FCC Civil Engineering Optimisation and Design Development

Slides:



Advertisements
Similar presentations
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
Advertisements

CFS challenges for a linear collider J.Osborne CERN ILC-GDE Dubna - 4 June 2008 OUTLINE : Introduction Civil Engineering -Geology (water, stability issues.
3/2011 CFS BTR Global Design Effort 1 Americas Region Civil Design Tom Lackowski.
John Osborne GS/SE March 2013
Yung Loo FCC: GIS & Tunnelling Update.
Infrastructure & Operation 27 th May 2015 Infrastructure & Operation 27 th May 2015 Update on optimisation of tunnel footprint and location Charlie Cook.
Investigation of FCC position Impacts on Hadron Injectors John Osborne, Charlie Cook, Yung Loo (ARUP) 16/09/2014.
TOT-FCC: Tunnel Optimisation Tool for the Future Circular Collider Introduction and lessons learnt C. Cook, J. Osborne, P. Lebrun, Y. Robert, M. Jones,
Geotechnical & Civil Engineering Studies Future Circular Colliders (FCC)
FCC Tunnel Civil Engineering and Geology John Osborne (CERN GS-SE) 4 April 2014.
Fred Asiri1 Conventional Facilities and Siting Global Group (CFS) SLAC Update Conventional Facilities and Siting Global Group (CFS) SLAC Update November.
LCWS14 - Belgrade October 6-10, 2014 Conventional Facilities & Siting Working Group Summary V Kuchler, M Miyahara, J Osborne.
HF2014 Workshop, Beijing, China October 9 th -12 th, 2014 Constraints on FCC-ee lattice design Bastian Haerer Constraints on the.
November 17, st XFEL / ILC Meeting 1 ILC GLOBAL Design Effort The Current ILC Twin Tunnel Design Wilhelm Bialowons and Nicholas Walker · MPY.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
TILC08 - WG1 Summary Global Design Effort 1 TILC08 仙台 GDE 会議 WG-1 活動報告 GDE 活動報告会 3月11日10:00- 3号館7階会議室 設楽
Contents Scope of Work and Work Stages
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
Global Design Effort - CFS ILC10 Beijing, March, Single-Tunnel Accelerator Configuration Of Asian Region Atsushi Enomoto (KEK)
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
John Osborne : GS-SEM Civil Engineering 18 May 2009 CES 9 June News from ILC Japan CFS review 1-3 June 2010 :
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Summary Session Infrastructure and Operation P.Collier & Ph. Lebrun.
General Infrastructures Services Department Civil Engineering planning for LSS4 Option, presented at review workshop 30/7/ months Planning and Resources:
FHI 32: FCC tunnel layout and transferline update Tuesday, 9 February 2016 CE Updates: Comparison of 100km Intersecting and Non-Intersecting options New.
MDI 9 th Meeting - 22 nd January 2016 FCC Experimental Caverns - Feasibility and Excavation C. Cook (GS), J. Osborne (GS),
FCC-hh MDI 5 th Meeting Friday 13 th March 2015 Civil Engineering Layouts for Experimental Caverns – First Draft Charlie Cook (GS), John Osborne (GS)
Infrastructure and Operation meeting 20 th January 2016 Amberg’s Report Summary : Comparison of 100km Intersecting and Non-Intersecting options C. Cook.
Survey Meeting John Osborne, CERN 8 February 2016
ILC J.Osborne / A.Kosmicki / B.List – March 22 th 2012 CFS update for Europe.
Review of FCC tunnel footprint & implementation Introduction & scope Philippe Lebrun Review of FCC tunnel footprint & implementation CERN, 11 June 2015.
Matt Sykes Andy Kervell Yung Loo Heidi Clough Craig Sturzaker ARUP: Update on GIS Model and tunnel options under lake.
HF2014 Workshop, Beijing, China 9-12 October 2014 Constraints on FCC-ee lattice design Bastian Haerer Constraints on the FCC-ee.
WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Review of FCC tunnel footprint & implementation Outcome & conclusions Austin Ball, Paul Collier, Massimo Giovannozzi Philippe Lebrun (chair), Lluis Miralles,
RISK ASSESSMENT FCC draft, 2. September 2015.
FCC Underground Infrastructure
Layout Daniel Schulte for the FCC-hh teams ALBA, November 2016.
Civil Engineering for FCC-eh and LHeC
LHeC Coordination Meeting, 9 June 2017
CERN Construction Planning and Scheduling (LHC installation)
Civil Engineering update - alignment configuration
CLIC Civil Engineering Update
CLIC Civil Engineering Update
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
1st FCC Infrastructure & Operation meeting
Marco Oriunno (SLAC), March 12, 2014 MDI WG
CLIC Civil Engineering & Infrastructure
FCC Civil Engineering John Osborne & Jo Stanyard (SMB - Site Engineering - FAS Section) FCC week outline 10th May 2017.
Acknowledgements to all FCC study teams
Selected comments and recommendations of the International Advisory Committee - Comments/replies from IOWG Resulting actions V. Mertens IOWG
CLIC / ILC Collaboration for CFS works
Interaction Region Alternative Layouts
5th FCC Infrastructure & Operation meeting
FCC Civil Engineering update
Latest ILC tunnel cross section May 2017
FCC-ee MDI Civil Engineering update
Tunnelling under lake Geneva
ILC DRAFT CONSTRUCTION SCHEDULE Flat topography & Mountainous sites
Civil Engineering for FCC-eh IR
CLIC Civil Engineering Update
Infrastructure and Operation Summary
Overview of Day One – 29 Feb 2016
Workshop on fire protection for physics research facilities
FCC Week 2019 Civil Engineering Summary
Presentation transcript:

