Spoke section of the ESS linac: - Status of prototypes and CDS-SL

Slides:



Advertisements
Similar presentations
ESS Cryogenic System Design
Advertisements

WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
Spoke test in vertical cryostat IPNO-UU Meeting on spoke test program, 2 nd -3 st October 2013 IPNO Team.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
TE-CRG Activities D. Delikaris, TE-CRG.
General overview of WU : Cryogenic Distribution for Elliptical Linac Jarosław Fydrych Cryodistribution Project Engineer Preliminary Design Review,
C. Darve / Technical Board – December 13 th, 2012Preliminary pressure vessel code requirements Preliminary pressure vessel code requirements Technical.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
O. Kester, NuSTAR annual meeting, 27/02/2013
High Voltage modulators ESS developments Carlos A. Martins ESS Accelerator Division, RF electrical power systems.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
ESS WP4 Strategy for series production ESS TAC10 – 5th to 6th November Lund Sébastien Bousson WP 4 leader.
Chapter Editor: John Weisend TDR Chapter 6 Cryogenic System, Vacuum System & Test Stands.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
ESS Program Plan and Schedule Update
WP High Beta Cavities Delivery
Teleconf ACS – FREIA 28th March 2017
Cryomodule test stand at ESS site
Process Simulation for the LCLS-II Cryogenic Systems
at STFC Daresbury laboratory
CSP 25th November 2010 Technical agreement number 3: overview
Complementary ISTC Projects #3888, 3889p
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
Functional interfaces
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Hollow e- lens, Cryogenic aspects
Spoke CDS PDR Closeout J. G. Weisend II June 10, 2016.
ESS RF Development at Uppsala University
Cryogenic C&C Scope of work
Status of the cryogenic system for B180
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
UK RFD Pre-Series cryomodule
recent activities our company Jean Claude Le Scornet - Tomas JUNQUERA
Optimum cryomodule length at the ESS
Teleconference ACS – FREIA 20th February 2018
Report on HIE-ISOLDE Status
Jaroslaw Fydrych SHC Lead Engineer
Status of the CNRS Contribution to the ESS Accelerator
Prototype cryomodule development
Ciprian Plostinar Workshop on Testing and Commissioning
Daresbury ESS In-Kind Contributions
Target Helium Cooling System Design Code 10th Target Technical Board Meeting Ulf Odén WP2 Manager 19 April, 2019.
Licensing requirements for Cryomodules
Overall time schedule of SRF activities
Double-Spoke Cavities
WP11: CDS-SL CDR Overview
CNRS contribution to ESS – 01/02/17
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Teleconference ACS – FREIA 19th June 2017
Prototype cavities development
High Level Readiness Reviews
ESS Spoke cryomodule testing: cryogenic experience
IKCA CEA Technical ANNEXES Follow up 18th DECEMBER 2015.
Status of the ESS High Power RF Systems
PANDA Cryostat and Yoke
UPPSALA UNIVERSITY_GERSEMI PROJECT
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
Accelerator Installation Schedule
Burst Disc Experiences at CEA Test Stand
Burst Disc Review Closeout 21 May 2019 J.G. Weisend II, Chairman.
Work Unit AIK 11.2 CDR of the CDS-SL Quality
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Spoke section of the ESS linac: - Status of prototypes and CDS-SL P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on behalf of the IPNO team

Prototype cryomodule and valve box Last ESS bi-weekly meeting: May 30th 2017  progress status from this meeting Tests at IPNO: Goal: RF and cryogenic tests of {1 Spoke cavity (Giulietta) + 1 mock-up cavity}  the cryomodule was entirely disassembled to change from the {2 mock cavities} configuration to the {1 Spoke cavity + 1 mock-up cavity} one. June: Test Valve box: . ready for cryo tests (repaired, leak tested and set in the Supratech experimental platform) . design of the transport to Uppsala: to design the transportation frames of the prototype cryomodule and valve box, mechanical analysis of the prototype valve box were carried out: eigen modes of the test valve box were estimated; allowable accelerations wrt to the elastic-damping transport frame were evaluated. Cryomodule: . Assembly of the cryomodule under progress (all components repaired) ; . Repaired VLP branch line of the cryogenic jumper of the cryomodule repaired by the manufacturer and delivered on June 14th; integration of this line by IPNO started Helium infrastructures: . Were not (fully) available due to supervision defects  valve box cryo tests postponed to July

