Mike Anerella December 17, 2013

Slides:



Advertisements
Similar presentations
LARP LQX and MQX Cold Mass Testing at Fermilab Overview and Required Test Stand Upgrades Cosmore D. Sylvester.
Advertisements

CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
1 Preparation for MQXF Short Model Tests G. Chlachidze Fermilab.
Current status Arkadiy Klebaner November 21, 2012
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
HQ TEST CERN by Marta Bajko CERN TE-MSC TF For Hi Lumi and LARP the 16 th of November 2011 CERN.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
HL-LHC/LARP, QXF Test Facility Workshop– R. Carcagno QXF Test Requirements Ruben Carcagno BNL Workshop December 17, 2013.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
Ultra-Compact Electrical Machines for Wind Energy DE-FOA : Demo Machine C. L. Goodzeit and M. J. Ball May 1, 2014 General List of Tasks by Performance.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
DOE Review of LARP – February 17-18, 2014 Coil Design and Fabrication Miao Yu February 17,
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design.
Lab Coordination Meeting 9/25/13Introduction – G. Sabbi 1 Magnet Development Plan Update Overview GianLuca Sabbi LARP Lab Coordination Meeting September.
LARP CM15 Magnet Testing Working Group SLAC, November 2 nd 2010.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
Lab Coordination Meeting 3/21/13LHC IR Quadrupole Plan – G. Sabbi 1 LARP Magnet Systems Plan GianLuca Sabbi Lab Coordination Meeting March 21, 2013.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
1 MQXF(S) Magnet Interface Document MQXF(S) magnet interface document will describe electrical connection between the magnet and the header assembly Scope.
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
17-18 December 2013 LARP VTF Workshop BNL Proposal 1 A.Marone
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone September 25, 2015.
LCLS-II Cryoplant Overview
LARP Review, June 10, 2013Magnet Cost and Schedule – M. Kaducak 1 IR Quadrupole Cost and Schedule Marc Kaducak LARP Review June 10, 2013.
BNL MAGNET TEST FACILITY FOR MQXF Q1/Q3
BNL - FNAL - LBNL - SLAC 6m (and 8m) scale-up Giorgio Ambrosio Fermilab Contributions from: Fred Nobrega, Rodger Bossert, Guram Chlachidize (FNAL) Jesse.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
WP10 General Meeting, Giovanni Volpini, CERN 1 December 2015 Test progress INFN 1.
October 7, 2010 HINS Test Cryostat 2 K Conversion Status October 7, 2010.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Resource Loaded Schedule and Budget Profile
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
QXF Coil Fabrication & Tooling Reaction / Impregnation
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
Cryogenic behavior of the cryogenic system
HFM Test Station Main Cryostat
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
LARP Vertical Test Facility
Cryogenic cavern in Asian site
TEST PLANS for HL LHC IT STRING
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
ESR 2 Presented to Joint Hall A/C Summer Meeting
CTF Users’ Perspective
as a prototype for Super c-tau factory
Cryogenic behavior of the magnet
LCLS Injector System Overview D. H
Conceptual design of the Cryogenic System of Comprehensive Research Facility for Key Fusion Reactor Core Systems Liangbing Hu Sep.4.
News from the FNAL test facility
Review Bloc 4 and SM18 facilities and upgrade
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Mike Anerella December 17, 2013 BNL LARP QXF Cold Mass Vertical Cold Test Facility Proposal Overview – Cost & Schedule Mike Anerella December 17, 2013

Goals Description of current test capabilities Description of the upgrades needed to meet test requirements Upgrade and Operating Cost Upgrade and Operating Schedule

Available Equipment (more later) CTI Model 4000 refrigerator (~ 320 L/hr) Ø710 mm, 6.1M Vertical Test Dewar ILC Service Cryostat (under construction) Other: 30T/5T Crane Hook max. height = 7.6 m/ 8.3? m Dewar height above floor = 0.9M (max. coil length ~ 6M)

Installation Location – high bay of Building 902 Nash Pump He refrigerator Dewar 3 Service cryostat

Scope Complete service cryostat assembly & commission unit Design / build 1.9K, 22KA vertical dewar within existing dewar Design / upgrade power supplies, energy extraction, quench protection systems, data acquisition Analyze, satisfy test requirements Andy / Paul Piyush Joe

Service Cryostat schedule Assembly is nearly complete Transfer line length depends on final cryostat location Performance established by end of April

Service Cryostat Commissioning Cost $145K total, FY14

design / construction schedule Engineering & design must be completed sometime in FY14 to meet 8/15 test schedule → need ~ $370K in FY14 Controls / DAQ = Smallest float; → need $173K for M&S in FY14 Approx. 3 months of schedule float

design / construction cost TOTAL COST 1.9K mechanical 4.5K mechanical electrical Notes: no contingency Details in backup slides

LQXF test operating schedule Schedule (for now) assumes 12 hr. test / 16 hr. cryo days 48 days total 8 days before test Note: Functional Test Requirements specifies 2 month total testing time including installation, cool down, test, warm-up & removal (close!) Assumes great efficiency via connectors Details later (Joe) 6 days to disconnect

LQXF test operating cost $376K total labor & material, FY14 – 1308 M-H

MQXF test operating schedule Schedule (for now) assumes 12 hr. test / 16 hr. cryo days 30 days total 8 days before test Note: Functional Test Requirements specifies 1 month total testing time including installation, cool down, test, warm-up & removal → can be achieved by using a second top hat Assumes great efficiency via connectors Details later (Joe) 6 days to disconnect

MQXF test operating cost $168K total labor & material, FY14 – 756 M-H

(NO contingency, no measuring coils) Summary $1.4M total cost to design, build, install VTF, commission service cryostat (NO contingency, no measuring coils) Proposal heavily leverages existing infrastructure: 320L/hr helium refrigerator Ø710 mm diameter, 6.1 m long test dewar Nash-Kinema 2.7 g/s @ .016 bar vacuum pump 1.9K external heat exchanger (ILC service cryostat) 30KA Power supply IGBT’s, HV, LV data loggers, DAQ, etc. Work can be completed in time for LQXF mirror assembly test, provided funding is available in FY14 for engineering and design ($370K), service cryostat commissioning ($145K) and electrical LLP’s ($173K); →total FY14 funding needed = $688K Proposal (almost) meets FTR schedule for LQXF Proposal meets FTR schedule for MQXF by adding a 2nd top hat Vertical – early - testing of cold mass provides greatest risk reduction for LARP

Backup slides

(FNAL) MQXF testing costs (from June 2013 review) $3M total construction cost $180K per test in production, 2 cold masses at a time! Only $41K material per test!

Design/ Construction Electrical costs

Design / construction Mechanical costs 4.5K 1.9K add’l

LQXF testing time & resources 150% = 12 hr. work day • 200% = 16 hr. work day

MQXF testing time & resources 150% = 12 hr. work day • 200% = 16 hr. work day

1.9K heat exchanger