Status, Schedule and EVM for the test facility project

Slides:



Advertisements
Similar presentations
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Advertisements

CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Olivier Pirotte AT-ECR-ME NTof Examples of cryogenic equipment installed by AT/ECR-ME O. PIROTTE.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
Helmholtz Centre for Ion Research D. Krämer, 2nd Lab Directors Meeting, Protvino, January 15-16, 2008 Design and Engineering Issues; Standardization and.
Progress report on the test facility project design and construction P. Schnizer and L. Serio on behalf of bldg. 180 test facility project team members.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
Installation issues - update, July 2006A.Fabich1 MERIT installation: Update July 2006 A.Fabich CERN AB-ATB July 2006.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
The Building 180 Cryogenic infrastructure water cooling system Stefano Moccia, EN-CV Coordination meeting 26/09/14.
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
TE-CRG Activities D. Delikaris, TE-CRG.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
CERN GS Department CH-1211 Genève 23 Switzerland cern.ch/gs-dep Internet Services GS AIS General Services Department GS Advanced Information Services EVM.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
ELENA installation progress F. Butin / ELENA collaboration.
LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop ***********************************
WP High Beta Cavities Delivery
Neutrino Platform Proximity Cryogenics 68th EHN1 Cryogenics Integration TE-CRG
Cryoplant Controls Installation
CC LLRF SM18 test plan and BA6 infrastructure
MEDICIS Safety Alarms Systems
LHeC Coordination Meeting, 9 June 2017
Cryogenic Plant Electrical and Controls
CERN Construction Planning and Scheduling (LHC installation)
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
SM18 RF M7 Bunker Project Status 14th July 2017
Framework Schedule from EYETS 2016 to LS2
Francois and Lau EATM 17 July 2012
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Safety Documentation EHN1
SPS cryogenic proximity equipment and SM18 validation
BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016
Coordination meeting 12/05/15
EN 4946 – Refurbishment of Electrical Substations
Status of the PANDA Magnet
SIS100 quadrupole status S. Kostromin, H. Khodzhibagiyan, G. Trubnikov, FAIR 11th MAC, GSI, May,
International Review of the Conceptual Design of the Cold Powering system for the HL-LHC Superconducting Magnets J.Ph. Tock
CRG activities for EYETS 2016
LIU and TE/ABT/PPE activities
Overview & baseline of LS2 and roadmap for CRG
East Hall under construction
Status of the cryogenic system for B180
Testing CERN Magnet – Test Station Interface
Testing Workshop on Survey and MM
Benoît DAUDIN (GS-AIS-PM – CERN) 22-March-2012
ELENA Magnet Installation Planning
Far Experimental Hall Hutches Civil Construction
ESS Project Status Roland Garoby – Technical Director August 2018.
LCLS-II Cryoplant Controls Workshop.
Teleconference ACS – FREIA 19th June 2017
Managing Project Work, Scope, Schedules, and Cost
PANDA Cryostat and Yoke
DOE Status Meeting of the LCLS Project
East Hall under construction
Cryogenic upgrade of B165 CRG Status Meeting 16th may 2019
ECR on pole order of the HL-LHC IT circuit and resulting implications
East Hall under construction
WP1: Status and Plans Francisco Sanchez Galan (EN-EA-PE)
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Status, Schedule and EVM for the test facility project L. Serio

Progress report: executive summary Major critical path contracts signed Design and manufacturing in industry started Interfaces being revised for construction Cryogenics, on critical path, delay of 3 - 4 months, other systems have a significant float Several re-design of layout and platforms due to changes Change Requests sent by GSI with potential impact on test plan and layout to be analyzed CERN – GSI meeting 20151014 L. Serio

EVM Cost and profiling requires review due to CERN delays in cryogenics and adaptation to GSI maturity of requirements and need date Baseline change agreed by CERN – GSI c.ttee last June Waiting for inputs from WP on new baseline to fulfill end of 2016 readiness No major cost increase expected (apart from the longer schedule) Favorable CHF/EUR exchange rate Cryo compressor building consolidation being review Control room and operation infrastructure to be covered by additional financing Procurement lagging behind by about 3 months CERN – GSI meeting 20151014 L. Serio

EVM CERN – GSI meeting 20151014 L. Serio

EVM: Late deliverables ( + 3 m) Integration - Y. Muttoni Integration 3D Cryogenic system A. Perin Control system comp. station precooler 1 (0%), Control system precooler 1 (0%) , Decabling + various CE (95%), Precooler 1 refurbishment B180 (FSU) (2%), Refurbishment of DVB B180 (15%), TCF200 cold box + local cryo lines refurbishment (5%), Control system precooler 1 (0%), Precooler 1 compression station refurbishment B279 (0%), TCF200 cold box refurbishment (10%) Magnet test stand goods - G. Willering Commutators and connections Engineering specification (40%), Powering cables Approval of engineering specification (80%) Platforms - M. Wilhelmsson Adaptation and finish after the other services are in place (0%), Adaptation, modifications if needed (0%), Building the platforms in b 180 (0%), Final design included contruction drawings (75%), Prefabrication in workshop (b 904) (include painting) (0%), Procurement of raw-material (0%) Electrical Powering and distribution - R. Necca Dismantle existing installations (0%) Fiducialisation of the magnets - D. Missiaen Network points technical specification (5%) CERN – GSI meeting 20151014 L. Serio

Late or no progress report (!!) Workunit Holder WBS Plan Start Plan Finish Last Report 156737 - Integration Y. Muttoni (EN-MEF-INT) 06-May-2015 156740 - Magnet test stand goods G. Willering (TE-MSC-TF) 14-Jul-2015 156741 - Magnet test other material G. Willering (TE-MSC-TF) 17-Aug-2015 156751 - Electrical Powering and distribution R. Necca (EN-EL-BT) 24-Aug-2015 156743 - Control and DAQ (OM) E. Blanco Vinuela (ENICE- PLC) 24-Aug-2015 156738 - Cryogenic system (OM) A. Perin (TE-CRG-ML) 07-Sep-2015 156752 - Fiducialisation of the magnets D. Missiaen (EN-MEF-SU) 14-Sep-2015 CERN – GSI meeting 20151014 L. Serio

Schedule CERN – GSI meeting 20151014 L. Serio LLI procurements Fix layout interfaces Commissioning CERN – GSI meeting 20151014 L. Serio

Tentative schedule for next phase Final tuning and exact sequencing of installation to be made in the coming weeks following the implementation of the new baseline (EVM and Schedule) Pending analysis of recent Change Requests from GSI/FAIR CERN – GSI meeting 20151014 L. Serio

References Project Plan (contains all up to date information): EDMS: https://edms.cern.ch/document/1370663/3 Technical coordination meetings and reviewed interface parameters: EDMS: https://edms.cern.ch/nav/P:FAIR-000001263:V0/P:FAIR-000002500:V0/TAB3 Interface requirements documents: https://edms.cern.ch/nav/P:FAIR-000001263:V0/P:FAIR-000002718:V0/TAB3 CERN – GSI meeting 20151014 L. Serio