Situation of the Static Var Compensators at CERN.

Slides:



Advertisements
Similar presentations
André Augustinus 16 June 2003 DCS Workshop Safety.
Advertisements

NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
UPS Improvements to Beam Availability at the Australian Synchrotron Light Source Don McGilvery.
Operation TCR 2 nd of July to 10 th of September 2001 More than 20 major events Events grouped by equipment group and zone affected.
Disconnect Switches There are many purposes for disconnect switches in substations and power lines. They are used to isolate or deenergize equipment for.
System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS Facilitator Team.
ET2105 Electrical Power System Essentials
PSB Main Power Supply Serge Pittet Jean-Paul Burnet, Karsten Kahle, Fulvio Boattini, Max Chamiot-Clerc TE-EPC Serge PITTET LIU-2011 Event, 25/11/2011.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March ELECTRICAL NETWORK: 18 KV NETWORK REVIEW AND STATUS OF THE SPS CONSOLIDATION PLAN D. Bozzini on.
17.March Connection to the CERN Power System of the TT2 mercury target project by Karsten KAHLE (TS-EL)
Power converters implications for Booster Energy Upgrade Jean-Paul Burnet, Serge Pittet LIU day, TEEPC.
CONSOLIDATION ON CIVIL ENGINEERING AND TECHNICAL INFRASTRUCTURE P. Alves, M. Nonis, P. Pepinster, W. van Baaren 6 th ST Workshop – March 2003.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Trieste (IT), 20 may 2008POPCA A novel 60 MW Pulsed Power System based on Capacitive Energy Storage for CERN PS machine Jean-Paul BURNET CERN, European.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Jean-Paul BURNET, AB/PO ATC-ABOC days, 22 January 2007 PS Main Power System: What has been done from June 2006? What will be the situation in 2007? PS.
First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,
J. Pedersen, ST/EL Consolidation of the CERN technical infrastructure and civil engineering. J. Pedersen ST 6 th ST workshop, Thoiry, 1 – 3 April 2003.
Power Quality Karsten KAHLE Electric Power Converter Group (TE-EPC) High Power Converter Section Review of CERN’s Electrical Power Network October.
Static Var Compensator Status (SVCs for Booster and SPS) Situation in 2009 Karsten KAHLE, TE-EPC ATOP days March 2009.
ATC/ABOC Days, 22 January 2007 The safety electrical networks at CERN Anne Funken, TS-EL.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
ABOC/ATC days Electrical Network: Selectivity and Protection Plan José Carlos GASCON TS–EL Group 22 January 2007.
THE NEW STATIC VAR COMPENSATOR FOR SPS – COMMISSIONING RESULTS based on the CIRED2003 conference paper from K. Kahle, J. Pedersen (CERN) and T. Larsson,
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
LARSSON SE Session 2 – Block 2 Barcelona May The new 150 Mvar, 18 kV SVC at CERN – background, design and commissioning K. Kahle, J Pedersen,
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
A second Thyristor Controlled Static Var Compensator for SPS
Ans Pardons (with input from Jean-Marc Cravero) CERN CNGS Horn Experience (issues since NBI2010) Ans Pardons, CERN 1 NBI2012.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
POWER QUALITY AND NETWORK DISTURBANCES in CERN’s electrical network K. KAHLE, TS-EL Diploma students R. Sternberger, M. Neubert 1 st TS Workshop Archamps,
Roberto Saban/TSPS&SPS Days – January 2005 the background Following a request by the DG and after a comprehensive tour of the responsibilities of the Department,
Mikhail Ovsienko TE-MPE-EE
TE-CRG Activities A. Perin, on behalf on the Cryogenics Group.
YETS & LS2 Works EN-EL / Power distribution
Session 1: Major Events in 2006
CONS and HL-LHC day Analysis of needs from TE-EPC
ABT-EC EYETS Activities 2nd reports
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
LBDS TSU & AS-I failure report (Sept. 2016)
Update on the Critical Path of the PS Booster Schedule for the EYETS
SIMULATION AND IMPLEMENTATION OF FC-TCR
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
the high-voltage network of CERN ToMORROW
Installations, modifications, consolidation in 2005:
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
Renovation of the 45-year old PS magnets
the CERN Electrical network protection system
SPS activities during LS2 TE-EPC (Power Converter Group)
YETS & LS2 Works EN-EL / Power distribution
Transmission Solutions
POPS Strategy for Restarting & Repairing
F Duval, on behalf of EN/EL
DEC System Voltage Planning - June 2018
Yesterday Issue of injection kicker not pulsing:
F Duval, on behalf of EN/EL
Experimental Areas – LS2 planning
ILO Industrial Opportunities Days, 6-7 June 2019
Presentation transcript:

