Temporary Works – P8 Project Practice
Temporary works are an essential part of construction process Construction would not be possible without some form of temporary works.
Definition “any temporary construction necessary to assist the execution of the permanent works and which will be moved from the site on completion” J. R. Illingworth
The Site and it’s Boundaries Provision of temporary access roads, bridges, temporary support to adjacent buildings – shoring and waterproofing. Protective measures when plant is required to travel under HT lines or are working adjacent to HT lines.
Safety measures when working adjacent to railways Protection of the public adjacent to the works or where rights of way are to be maintained. Safety measures when working adjacent to railways Hoardings and fencing plus traffic management.
The Site Set – UP Provision of site offices, toilets, storage facilities, first aid room, canteens and drying facilities and appropriate services. Where overseas work is concerned, camps and other facilities may also be needed.
Temporary Works Associated with Plant Provision of crane tracks and bases. Provision of hoist foundations. Temporary anchorages to structure of cranes and hoists.
Foundation and services for mixing plants Power supply for cranes hoists, bar benders
Safe Places of Work and Access Scaffold required by law and to the standards laid down by the regulation. In providing scaffolding, public safety must be considered – netting to stop falling materials, safe access under scaffold which have to be erected over a pavement.
Work in Excavations Legislation used to require that all excavations more than 1.2m deep must be adequately supported. This is now dependant on ground conditions irrespective of the depth of excavations.
In addition, rescue equipment and testing facilities are necessary where there is a risk of a foul atmosphere in the excavation
In Situ Concrete Work Provision of formwork or false work adequate to resist the concrete pressures arising and the loads imposed to be supported until the concrete cure to a sufficient strength to support itself.
Erection of Structural Frame Establishing special lifting gear, methods of work to achieve safe access and temporary support to provide stability to structural members while in the process of erection.
TW Schedule for a Major Building. Construction mainly involves two fundamental activities: Handling of materials and – Their fixing in the final location
Construction Method Handling is a combination of both plant and labour. Whilst fixing is a handling operation For construction to take place TW must be used as it enables both plant and labour to work efficiently and safely hence:-
Material Handling (Plant and Labour) + TW = Construction Method
Site Establishment TW required Temporary offices Stores Hoardings Welfare Facilities Temporary Services
Party Wall TW Required Temporary support of adjacent property, weather proofing.
Excavation, Oversight and regarding TW Required:- Temporary drainage Support to adjoining property Access to vehicles
Drainage and HT cable Protection Access Temporary roads Temporary bridges Drainage and HT cable Protection
Basements Support system before permanent works are in place
Access to plant items for erection Foundations and ground floor slabs Support of excavation Foundations for plant Formwork to bases Pile caps Access to plant items for erection
Temporary support for pre- cast and steel Superstructure Formwork False work Scaffolding Temporary support for pre- cast and steel Anchors for cranes and hoists
Temporary fixings for aligning and level External Cladding Scaffold and cradles Temporary fixings for aligning and level
Internal Service Carcass Scaffold Mobile or work platforms
Plant room installation Temporary weather proofing Work platforms
Building Carcass – Roof Cladding Scaffold and work platforms Scaffold and edge protection
Building and Service Finishes Work Platforms and ladders
External Works - Formwork Protection and support for excavation Formwork to interceptors and manholes Formwork to kerbs and backing
Questions