Prototype cryomodule and valve box Tests at IPNO: Goal: RF and cryogenic tests of {1 Spoke cavity (Giulietta) + 1 mock-up cavity}  the cryomodule was entirely disassembled to change from the {2 mock cavities} configuration to the {1 Spoke cavity + 1 mock-up cavity} one. July: Test Valve box: . cryogenic tests performed = cool-down and 4 K mode: C&C tested (PLC controls such as regulation loops, etc.) + cryofluids consumption  good results i.e. the valve box was operated and works as expected;  preliminary test report sent to ESS. Cryomodule: . cryomodule assembled and leak tested; . cryomodule installed in the Supratech experimental platform; . repaired VLP line of the cryogenic jumper prevented the cryomodule from its connection to the valve box (VLP too long…) Helium infrastructures: . Supervision temporally repaired (new server and OS environment needed)

Prototype cryomodule and valve box Tests at IPNO: Goal: RF and cryogenic tests of {1 Spoke cavity (Giulietta) + 1 mock-up cavity}  the cryomodule was entirely disassembled to change from the {2 mock cavities} configuration to the {1 Spoke cavity + 1 mock-up cavity} one. August: Test Valve box: standby (waiting for the cryomodule) Cryomodule: . VLP line of the cryogenic jumper shortened; . cryomodule connected to the valve box; . He leak tests of this connection (multichannel cryogenic line) are carried out  if no leak detected: cryomodule and valve box ready for the cryo and RF tests  tests to be performed in September. Helium infrastructures: . New server and OS environment being installed . Re-qualification of the He high pressure storage (Pressure Equipment Directive): storage sectors will be successively removed from service for this qualification  He storage capacity will be diminished this autumn (ESS experiments should not be affected as ESS is the priority);  infras momentary shutdown will be performed; (ESS experiments might be affected)

CDS-SL Schedule: Following the CDR (end of April) a new detailed schedule was sent to ESS on July 5th (to be discussed) Design Design is still under progress Procurements Control (cryogenic) valves: Contact notified on July 19th kick-off meeting on July 20th Heat exchangers: Contract notified on July 12th kick-off meeting on July 21st Valve boxes: Administrative work began (see news from the CNRS procurement department) The date for the publication of the call for tender is targeted to be end of Sept. 2017

CDS-SL SCHEDULE Guidelines: Procurements are divided into several calls for tenders: priory the components which are on the critical path (do not wait for the finalization of the other components) save time on the administrative aspects of the calls for tenders: (smaller budget  simpler procedure  less administrative time)  expect to save time (or not to loose)  more human resources involved (calls for tender and manufacturing follow-up) Valve boxes (critical path) production is organized such that: a 1st series valve box is produced and tested at the manufacturer premises (control and tests + LN2 cool-down) = FAT at IPNO: LHe tests then the 12 series valve boxes are produced  organization of the series (mass) production during the production of the first valve box: . human resources (team completion) (manufacturers feedback; . materials procurements;  check the manufacturing (and design) with the complete test of the first valve box Some milestones: Valve boxes (critical path) Call for tender publication: end of September 2017 Procurement notification : beginning of 2018 1st valve box FAT: end of October 2018 1st valve box delivered to ESS: end of November 2018 Last valve box delivered to ESS: August 2019 CDS-SL installed and tested: beginning October 2019

Thank you for your attention CSP12 28 Novembre 2014 Thank you for your attention