Situation of the Static Var Compensators at CERN. ABOC / ATC workshop 22 January 2007 Situation of the Static Var Compensators at CERN. Risk analysis, maintenance and consolidation strategy Karsten KAHLE, TS-EL

Situation of the Static Var Compensators at CERN ABOC / ATC workshop 22 January 2007 Situation of the Static Var Compensators at CERN Introduction General risk analysis for SVC’s - typical faults - how to reduce the risk 3. The SVC’s at CERN in detail - technical state - maintenance strategy - consolidation 4. Summary

Introduction Purpose of an SVC: Reactive Power compensation Voltage stabilization 18 kV Harmonic filtering

Introduction SVC Example: SVC2 for SPS SPS 18 kV SPS reactive power

Purpose: Reactive power compensation SPS EDF 400kV SVC

SVC’s and harmonic filters at CERN (status end 2007): Introduction SVC’s and harmonic filters at CERN (status end 2007): Total of SVC’s / filter inst.: 12 Rated voltage: 18 kV Total surface: 14’000 m2 Total value (prices 2007): 45 MCHF Total capacitive power: 550 Mvar (=17.6 kA @ 18 kV) For comparison: CERN consumption 2008: 380 MVA peak (=12.2 kA peak @ 18 kV)

Introduction: Meyrin network and Booster 66 kV (Prevessin) 18 kV PA1 18 kV Meyrin network Station ME9, b. 212 TCR Booster Filters Meyrin Meyrin network Booster

Introduction: SPS electrical network (1974) SPS 400 kV 18 kV (2002) (Nov. 2007) T1 T2 T3 SVC1 SVC2 Project SVC3

Introduction: LHC machine network 66 kV (Prevessin) SVC PA4 SVC PA6 CMS LHC 18 kV 18 kV SVC PA2 SVC PA8 ATLAS

Filters Meyrin Booster (build. 202) 2nd floor: reactors 1st floor: capacitors 3rd floor: resistors

NB: LHC operation depends on them. Filters Meyrin Booster (build. 202) Reactors (1971) NB: LHC operation depends on them.

TCR Booster (build. 242, Meyrin) (1997)

SVC1 (build. 884, Prevessin) Harmonic filters Saturated reactor (1974)

SVC2 (build. 980, Prevessin) (year 2002)

Faults with low severity Risk Analysis (types of faults) 1/3 Faults with low severity type of fault typical downtime TS-EL probability of event severity preventive measures disturbance of network 400 kV (external cause) 1 h high low none false trip of protection optimize protection lack of cooling water, water filter clogged etc. 2 h miscellaneous (small) failures such as animal entry, Emergency Stop operation etc. ½ day medium

Faults with medium severity Risk Analysis (types of faults) 2/3 Faults with medium severity type of fault typical downtime TS-EL probability of event severity preventive measures Trip: capacitor bank unbalance (small capacitor failures) ½ day high medium - annual maintenance, - monitor capacitor unbalance currents, - spare capacitors Trip: thyristor failure (one thyristor per phase) low / medium - spare thyristors

Faults with high++ severity (major events) Risk Analysis (types of faults) 3/3 Faults with high++ severity (major events) type of fault typical downtime TS-EL probability of event severity preventive measures overheating of bad electrical connection (short-circuit) - ex: 2003 SVC1 up to 3 days low high - IR thermography - maintenance capacitor bank avalanche failure ex: 2006 SVC1 several weeks very high - annual maintenance, - monitor ub currents, - spare capacitors thyristor avalanche failure - ex: 1998 BB3 & 1998 PA2 1 ... 5 days very low annual maintenance, spare thyristors Failure of air-core coil - ex: 1999 LEP PA4 2 ... 3 months spare coils ? (45 types at CERN) Major internal failure of Saturated reactor (SVC1) repair impossible medium extremely high oil analysis, redundant SVC3

Risk Analysis - Summary How to reduce the risk? - consolidation - redundancy for large SVC’s (e.g. SPS) - annual maintenance - IR thermography - sufficient spare parts

SVC Meyrin for Booster ● TCR (20.5 Mvar, 1997) Technical state Risk of major breakdown actions good state annual maintenance was done low risk Annual maintenance check avail. spare parts ● Meyrin Filters (17 Mvar, 1972) Technical state Risk of major breakdown actions ageing equipment (35 years) unknown technical state capacitors (1990) high 2007: Annual maintenance consolidation project (will be studied)