FCC Civil Engineering Optimisation and Design Development John Osborne & Joanna Stanyard (SMB - Site Engineering - FAS Section) With acknowledgements to I&O and all FCC study teams

Brief history of previous layouts and positions Outline Brief history of previous layouts and positions Layout & siting progress since Rome 2016 Design development of structures Cost & Schedule study Future steps John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Brief History of Previous Layouts and Positions European Strategy, Krakow 2012: 80km Options During pre-feasibility an 80 km layout was considered with 2 distinct positions: Jura mountains v lakeside Kick-off meeting, Geneva 2014 The two 80 km options were reviewed in addition to a 47 km option. Washington 2015: Multiples of LHC Considered in 80 km, 87 km , 93 km, 100 km In addition to the 80 km option, other multiples of the LHC were considered: 87 km, 93 km, 100 km. Rome 2016: Intersecting v non-intersecting 100 km options considered August 2016: 97.75 km options introduced in comparison to Intersecting option (V1) A variety of options were considered to identify the optimal layout for the machine whilst fitting within the geological constraints. “Intersecting” option Challenges: 7.8km tunnelling through Jura limestone 300m-400m deep shafts and caverns in molasse “Non-Intersecting” option Challenges: 11.6km tunnelling through Prealps geology 1.35km maximum tunnel overburden 80 km (3.0x LHC) 87 km (3.25x LHC) 93 km (3.75x LHC) 100 km (4x LHC) John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Comparison Criteria 1. Geology along alignment: 2. Shaft length: Maximum proportion of tunnel in molasse. Avoid limestone formations wherever possible due to associate risk of water ingress and karsts. Avoid water bearing moraines wherever possible due to risk of water ingress and potential contamination of water sources. Minimise overburden. 2. Shaft length: Minimise total shaft length. Avoid individual very deep shafts, particularly at experimental points where there are multiple shafts. 3. Geology of shafts and caverns The greater the depth of the moraine before reaching the molasse layer, the more costly/ time consuming the construction. Cavern construction requires good ground conditions. 4. Environmental Constraints Avoid protected water sources. 5. Shaft Surface Locations Initial assessment to avoid clashes with buildings, natural features or protected zones. Followed by a more refined assessment of feasibility including potential access to the site. 6. Injection Line Length + Additional ‘softer criteria’ John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Layout & Siting review since FCC week Rome 2016 (1) The round of optimisation undertaken in August 2016 led to the selection of the current 97.75 km layout. In early 2017 small variations on this layout were assessed that incorporated increased L_sep. Reduced straight sections at points J & D enabled the tunnel to fit between Jura and Pre-Alps limestone. Introduced potential for significant shaft depth savings. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Selected Baseline – Berlin97.75 Highlights: Avoids Jura and Pre-Alps limestone. Only one sector containing limestone. Significantly reduced total shaft length. Experimental Site at Point A on existing CERN land. Avoids extremely large overburden. Mandallaz Lake Geneva Vallée de l‘Arve Les Usses Le Rhône John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Key Issues and Possible Solutions – Berlin97.75 Issue: Tunnel excavation through water bearing moraines Possible Solutions: Excavation using a multi-mode earth pressure balanced TBM. Employ a double-lining method for waterproofing. Issue: Unavoidable Mandallaz Limestone formation Possible Solutions: Drill & Blast excavation method Systematic exploration ahead of excavation Issue: Exceptionally deep shaft at point F Possible Solutions: Remove shaft Replace with a shaft of a smaller diameter Replace with an inclined access tunnel John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

TOT capabilities & Limitations TOT is a bespoke, web-based geological tool. Datasets imbedded: Interpreted geological data, simplified to major types of geology. Topography Hydrological Information Protected areas Existing Boreholes and Geothermal farms Very powerful tool for early stage feasibility Quickly assess different layout options. Clear visual outputs for communicating results John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

