanks (1-2 GHz) 2 Kicker tanks (1-2 GHz) 1 Palmer Pickup tank produced by GSI must be integrated in the CR After CR upgrade 1 – Pickup tank (2-4 GHz) 1 – Kicker tank (2-4 GHz) The space and infrastrucutre must be reserved now. Palmer cooling PU 1 Pick-Up (2-4 GHz) 2 Pick-Ups (1-2 GHz)

Status Stochastic Cooling System Prototype stochastic cooling tank with PU movers, cold heads (20 K) and cooled pre-amplifiers 2 new linear motor drive units designed and manufactured, assembled and now under test (mechanical, electronics, software) Prototype electrode (ß = 0.83-0.97)

Status Stochastic cooling Pick-up tanks and electrodes: Prototype Pick-Up tank is ongoing to reassembly, tests at very low temperature. -Motor drive units: successfully tested, improvements underway; emergency switch in fabrication for work safety. -First successful function test of He cryoheads and cryocompressors. -Ongoing preparations for cryotests in the tank. Palmer pick-up: Engineering activities for Faltin electrodes: -Manufacturing/procurement of prototype Faltin electrodes underway; -HF Simulations on mode damping in the tank. Kicker electrodes and it tanks: No activity Software: - FOPLEQ 1D, 2D codes has been developed (Solution of Focker-Planck Equation (1D, 2D)) -MPT code is developed (Multi Particle Tracking in time domain approach) RF- electronics: Contract for production of 34 power amplifiers has been signed. Procurement is started. First (prototype) amplifier is expected in the middle of 2014. Preparation of infrastructure for SAT. (see the C.Domopoulou’s talk for more details)

Beam diagnostic Cryogenic Current Comparator (CCC) (GSI in - kind) One common design (for SIS100, HEBT, CR, CERN AD is under development by GSI and CERN collaboration. Schottky Pick-Up ( ITEP in-kind, Moskow ) (the specs is reconsidered by GSI experts) Tune BTF exciter (ITEP in-kind, Moskow ) (the specs is under prepararation by GSI experts)

Beam diagnostic (Schottky detector) The specifications for Schottky pick-up has been prepared and approved Schottky pick-up construction is assigned to ITEP, Moskow (Russia In-Kind) The prepared specifications of Schottky pick-up is checked by experts from ILIMA collaboration. Final decision will be done in December 2014

Schottky detector CR Schottky SIS100 Schottky Schottky pick-up   Number of elements 1 Overall length mm 1000 Horizontal aperture 200 Vertical aperture Bandwidth MHz 5-100 Frequency resolution 2×10-7 Absolute frequency value Tune measurement resolution 10-5 Intensity range 106 -1011 Which type of Schottky detector to apply at CR Pick-up plates (like SIS100) ? Resonator cavity type (R@D is still required) Narrow band resonator cavities (several units are needed)

Schottky resonators in CR 14 Schottky resonators are planned to install in the ring for mass measurements. Shahab Sanjari will present the conceptual design of these resonators.

Other activities - Stability properties of the dipole magnet versus current ripple was studied by Y.Shim (see his talk in this workshop). - TOF detectors is under development at Giessen University (see the talk of M.Diwisch).