SVC1 for SPS ● Saturated Reactor (117 Mvar, 1974) Technical state Risk of major breakdown actions approaching end of life time (very) high risk annual maintenance oil analysis / oil treatment ● Harmonic filters (92.1 Mvar, 1974) Technical state Risk of major breakdown Actions capacitors (1992) 2 identical faults (1991, 2006) sufficient spare capacitors are available to cover breakdowns medium risk of major capacitor failure (again) annual maintenance consolidation project (Will be studied. Additional spare parts for SVC2+SVC3 or SVC1 consolidation?)

SVC1: Major breakdown on 8.5.2006 [EDMS 813568] ● Causes: identical breakdown happened 1991 ageing of capacitors status of maintenance low impedance of HF filter (filter design) ? breakdown not linked to manual operation on 1.5.2006 ● What has been done so far ? re-commissioning in May/June 2006, only minor techn. modifications prevention of manual energization sufficient spare capacitors available major maintenance scheduled for spring 2007 ● Risk - Risk is reduced, but cannot be eliminated

Risk of major breakdown SVC2 for SPS ● TCR (150 Mvar) and harmonic filters (130 Mvar) (2002) Technical state Risk of major breakdown actions good technical state annual maintenance during previous years sufficient spare parts in stock low risk annual maintenance

Risk of major breakdown SVC3 for SPS ● TCR (150 Mvar) and harmonic filters (130 Mvar) (2007) Technical state Risk of major breakdown actions work in progress energization 1.11.2007 will be identical to SVC2 budget about 6 MCHF

Auxiliary Compensator BB3 for SPS BB3 is required as long as SVC1 is in operation. As soon as SVC1 is out of service (e.g. saturat. Reactor h/s), we can dismantle BB3. ● TCR (18 Mvar, 1982) Technical state Risk of major breakdown actions ageing equipment (25 years) has been maintained regularly medium risk annual maintenance ● Capacitor bank (18 Mvar, 1982) Technical state Risk of major breakdown actions ageing equipment (25 years) has been maintained regularly medium risk annual maintenance increase spare capacitors

Stable Filter BEF4 for Stable Network ● Stable Filter (21 Mvar, 1977) Technical state Risk of major breakdown actions ageing equipment (30 years) major capacitor failure in 2006 medium 2007: Annual maintenance increase spare capacitors

4 SVC’s for LEP/LHC in PA2, PA4, PA6, PA8 ● TCR (50 Mvar) and harmonic filters (50 Mvar) in PA2 (1987) ● TCR (25 Mvar) and harmonic filters (25 Mvar) in PA4 (1992) ● TCR (25 Mvar) and harmonic filters (25 Mvar) in PA6 (1987) ● TCR (25 Mvar) and harmonic filters (25 Mvar) in PA8 (1992) Technical state Risk of major breakdown actions all SVC’s are out of service 2007: consolidation progr. (Techn. Note EDMS 768037) budget 1.2 MCHF

Summary 1/2 ● Goals: - prevention of major SVC failures (high severity) - repair a.s.a.p. ● Actions for 2007 and beyond: - consolidation (4 SVC’s for LHC, Meyrin Filters ?, SVC1 ?) - commissioning of SVC3 for 1.11.2007 (= redundant SVC for SPS) - annual maintenance of all SVC’s in service - IR thermography - intermediate checks during operation (early detection) - increase of spare parts in stock (e.g. to cover major failures)

Summary 2/2 ● Order of priorities: 1. terminate SVC3 project 2007 2. consolidation PA2 and PA4 (most critical for LHC) 2007 3. consolidation Meyrin Filters for Booster *) 2007..08 4. consolidation PA6 and PA8 (less critical for LHC) *) 2007..08 *) order of priority, depending on - technical state of Meyrin Filters - future strategy for Meyrin network (PS2, SPL, LINAC’s etc.)

Outlook Spring 2007: - annual maintenance for all SVC’s in service End 2007: - 3 SVC’s for SPS (redundant SVC for SPS) - 2 most critical SVC’s for LHC renovated (PA2, PA4) - strategy for Meyrin network, incl. Meyrin Filter for Booster Mid 2008: - all 4 SVC’s for LHC renovated End 2008: - depending on strategy: Meyrin Filter for Booster renovated

Questions? Karsten KAHLE, TS-EL