Temporary Works – P8 Project Practice.

Slides:



Advertisements
Similar presentations
Safety Absolutes Green Lake
Advertisements

Health and Safety Executive Health and Safety Executive Running a Small Construction site Presenters name in Arial regular 32pt.
Lesson 9 Design & Construction of Food Premises & Equipment
Erecting steel structures Setting up or dismantling cranes or hoists
Chp12- Footings.
Concrete and Masonry Work Different forms of concrete work Each has it’s own unique hazards – Lift Slab – Pre-stressed Concrete – Concrete Pumping – Masonry.
INTRODUCTION TO THE NEW SUBPART R Prepared by the U.S. Department of Labor, OSHA Office of Construction Standards and Compliance Assistance.
Subpart R Steel Erection
Design C a s t i n g E r e c t i o n F i n a l S t r u c t u r e D e s i g n C o n s t r u c t i o n P r o c e s s P r e–c a s t C o n c r e t e 3D M o.
OSHA Office of Training and Education
Learning Objectives Understand the OSHA requirements for fall protection during steel erection Understand the OSHA requirements for fall protection during.
Rev: Section 3 Framing Operations. Rev: Learning Objectives: Section 3 Understand when fall protection must be provided Evaluate the use.
Most Frequently Cited Serious Violations Construction – FY 2008.
Health and Safety Manual Section F9 Working at Height.
Rectangular framed structures
Which Standards might apply to these hazards
First conceptual design 3D Side view Arch supporting the structure.
1 Out of Site, Out of Mind! Mark Mallen Group Health and Safety Manager.
PRE-FABRICATED STRUCTURES
Temporary Works.
Prefabricated Timber Frame Construction
Appendices Subpart R Steel Erection
Excavation Instructional Goal: through class participation and discussion, the participant will identify the issues and hazards related to trenching and.
Steel Erection These handouts and documents with attachments are not final, complete, or definitive instruments. This information is for guidance purposes.
Construction Health and Safety Management By Dr Simon Smith – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike License.
1 CV4902- Construction Methods Dr David Chew. 2 Construction Considerations Site layout plan Outline of entire construction process Details of temporary.
Construction Management Two 2014 Setting up Site Presenter Tony Bosnich Feb 2014.
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
Site Layout constructionsite.
PMP1 Taija Puolitaival Unitec 2012 Presenters Tony Bosnich Glenn Edmonds 2014.
Excavations & Trenching 1 OSHA 1926 Subpart P Bureau of Workers’ Comp PA Training for Health & Safety (PATHS) PPT
Office of Safety & Health Consultation Office of Safety & Health Consultation presents Focus Four Fall Protection in Construction Focus Four Fall Protection.
Accident Prevention Manual for Business & Industry: Engineering & Technology 13th edition National Safety Council Compiled by Dr. S.D. Allen Iske, Associate.
L04: Understand the implications of the issues and constraints on building construction Lesson Objective To be able to explain the different plant required.
Most Frequently Cited Serious Violations Construction 2000.
Infrastructure that Supports the Construction Industry In order for the construction industry to function effectively there is a large amount of infrastructure.
Name ________________ Unit 6/P6 – Concrete Construction Expensive Heavy and dense = strong, sound proof and thermally efficient. Cast in situ or pre-cast.
Foundation Loads Dead Load Live Load Wind Load
§1926 Subpart M Presented by: ETTA, OSH Division, Fall Protection in Construction.
BPS3413 CONSTRUCTION SAFETY Lecture 6 : Working at Height.
Unit 6: Building Technology in Construction Learning Outcome Understand the implications of the issues and constraints on building construction Lesson.
CAISSON FOUNDATION.
KEY LEARNING from an Electrical Discharge [Dangerous Occurrence] that occurred on Thurs 03 October 2013.
This presentation was created by the N.C. Department of Labor for safety and health training. §1926 Subpart M Presented by: ETTA, OSH Division,
Concrete Repair.
Trench Hazards Introduce the module. Trenching & Excavations Continuing Education Third Quarter 2017 Session 3.
Fall Protection for Construction
Prefabricated Timber Frame Construction
Most Frequently Cited Serious Violations
BUILDING ECONOMICS.
Most Frequently Cited Serious Violations
Construction Technology
Steel Erection 29 CFR 1926, Subpart R
Floors.
BUILDING CONSTRUCTION 1
Progress Charts.
Arch205 Materials and building construction 1 foundation
Awarding Criterion for late tender: the lowest bid- why?
Arch205 building construction foundation
CIVIL WORKS CONSTRUCTION TECHNOLOGY 2017/18
Presenter Tony Bosnich 2015
Value of contract: Length of contract: Contract start date:
ESTIMATION Estimation is the scientific way of working out the approximate cost of an engineering project before execution of the work. It is totally different.
Most Frequently Cited Serious Violations
INTRODUCTION TO THE NEW SUBPART R
6th. Semester Schedule: 1st. Week
Steel Erection 29 CFR 1926, Subpart R
BUILDING CONSTRUCTION Foundation
Life Cycle Costing.
Presentation transcript:

Temporary Works – P8 Project Practice

Temporary works are an essential part of construction process Construction would not be possible without some form of temporary works.

Definition “any temporary construction necessary to assist the execution of the permanent works and which will be moved from the site on completion” J. R. Illingworth

The Site and it’s Boundaries Provision of temporary access roads, bridges, temporary support to adjacent buildings – shoring and waterproofing. Protective measures when plant is required to travel under HT lines or are working adjacent to HT lines.

Safety measures when working adjacent to railways Protection of the public adjacent to the works or where rights of way are to be maintained. Safety measures when working adjacent to railways Hoardings and fencing plus traffic management.

The Site Set – UP Provision of site offices, toilets, storage facilities, first aid room, canteens and drying facilities and appropriate services. Where overseas work is concerned, camps and other facilities may also be needed.

Temporary Works Associated with Plant Provision of crane tracks and bases. Provision of hoist foundations. Temporary anchorages to structure of cranes and hoists.

Foundation and services for mixing plants Power supply for cranes hoists, bar benders

Safe Places of Work and Access Scaffold required by law and to the standards laid down by the regulation. In providing scaffolding, public safety must be considered – netting to stop falling materials, safe access under scaffold which have to be erected over a pavement.

Work in Excavations Legislation used to require that all excavations more than 1.2m deep must be adequately supported. This is now dependant on ground conditions irrespective of the depth of excavations.

In addition, rescue equipment and testing facilities are necessary where there is a risk of a foul atmosphere in the excavation

In Situ Concrete Work Provision of formwork or false work adequate to resist the concrete pressures arising and the loads imposed to be supported until the concrete cure to a sufficient strength to support itself.

Erection of Structural Frame Establishing special lifting gear, methods of work to achieve safe access and temporary support to provide stability to structural members while in the process of erection.

TW Schedule for a Major Building. Construction mainly involves two fundamental activities: Handling of materials and – Their fixing in the final location

Construction Method Handling is a combination of both plant and labour. Whilst fixing is a handling operation For construction to take place TW must be used as it enables both plant and labour to work efficiently and safely hence:-

Material Handling (Plant and Labour) + TW = Construction Method

Site Establishment TW required Temporary offices Stores Hoardings Welfare Facilities Temporary Services

Party Wall TW Required Temporary support of adjacent property, weather proofing.

Excavation, Oversight and regarding TW Required:- Temporary drainage Support to adjoining property Access to vehicles

Drainage and HT cable Protection Access Temporary roads Temporary bridges Drainage and HT cable Protection

Basements Support system before permanent works are in place

Access to plant items for erection Foundations and ground floor slabs Support of excavation Foundations for plant Formwork to bases Pile caps Access to plant items for erection

Temporary support for pre- cast and steel Superstructure Formwork False work Scaffolding Temporary support for pre- cast and steel Anchors for cranes and hoists

Temporary fixings for aligning and level External Cladding Scaffold and cradles Temporary fixings for aligning and level

Internal Service Carcass Scaffold Mobile or work platforms

Plant room installation Temporary weather proofing Work platforms

Building Carcass – Roof Cladding Scaffold and work platforms Scaffold and edge protection

Building and Service Finishes Work Platforms and ladders

External Works - Formwork Protection and support for excavation Formwork to interceptors and manholes Formwork to kerbs and backing

Questions