Bridge Pile Foundation Evaluation for a Soil Remediation Project

Slides:



Advertisements
Similar presentations
Revised Environmental Site Assessment Guidelines & Asbestos Inspection Guidelines for Bridges.
Advertisements

Potential Solutions Goals for Design – What are we concerned about? –Primary Goal: Get the deck on successfully Stability during deck pour Stability during.
BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next.
JP Singh and Associates in association with Mohamed Ashour, Ph.D., P.E. Gary Norris, Ph.D., P.E. March 2004 COMPUTER PROGRAM S-SHAFT FOR LATERALLY LOADED.
Ying Tung, PhD Candidate
Summary of Conceptual Design Site 3 Causeway Landfill Culvert Stabilization Marine Corps Recruit Depot Parris Island (CTO JM38) 19 August 2014.
Chp12- Footings.
Click to continue…. Railroad Track wetland Image Date: December 2003.
1 Application and Analysis of Helical Piers in Frozen Ground He Liu, Ph.D., P.E. Daniel Schubert, P.E. Hannele Zubeck, Ph.D., P.E. Sean Baginski.
ADSC/CALTRANS CIDH Pile Workshop Spring Overview of Structural Design and Detailing of Large Diameter Drilled Shafts (Caltrans Practice) Amir M.
Designing Piles for Drag Force
AASHTO LRFD Section and 10
USING THE RAPID LOAD TESTER TO PROVIDE PROJECT QUALITY CONTROL.
Prepared by J. P. Singh & Associates in association with
Bridge 2153 Final Report Premier Engineering Rose-Hulman Institute of Technology.
Wabash Pedestrian Bridge Design For Riverfront Development Committee INC. and The City of Terre Haute.
Reinforced Concrete Design II
Foundation Engineering CE 483
RM Product Update October 2009 Alexander Mabrich, PE, Msc Senior Engineering Consultant.
Office of Highway Safety Bridge Load Rating Dan Walsh.
Office of Research and Engineering Finite Element Analysis Carl R. Schultheisz.
Public Information Meeting Rehabilitation of Bridge No Flat Rock Hill Road over I-95 Old Lyme, Connecticut Rehabilitation of Bridge No Flat.
By PARIKH KALPESH. Overview Introduction Structural evaluation of the bridge deck, girders, abutment, and piers Recommended non destructive tests Short.
Sensitivity Evaluation of Subspace-based Damage Detection Technique Saeid Allahdadian Dr. Carlos Ventura PhD Student, The University of British Columbia,
Foundations for offshore wind towers
Details of Construction Lecture-2 “Shallow Foundation”
University of Maryland Department of Civil & Environmental Engineering By G.L. Chang, M.L. Franz, Y. Liu, Y. Lu & R. Tao BACKGROUND SYSTEM DESIGN DATA.
Feasibility Level Evaluation of Seismic Stability for Remedy Selection Senda Ozkan, Tetra Tech Inc. Gary Braun, Tetra Tech Inc.
Spectron Superfund Site Proposed Plan Contaminated Shallow Soils U.S. EPA Region III June 26, 2003 Philadelphia, PA Robert J. Sanchez US EPA - Remedial.
1 Driven Pile Foundation Support- Cost Components Wagner Komurka Geotechnical Group, Inc PDCA Professors’ Driven Pile Institute June 15-16, 2009.
AN INTEGRATED DESIGN CONCEPT … … FROM UNDERGROUND UP TO THE TOP ODOTECHNIKI LTD CONSULTING ENGINEERS Address: 59, 3 rd September Str.
Driven Pile Design George Goble. Basic LRFD Requirement η k Σ γ ij Q ij ≤ φ g R ng η k – factor for effect of redundancy, ductility and importance γ ij.
Robert M. Arnold Building Fred Hutchinson Cancer Research Center
A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T.
LONG TERM GEODETIC MONITORING OF THE DEFORMATION OF A LIQUID STORAGE TANK FOUNDED ON PILES P. Savvaidis Laboratory of Geodesy Dept. of Civil Engineering.
Introduction to Soils Testing & Mechanics
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Geotechnical Conditions Tom Joos Civil/Structural Engineer BNL Plant Engineering.
City of Winnipeg SOUTHWESTERN RAPID TRANSIT CORRIDOR Bidder Meeting October 16 th, 2009.
Kansas DOT Research Project Implementation Presented By Rick Kreider (Chief of Research) Created By Susan Barker (T 2 Engineer)
Decision Making and Data Management in Geotechnical Engineering
Wave Equation Applications 2009 PDCA Professor Pile Institute Patrick Hannigan GRL Engineers, Inc.
Rapid Construction of Bridge Piers with Concrete Filled Tubes
DESIGN OF AIRPORT TERMINAL AND CONTROL TOWER
Soil mechanics and foundation engineering-III (CE-434)
Brookeville Bypass Final Design Presentation Initech May 6, 2004.
SEISMIC & WIND ANALYSIS OF BRIDGES
General Formulation for Surface and Embedded Foundations (Gazetas,1991) FIGURE XXX (MIWA, 20XX) A number of investigations have been done after earthquakes.
Settlement prediction for deep foundation piles using artificial neural networks Arshiya ABADKON1*, Muhammed Ernur AKINER1 1Bogazici University, Civil.
AN OVERVIEW OF SHALLOW AND DEEP FOUNDATION SYSTEMS
Structural Health Monitoring of Chulitna River Bridge
Deep Foundation Institute Bay Area Rapid Force Pulse Seminar
Piling.
The Engineering of Foundations
Structural Engineering: The Design of Sky Scrapers and Foundations.
TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
Oregon DOT Integral Abutment Design Criteria
Clay Mineralogy & Geotechnical Applications Compiled by: Dr. Adly Al-Saafin GULF CONSULT.
Cláudia Santos1, Alexandre Santos-Ferreira2 & Ana Paula Silva3
S S SUBMITTED BY:- CHARU BHARDWAJ civil engineering
Lateral Earth Pressure and Displacement of
Arch205 Materials and building construction 1 foundation
Christopher R. McGann, Ph.D. Student University of Washington
4th Annual Construction Law Summit
Physical-Model-Based Data Interpretation
Arch205 building construction foundation
American Concrete Pipe Association Short Course
Project Purpose & Description
Scott McFarlane & Richard Merifield
Graduation Project Bracing system for deep excavation.
Technical Excellence Practical Experience Client Responsiveness
Presentation transcript:

Bridge Pile Foundation Evaluation for a Soil Remediation Project Will Tanner, P.E. Senior Engineer, Geosyntec Consultants, Inc. Njoroge Wainaina, P.E., Senior Consultant, Geosyntec Consultants, Inc.

General Area of DRO Plume Site Background Railyard in Washington, DC > 100-year history Historic fueling operations result in plume of Diesel Range Organics (DRO’s) I-295 elevated above tracks 1957 original 1988 expansion Yard office construction and other improvements 2004 General Area of DRO Plume

Immediate regulatory agency involvement Site Background Plume was intercepted by the installation of new stormwater infrastructure in 2004 Subsequent inadvertent DRO release to culvert junction area and adjacent creek Immediate regulatory agency involvement Commence plume delineation and Corrective Action Plan (CAP) Creek

Environmental investigation to delineate extent of plume Site Investigation Environmental investigation to delineate extent of plume 4 I-295 Bridge Piers within the footprint Geotechnical investigation 4 Standard Penetration Test Borings 4 Cone Penetration Tests (CPT’s) Soundings Pier 9 Pier 8 Pier 11 Pier 10

General Subsurface Profile Silty Sand Fill Silty Sand Fill Low Plasticity Clay Low Plasticity Clay Silty Sand Silty Sand Very Still Clay Very Still Clay

I-295 Bridge Piers Pier 11 Pier 9 Pier 8 Pier 10

I-295 Bridge Piers & Proposed CAP Several remedies considered Excavation and Replacement Approx 10-12 ft deep 5 ft offset from pile caps Trans. Agency review and approval

Load Estimation on Bridge Piers AASHTO 2002 Standard 1957 Bridge Drawings and 1988 Expansion Piers 8 and 10 have same configuration

Load Estimation on Bridge Piers AASHTO 2002 Standard 1957 Bridge Drawings and 1988 Expansion Piers 9 and 11 have the same configuration

Load Estimation on Bridge Piers (Summary) Looking at 1988 pile caps directly adjacent to excavation Max vertical Load = 800 kips Max transverse (y-direction) Toward the excavation = 14 kips Max parallel (x-direction) Direction of vehicular travel = 8 kips Max overturning moment = 560 kip-ft Wind directionality at 0 and 30 degree angles to bridge

Pile Group Geometry and Load Distribution Cast in place concrete piles Independent groups 1988 group most affected Loads distributed assuming cap is perfectly rigid 813 k 380 k-ft 14 k 460 k-ft 9 k

Pile Group Geometry and Load Distribution Cast in place concrete piles Independent groups 1988 group most affected Loads distributed assuming cap is perfectly rigid 840 k 421 k-ft 15 k 558 k-ft 9 k

Pile Group Geometry and Load Distribution Apply loads evenly across cap Superposition Rigid cap PILEGRP Resolve loads to single pile Ready for Lpile!

Use of pile-soil-pile modifiers to simulate group behavior Lateral Load Analysis Iterative finite difference computational approach implemented in Lpile Use of pile-soil-pile modifiers to simulate group behavior Two overall approaches Forward solution using resolved structural loads Inverse solution using target max. deflections of 0.25 inches (limit)

Parameters based on mix of lab data and literature values Lateral Load Analysis Reese Sand D = 4ft Selected p-y models Parameters based on mix of lab data and literature values Pile Properties 12 in dia. “CIP” piles Resteel cage 4 #6’s Soft Clay D = 16ft Reese Sand D = 39ft Stiff Clay D = 73ft

Lateral Load Analysis - Forward Single pile analysis P-multiplier = 0.7 (AASHTO 2010) for leading row Pier 8 (x-direction) Axial load = 48.64 kips Lateral load = 0.46 kips Calculated deflection = 0.06 in. Pier 9 (x-direction) Axial load = 50.58 kips Calculated deflection = 0.02 in.

Lateral Load Analysis – Inverse Deflection threshold for entire group = 0.25 in Pier 9 9 k applied

Conclusions and Recommendations Calculations demonstrated minor deflections are expected as a result of the excavation Inverse analysis demonstrated that the load required to move an entire pile group 0.25 inches is an order of magnitude larger than the applied load Both approaches indicated little concern However the bridge structure is a critical part of DC traffic conveyance Recommend pre and post construction condition assessments Construction monitoring program

Pre-Construction Condition Assessment

Monitoring Program Threshold value = 0.25 in Limit value = 0.50 in If exceeded, increase frequency of monitoring Limit value = 0.50 in Stop work if reached Notify agency Immediately place fill in excavation

Construction Excavation near Pier 9 Survey at Pier 9 pile cap

Monitoring Program - Results No discernable movement trends detected System “noise” of about 0.15 inches No threshold exceedance No limiting value exceedance

Post Construction Condition Assessment No additional distress observed on the inspected bridge elements (piers, bearings, girders, decking, etc.) Before After

Questions Thank you! Questions?