Prepared by Kim Randall Development Officer Hastoe House Association

Slides:



Advertisements
Similar presentations
Revised Environmental Site Assessment Guidelines & Asbestos Inspection Guidelines for Bridges.
Advertisements

New Homes Construction Overview To Code 4 Long Meadow, Diss Mark Hart Divisional Construction Director.
TIME MANAGEMENT 641 Topic 03 Activity Sequencing.
Timber Framed Structures
Historic Buildings Grant-Aid Scheme Details Built Heritage Directorate NIEA.
Floors construction After the foundations have been completed and the external walls constructed the construction of the floors commences.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Moray Street, Macduff: Insulation and Renovation Project SUMMARY The Moray Street Project involves local authority homes which have an extensive history.
Federal Aviation Administration Project Status Update: R90 Tracon, STL ATCT, MCI ATCT, mold and moisture issues Presented to : CSA Terminal and Technical.
REMEDIATION OF INCE CENTRAL ESTATE IN WIGAN A Part 2A Site Tony Brown, SiLC – Director of Ground Engineering John Crowther, SiLC - Technical Director 22.
Now is this a high risk job?. HIGH RISK JOBS – RED CODE WORKING WITH ASBESTOS, OR UNDERTAKING A JOB WHERE THERE IS A LIKELIHOOD THAT ASBESTOS IS PRESENT.
1 FUTURE EXPLOITATION OF THE EAST AREA Infrastructure and Equipment - Civil Engineering issues. Jonathan Carr – GS / SE.
Prefabricated Timber Frame Construction
The West London Free School Palingswick House Update.
We appreciate your co-operation during our works and any guidance you provide to help us minimise the impact we make on your lives will be gratefully received.
Construction Defect Mitigation Construction Cost Recovery Construction Litigation Consultants, LLC Jerry Peck Slide 1 of 12 slides / Total.
Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
Process Protocol Demonstrator Implementation of the Process Protocol at the Britannia Walk Development Stuart Carmichael Process Network 7 March 2002.
TRENTON Casing Filler Presentation
Name ________________ Unit 6/P6 – Traditional Construction Most common foundation = strip Damp Proof Course 150mm above ground level External Walls are.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
FLOORS CONSTRUCTION After the foundations have been completed and the external walls constructed the construction of the floors commences.
About Morgan Sindall Morgan Sindall is a leading UK construction and regeneration group operating through five divisions of construction and infrastructure,
Learning Outcome Lesson Objective
Installing A Bathroom Shower Panel American Bath Enterprises, Inc. The Bath Tub & Shower Enclosure Innovators!
CE Electric UK Major Incident Management 1 COMMISSION ON FLOODING Friday 9 October 2009 Andrew McLeod CEng MIET Emergency Planning.
When all the walls have been coated with Carlite finish and dried the plumbers can return to fit all the necessary pipe work and the radiators. Then a.
THE WATERPROOFING STANDARDS
Progress Report September 2015 Prepared by Kim Randall Development Officer Hastoe House Association Morris Close Burwash.
Dear Local Resident Kingston Regal Richmond Road, Kingston Upon Thames, Surrey KT2 5ED Welcome to the first issue of our residents newsletter which.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Ryan Thurston | Duncan McLennan
Construction Home Loan Fact Sheet
The Design Team Carl James.
Prefabricated Timber Frame Construction
Temporary Works – P8 Project Practice.
The design and construction of ground floors:
Administration of a FIDIC Contract - Pre-Contract Phase -
RIBA Plan of Work 2013.
Caryl School Open Hearing March 26, 2007.
Clydebank Town Centre Office.
Temporary Works Co-ordination
XRN4361 – UK Link Release 2 - Delivery
Project Development and Managing your Build Agenda
Suppliers without a Contract
Progress Report November 2015
PREPARATION FOR WINTER
Minuteman Vocational Technical Regional High School Progress
Eagle Programme : 4 Box Summary
20 Chestnut Drive, Mansfield
The Beehive House, Castledine Street, Loughborough
Purchase Order for Services
Progress Report January 2016
Name____________________________ Tutor Group _____
Project Name – ID # 7/1/2009 Current Project Status Project Issues
Value of contract: Length of contract: Contract start date:
Supported Living Scheme Reviews
14 Crow Hill Rise, Mansfield
Xoserve IX Refresh Customer Update 03/01/2019.
Lindleys Mill, Prospect Place, Sutton In Ashfield
Coppice Ridge, Fiskerton, Newark
Purchase Order for Services
BCAR & The Technical Guidance Documents Conference 2019 Part E: Sound
Software Reviews.
Preventive Maintenance Service Agreement
RIBA Plan of Work 2013.
Community Practice Asset Management.
Formal handover of construction pack to operations
Advancd Measurement and Contract Administration
Presentation transcript:

