Floating MD week 28 summary

Slides:



Advertisements
Similar presentations
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Advertisements

AB-ABP/LHC Injector Synchrotrons Section CERN, Giovanni Rumolo 1 Final results of the E-Cloud Instability MDs at the SPS (26 and 55 GeV/c) G.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
LHC Scrubbing Run 1 Day 3 (27/06/2015) Scrubbing team 28/06/2015.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Week 13: R. Assmann, J. Wenninger
Preliminary MD Report R. Assmann, G. Papotti, F. Zimmermann
LHC Status Fri Morning 3-June
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Machine Coordinators: G. Arduini, J. Wenninger
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary Friday h38: Ramp down and pre-cycle.
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
LHC Morning Meeting - G. Arduini
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
MD#4 Progress MD Coordinators: Giulia Papotti, Frank Zimmermann
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
LHC Morning Meeting - G. Arduini
Wed :40 Lost S78 - QPS controller.
Mike Lamont, Jorg Wenninger
Saturday 2/4/ :00-09:00 Problems with SPS:
Wednesday 8th August & night
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Monday Morning – recovery from cryo.
Chromaticity can make a difference…
Friday morning 10:30 Optics measurements and corrections.
Saturday – Morning 7:36 beams dumped
Tuesday 9th November 10:02 Fill beams dumped
Friday Morning 7:30 injection for fill 2908
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Saturday 7th May Sat – Sun night
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Thursday – Morning Energy matching at injection with H CODs
Collective effects in the SPS and LHC (longitudinal plane)
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Saturday :42 stable beams fill 3541
LHC Morning Meeting - G. Arduini
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Wednesday h18: 228b fill lost just before start of ramp.
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Another Immortal Fill….
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Floating MD week 28 summary Ralph Assmann, Giulia Papotti, Frank Zimmermann

48h floating MD MON 09/7 16:00 Beam Dump physics fill (need to come from high energy) 17:00 Q20 set up 21:00 High pile-up (~100): standard optics & 2b of 3e11 (Q20); collisions IR1&5 ; noise excitation, transverse offset etc TUE 10/7 07:00 Beam dump, revert to Q26 injection 08:00 25ns injection tests 13:00 Ramp down and cycle 14:00 ATS MD: Pre-squeeze and very low beta ATS (0.1 m) WED 11/7 03:00 Dump & ramp down 04:00 Beta* leveling test up to 36b OR Week AFTER 16:00 End of floating MD 11.07.2012 floating MD week 28

Q20 setup started 1h40’ late, then waited for SPS beam setup TL corrected no other studies due to lack of time 3 - 3.3e11 ppb in 2 - 2.4 um waited 30’ with single bunches at injection for IBS measurements 11.07.2012 floating MD week 28

High pile-up MD 4 fills, 3 (short) stable beams pile-up beams were quite touchy, had several issues with losses and emittance blow-up possibly emittance growth enhanced by chirp observed instabilities increased chroma (Q’ = 5) and blow-up target to 1.4ns for fills 2-3-4 managed b2 very well ramped up and squeezed emittance before collision about 2.2 um, losses <5% through cycle some small activity on BBQ b2v pile-up 48/45 (ATLAS/CMS) with first fill 70/65 in fourth fill no time for systematic studies parallel separation, levelling, noise excitation, … 11.07.2012 floating MD week 28

25 ns injection tests Injection of 25 ns bunch trains worked extremely well very small losses coming both from the TL collimators and debunched beam kept Q’ = 15 steered with 12 b only in h maximum losses at 3% from dump thresholds, mainly at the TDI and TCLIs (satellites?) 72 b injection clean (3% as for 12 b), good trajectories and injection oscillations 144 b injection 6-7% losses, injection oscillations and trajectories still fine 216 b for B1 only (MKI8D weakness) losses 11%, a small oscillation in h TL 288 b injected and stored for the first time very bad lifetime, injection losses at 12%, emittance 3.3 um 11.07.2012 floating MD week 28

25ns e-cloud observations beam 1, (12+12+) 72 b, Q’ = ~15 in both planes no instability after injection but bad lifetime and emittance growth of bunches at the end of the batch same behavior for beam 2, however slightly better lifetime continued with injection of 144 bunches in both rings signs of instabilities at injection (mostly in H), bad lifetime and clear signature of ecloud driven losses again beam 2 slightly better than beam 1 then injection of 216 and 288 bunches for beam 1 only similar behaviour as with 144 bunches Q’ = 3-5 for beam 2 injection of 72 b fine, although already signs of instability behaviour of freshly injected 72 b better than the first injections beams dumped after injection of 144 b on beam 2 after around 700 turns, stronger oscillations in h 11.07.2012 floating MD week 28

ATS MD 2 cycles second cycle was a success first one, beam lost at flat top during dispersion measurement second cycle was a success many measurements taken at beta* = 40 cm, 20 cm and 10 cm only beam 2 at 10 cm, beam1 lost from 20 to 10 cm (bad Q trim) beam 2 had very bad life time towards the end of the squeeze, down to 2-3h no IT corrector and beta_max up to 20 km optics results will follow 11.07.2012 floating MD week 28

beta* levelling MD ongoing first fill with 2 indiv/ring for cycle/settings verification arriving at 2 m - very good, both move up ! next: fill with 36 b trains for beam-beam effects 11.07.2012 floating MD week 28