MOVING FORWARD!!
Cooling Pond S/S Ponds Channels Coke Ovens Brook WTP Cutoff Wall GW Collection Tar Cell Cutoff Wall Landfill
Design at 95% ( Fall ’07 – Summer ’08) On Site Landfill
Channels in North and South Ponds (Fall ’07 – Fall/Winter ’09) Design at 100% Channels in North and South Ponds (Fall ’07 – Fall/Winter ’09) Floating Navigational Barrier
(Fall ’07 Start) Access Road Ferry St. Containment Cells for Sediments from Channels
Build Access Road Along Shoreline Infill for Access
Pile System Installation
New Channels By Spring of ‘10
Solidification and Stabilization Auger Excavator Sheet Piles Solidification and Stabilization
Design at 75% Start Fall ’07 to 2014
Transport Brook Sediments Design at 95% (Start Spring ’08) Transport Brook Sediments For S/S Treatment Tar Cell
Design at 75% (Spring ’08 to 2012) Capped Area
Design at 75% Cutoff Walls (Spring ’08 – Spring ’09)
Design at 50% WTP Fall ‘08 – Spring ‘10 Capping Ongoing
Design at 75% Tar Cell (2011 – 2012)
Cooling Pond S/S Ponds Channels Coke Ovens Brook WTP Cutoff Wall GW Collection Tar Cell Cutoff Wall Landfill