TOT capabilities & Limitations TOT is only as powerful as the data behind it. Topographical data is very accurate Certain areas of geological data more accurate than others. Interpreted data from existing maps and boreholes. Site Investigation is required to significantly improve understanding. Automation of the tool is a possibility but challenging. Optimisation algorithm such as ROXIE (previously used at CERN for magnet design optimisation) could be used. The challenge is the large number of variables. Not all variables are easily quantified. Potential for automating certain features such as shaft positions once the layout and siting are fixed. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Underground Schematic Secondary experimental Points moved to B & L Electrical alcoves introduced at 1.5 km spacing Additional shaft introduced at each experimental point Beam Dumps both located at Point D Survey Galleries introduced at experimental points John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Surface – Initial Concept Preliminary Layout Concept based on LHC and Hi-Lumi reference structures. Some scaling where deemed appropriate. Concept for non-experimental point John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Cost and Schedule Study Cost & Schedule Study launched in September 2016 Two sets of consultants engaged to work independently. Phase 1 Cost & Schedule estimate for “baseline” single tunnel design.* Phase 2 Cost & Schedule implications of variations considered: Double tunnel design Shallow option Alternative tunnel diameters Alternative shaft diameters Alternative cavern dimensions ee machine requirements Alternative schedule + Inclined access tunnels Phase 3 Refinement of results from Phases 1 and 2: Review to include updates made to baselined design. Incorporate desirable variations from Phase 2. *Some changes have been made since the study was launched including raising the profile and introduction of third shaft at experimental points. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

ee machine requirements Tunnel widening required around points A & G to accommodate ee lattice. Design is not fully developed: potential for a combination of double tunnel and enlargement caverns to accommodate lattice. For Cost & Schedule study: 1.8 km of tunnel widening on either side of IPs at A and G considered. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Inclined Access Study Study launched with Amberg Engineering following FCC week 2016 to verify feasibility of inclined access tunnels. Main questions: Can a shaft be replaced with a 6.0 m diameter tunnel and a TBM be launched from the bottom? What is the estimate for possible time saving? Feasibility of logistics confirmed. Confirmed that some time reductions are possible – construction of inclined access can start during procurement of TBM. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Possible Inclined Access Tunnel Locations Inclined alternatives: 14.9 % slope = 2560m 6% slope = 4800m Inclined alternatives: 11.9% slope = 1500m Inclined alternatives: Approx. 200m Replacing shafts with inclined access tunnels: Shaft F 2) Inclined access between shafts to accelerate program: Option a: between I & J and J & K Option b: between G & H Option b is favourable as it is desirable for the installation schedule for 2 of the shorter sectors to be delivered first. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Early schedule results – Baseline Draft to be verified. Construction complete in 6 years, 5 months. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Early schedule results – Baseline Draft to be verified. Construction commences with site installation and diaphragm wall construction. PM-B excavated first followed by US-B, TBM launched from this cavern for sectors R-AB and R-LA. PX-B and UX-B excavated in parallel but have a longer duration due to their larger dimensions. Second TBM launched following completion of both caverns. Transfer tunnel excavated using Drill & Blast or roadheader. Alcoves excavated behind tunnel excavation front and lined during TBM removal. Lining of tunnels and caverns completes underground construction. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Early schedule results – Accelerated schedule (1) Draft to be verified. First two sectors complete in 4 years, 8 months. Construction complete in 6 years, 5 months. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Early schedule results – Accelerated schedule (2) Draft to be verified. First two sectors complete in 4 years, 11 months. Construction complete in 6 years, 5 months. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Future steps for Cost & Schedule study Work to refine a cost estimate to an accuracy of +/- 30%. Design updates to be incorporated into Phase 3: Additional shaft at each experimental point. New layout and position. New cross-section. Fix inclined access positions and incorporate results into study. More closely study the schedule implications of the connection to the LHC or SPS. Scope for optimising the whole schedule once design and schedule constraints fixed. Iterative process of integrating the CE schedule into the full installation schedule. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

FCC-eh civil engineering FCC experimental point L. LHC/SPS Civil Engineering for FCC-eh IR – J.L Stanyard Thursday 14:25 John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

High Energy LHC Civil Engineering SPS beam dump tunnel enlargement If it is concluded High Energy LHC cannot fit into the current LHC envelope, a technical and cost and study will be launched to evaluate an option to enlarge the cross-section of the existing tunnel. Crossrail – Cross Passage Temporary Frames John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)

Future Steps Continue to evaluate new layout and position: Confirm shaft and inclined access tunnel locations. Evaluate the risk of construction in the moraines under the lake. Confirm civil engineering requirements for ee machine. Evaluate cavern and shaft construction methods. Develop TOT, potentially working towards automating some features. Environmental impact and spoil management study. Develop High Energy LHC and FCC-eh studies. Site investigation planning. John Osborne, Joanna Stanyard (SMB-SE-FAS) FCC Week, Berlin 2017 John Osborne, Joanna Stanyard (CERN-SMB-SE)