L. Gentini, A. Bertarelli, F. Carra

Slides:



Advertisements
Similar presentations
SPL Intercavity support Conceptual design review 04/11/ A. Vande Craen TE/MSC-CMI.
Advertisements

Summary of the discussion for the commissioning session 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 6/ 1/ 2006 T.Okugi (KEK)
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
Progress on the MICE 201 MHz Cavity Design Steve Virostek Lawrence Berkeley National Lab RF Working Group Fermilab August 22, 2007  automatic.
Progress on the Coupling Coil & Focus Coil Interface Engineering
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
F.E.T.S. Mechanical Engineering Update by P. Savage 13 th August 2008.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
MECHANICAL DESIGN OF TCSP COLLIMATORS Secondary Collimators Embedding BPMs L. GENTINI, A. Dallocchio, A. Bertarelli, F. Carra, M. Garlasche.
RFCC Module Design Update  automatic tuners  cavity suspension  cavity installation Steve Virostek Lawrence Berkeley National Lab MICE Collaboration.
Changes to IR6 dump protection elements B.Goddard, W.Weterings, C.Maglioni, R.Versaci, T.Antonakakis, R.Schmidt, J.Borburgh, J.Blanco, plus many other.
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
Engineering Department ENEN Status of TCSP manufacturing Collimation Working Group (CWG) 24 June 2013 A. Dallocchio, A. Bertarelli, F. Carra, L. Gentini,
TCDI operation until LS2 LIU-SPS-to-LHC Transfer Line Protection Devices (TCDI) Review 1 Oliver Aberle 26/03/2014 O. Aberle (EN-STI-TCD)
LHC Machine Protection System Review LHC Machine Protection System Review Oliver Aberle13 April 2005 with input from R. Assmann and R. Losito Ensuring.
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
TCLDA Design status Collimation Upgrade Specification Meeting L. GENTINI.
A. Bertarelli CERN TS – MME Group 1 CERN European Organization for Nuclear Research Actuating system of the LHC Collimators (Phase 1) Main Features.
Review of Mechanical Movement and Motorization for LHC Collimators The LHC Collimation project LHC Collimators for Phase 1 Alessandro Bertarelli.
Lukasz Krzempek TE-VSC-DLM 28th WP8 Bi-weekly meeting Tuesday, 24 November 2015 Vacuum layout (Experimental side)
Updated Design of TCLD whit reduced jaw length Collimation Upgrade Specification meeting L. GENTINI.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
Vacuum, Surfaces & Coatings Group Technology Department 22 nd January 2015 C. Garion2 Beam Line Interconnection: snapshot of present design principles.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Francesco Cerutti ENERGY DEPOSITION ASPECTS FOR LHCb REQUEST 5th Joint HiLumi LHC - LARP Annual Meeting Oct 29, 2015 through L.S. Esposito’s work and essential.
Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE) Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE)
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Mechanical Upgrade Interaction Region IR1 Luigi Pellegrino Mechanical Engineering Group (LNF Scientific Committee, May 9, 2013)
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
SPL RF coupler: integration aspects
Francesco Cerutti, Andrea Tsinganis WP10 Energy deposition & R2E
Alignment of VSC components along LSS 1&5
Solenoid Yoke Door-Barrel Connection
TANB Integration – LS2 BLM Relocation Proposal C4R8 and C4L8
HL-LHC Aperture Update
The Budker Institute of Nuclear Physics
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
PANDA Yoke of the Magnet
A. Rossi on behalf of the whole team:
INSTALLATION SEQUENCE
LARP Phase II Secondary Collimator RC1
Challenges of vacuum chambers with adjustable gap for SC undulators
Preliminary Y-chamber specifications – First draft
R. Kersevan, TE-VSC-VSM 30/06/2016
Cedric Garion, TE-VSC-DLM, WP12
Region between TAXN and D2 in HL-LHC IR1/5: Implications on Collimator Design Alessandro Bertarelli, L. Gentini (EN/MME) On behalf of the LHC.
Sphere Option for Helical spring CF16 Bellows Adjustment bolts (horizontal plane) CF38.
TCTW Collimator Design F. Carra1,2 A. Bertarelli, M. Garlasche, L
The 11T cryo-assembly: summary of design and integration aspects
Design of Distribution Feedbox at LHC P7
Challenges for FCC-ee MDI mechanical design
Magnetic gap calculation
PBC Method Flat Mirror Gas Mixture Dielectric Mirror Pump Window PM
Discussion on the TDI impedance specifications
X-Rays made by P. Lepeule (TE/VSC) and J-M Dalin (EN/MME)
questions for cern – doyle rev 7/09/07 1/5
LARP Rotatable Collimators for LHC Phase II Collimation
Additional Upstream Coil Shielding
LARP Phase II Secondary Collimator RC-1
LHC Collimator – RF Contact Concept (180o wrap)
Collimator design with BPMs (TCTP)
HL-LHCV1.4 (BI) R. De Maria WP13 meeting 3/9/2018.
HL-LHC - WP15 modifications Coffrets Prise C4L8
HL-LHCV1.4 (BI) R. De Maria WP13 meeting 3/9/2018.
Presentation transcript:

L. Gentini, A. Bertarelli, F. Carra TCTPV - TCTPH - TCLX collimator designs between TAXN and D2 ColUSM: Collimation Upgrade Specification Meeting L. Gentini, A. Bertarelli, F. Carra

TAXN  D2 area TAXN D2 TCTPV TCTPH TCLX

SPECIFICATION REQUIRED TCTPV TCTPH TCLx Orientation Vertical Horizontal Absorber Material Inermet IT180 Absorber Cross-section 34 x 20 mm2 70 x 40 mm2 Jaw Stroke 40 (+5) mm 30 (+5) mm Interference* with present layout 11.3 mm 43 mm 58.1 mm * Interference calculated assuming a standard collimator tank and including baking equipment thicknesses (tank jacket thickness 25 mm and/or vacuum chamber wrapping 5 mm) and a ID/OD 90/94 mm vacuum chamber A. Bertarelli’s presentation 5-2-2016 Source: A. Rossi (BE/ABP) N. Joannon (EN/ACE)

Tctpv – new design New RF finger cycling test required New design VACUUM VESSEL JAW MECHANICAL TABLE TANK SUPPORT First solution NEW design: 20 mm bigger Bellow bigger Aperture ø91 mm Standard TCTP NEW design Stroke +40 ; -5 Standard TCS Second solution NEW design: Bigger bellow Aperture ø91 mm NEW design 10 mm thinner New design Old design ø80 ø134 ø91 ø134 New RF finger cycling test required

Tctpv – new jaw design (solution 2) Thicker back stiffener Slim jaw design: Thickness optimization of jaw assembly allows saving 10 mm per side, keeping same jaw functionality. This translates into a 20 mm reduction of the tank width STANDARD DESIGN SLIM DESIGN Axle offset inward 10 mm Thicker back stiffener

TctpH – new design VACUUM VESSEL JAW MECHANICAL TABLE TANK SUPPORT First solution NEW design: Double beam Coll. aperture ø91 mm 2nd beam ch. aperture ø91 mm Standard TCTP Standard TCS Second solution TCLX Common design TCLX common design

TcLX – preliminary design Short and long RF fingers VACUUM VESSEL JAW MECHANICAL TABLE TANK SUPPORT NEW design: Double beam Coll. aperture ø91 mm 2nd beam ch. aperture ø80 mm NEW design Abs. blocks 70x40 mm NEW design Stretched Stroke +30 ; -5 NEW design Tank support Standard support Short and long RF fingers

TctpH / tclx common design                            s [m] half separation [mm] TCTPV 131.449 80.42 132.449 81.919 TCTPH 133.45 83.419 134.45 84.917 TCLX 135.207 86.052 136.207 87.55 Separation gap between TCTPH upstream and TCLX downstream is 9.7 mm. The 2nd beam chamber must be flexible enough to assume this displacement (±5 mm) Source: R. De Maria (BE/ABP) 1480 1000 171 169.834 170.554 166.118 166.838 TCLX / TCTPH 171.384 172.104 175.1 175.82 TCLX TCTPH

TctpH / tclx common design 171 ±5 Bellow Chamber support New BPM RF contact The chamber of the second beam is insert on one side and welded on the opposite flange after assembly.

TctpH / tclx common design The 2nd beam chamber cannot be bigger than ø60 mm The actual design must be modified to have tolerance margin between the 2nd chamber and the jaw. No automatic MKT connection A DN100 flange can be used also on the 2nd beam chamber, but really tight space for installation 5 DN 100 flange - aperture ø91 DN 63/100 flange - aperture ø60

Thank you for your attention summary TCTPV VACUUM VESSEL JAW MECHANICAL TABLE TANK SUPPORT First solution NEW design: 20 mm bigger Bellow bigger Aperture ø91 mm Standard TCTP NEW design Stroke +40 ; -5 Standard TCS Second solution NEW design: Bigger bellow Aperture ø91 mm NEW design 10 mm thinner TCTPH NEW design: Double beam Coll. aperture ø91 mm 2nd beam ch. ø91 mm TCLX design TCLX / TCTPH NEW design: Double beam Coll. aperture ø91 mm 2nd beam ch. ø60 mm TCLX (single design) 2nd beam ch. ø80 mm NEW design Abs. blocks 70x40 mm NEW design Stretched Stroke +30 ; -5 NEW design Advised ? Mandatory Thank you for your attention