Prepared by Kim Randall Development Officer Hastoe House Association Morris Close Burwash Progress Report March 2016 Prepared by Kim Randall Development Officer Hastoe House Association

Scheme Review Block A Scaffold now struck. Repairs to dpm will be implemented to achieve water tightness before re erecting scaffold to install roof coverings Insulation, breather membrane and counter battens complete to all roofs External wall insulation, breather membrane and battens 75% complete Instructions issued to PAGeoContracting for remedial works to external DPM and service penetrations to Block A Foxdown instructed to excavate in readiness for remedial works. Plot 6 sub floor has been dried out but water has reappeared, this is suspected to be rainwater ingress through the incomplete/defective edge DPM detail Order placed with drying out company to commence when water tightness is achieved Block B roof tiles stripped. Holes in breather membrane and insulation made good. Roof recovering and remedial works to roof lights Service penetrations and verge details will be completed prior to scaffold strike which will enable commencement of remedial works to external DPM

Remedial Works Water has been located in the void between the ground level and floor slab. Specialist engineer has been to site to inspect the issue and provide solution External insulation installed External wall insulation, breather membrane and battens 75% complete Roof tiles stripped. Holes in breather membrane and insulation made good. Roof recovering and remedial works to roof lights completed.

Key Project Dates Description Date Contract commencement date 29.06.14 Drying out plots and DPM integrity test 15.03.16 Complete insulation and breather membrane to block A elevations 18.03.16 Excavate in readiness for remedial works to block A external DMP 16.03.16 Complete remedial works to block B roof 25.03.16 Snagging & desnagging TBC Estimated handover date September 2016

Project Risk Risk Status change in period Standard of existing construction Structural remedial works complete, records to be sent to Canham Standard of existing construction Dampness/water ingress discovered to Block A plots 1, 2, 3, 4 and 6; Block B Plots 7 and 10. Remedial works required to damp proof membranes. Air tightness Replacement membranes to be installed to all plots Defective roof coverings to Block A require remedial works Remedial works will address defects Defective roof detailing to Block B verge and penetrations discovered. Also deflection to Block B roof discovered, measurements provided to Canham. Report received from Canham, no issues with deflection. Remedial works in progress

Scheme Details 8 x affordable units 2 x shared ownership 10 units in total 1 x 1 bedroom bungalow 2 x 1 bedroom flats 2 x 2 bedroom flats 4 x 2 bedroom houses 1 x 3 bedroom house Site possession 08.04.14

Hastoe Housing Team - Burwash

Contact List Hastoe Kim Randall - Development Officer 020 8973 0427 krandall@hastoe.com Responsible for managing the development of the scheme RG Carter Nick Pitcher- Site Manager Contact details T.B.C Responsible for site management Rother Council Amy Fearn – Housing and Asset Development Officer – 01424 787514 Amy.Fearn@rother.gov.uk Responsible for allocation queries and Rother Council waiting lists for local residents

Summary The scheme has been slipping behind schedule for several weeks and we have not had a revised handover date. Productive work during this reporting period has been confirmed as delayed due to the amended planned site works to accommodate the necessary repairs to the DPM. Without the basic building being weather tight and dry the airtight membrane works cannot commence.  During the last four weeks little progress has been made due to the fundamental issues of water ingress to the ground floor void postponing and stopping progress on block A and having similar effects on the DPM on block B where the roofs are currently being stripped off to repair the membrane and resolve the issue of the dipping on the rear of block B. The specialist membrane engineer was on site to discuss options to resolve the issue with the membrane and I believe we have a solution. We will have to excavate around the outside of both block A & B to expose the membrane, this need to be made airtight and we will also need to ensure that the water ingress has fully dried out and this will take a minimum of 14 days.   Once the membrane has been repaired we will hose test the external area to ensure that no water will penetrate the membrane to confirm we have resolved the water ingress issue.