BE-ICS activities for LIU Project

Slides:



Advertisements
Similar presentations
PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
Advertisements

Safety Management of the LIU Project A. Funken Anne Funken, LIU PT 21/05/15.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
May Exp-Area meeting1 Safety Systems Installation status Flammable Gas Detection System Fire Detection System in SG8 ODH Detection System CO2 Detection.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Joint ILC/CLIC Safety document ► Incentive for this document:  Share effort to define a coherent safety protocol for future linear colliders.  Insure.
TS Workshop, Archamps, May 24 – May 26, 2005 The LHC Access System Status report – May 2005 P. Ninin & the Access project team TS/CSE.
LHC ACCESS SYSTEM 1 Authors: P. Ninin, L. Scibile, T. LadzinskiEDMS: Access Control and Safety System for the LHC Experiments P. Ninin L. Scibile.
1 1. Some recent views ( ) 2 Linac tunnel
LIU Safety Packages: Kick off Meeting A. Funken, I. Kobzeva BE Safety Unit LIU Safety Packages Kick off Meeting, 30/07/2015.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
Purpose NEW BEAM DUMP TUNNEL Launch Safety Agreement - conventional aspects LIU-SPS external beam dump meeting - C. Colloca DGS/SEE LSA conventional.
Design, integration and installation milestones Legend: 2015/Q1= 1 st quarter of 2015 (January-March) Phase 1 = proton & laser beams operation Phase 2.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Safety Documentation How do we organize it and what will be the contents? A. Funken, LIU Project Meeting, 26 th September 2013.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Linac4-PSB 160 MeV connection readiness review Tuesday 30 August August 2016 Linac4-PSB 160 MeV connection readiness review 2.
Electrial Safety LS2 days November 2016 AP
Magnet activities in SPS during EYETS
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
YETS & LS2 Works EN-EL / Power distribution
SPS Personnel Protection System Renovation Project
ABT-EC EYETS Activities 2nd reports
BE-CO Activities for LIU-CPS and LIU-SPS
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
EYETS Works EN-EL [ FC excluded ]
BE-ICS Activities during the LS2 Period (15 min)
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
LIU Consolidation project (INDICO ) E. Blanco BE/ICS
Evolution and future of the Access safety and control systems
LIU – EVM status and next steps
LIU–PLI report LIU PSB meeting.
Planning and Installation
BE-ICS activities for LIU Project
East Area Renovation Project team #6 Launch safety agreement
LIU–PLI report LIU SPS meeting.
EN 4946 – Refurbishment of Electrical Substations
The ELENA Safety Documentation «time to prepare the safety clearance»
TE-ABT Activities for LS2
M.Jonker CTC MPO-WG status
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
B245 Modifications & Cabling Update
M.Tavlet, H.Taureg - ALICE
HL Consolidation Day Analysis of needs from BE-ICS
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
SPS activities during LS2 TE-EPC (Power Converter Group)
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
Acknowledgments: LIU-PT members and deputies, H. Bartosik
YETS PS + PS SWY + TT2 Facility Coordinator:
YETS & LS2 Works EN-EL / Power distribution
TE-MSC activities in SPS during YETS
Status with crucial LSS5 kicker transmission line cables
GIS Portal Racks Project
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Vers PS YETS PS Booster David HAY & Cyrille BEDEL.
Experimental Areas – LS2 planning
North Area Safety Review 2019
Access Control for CERN Experimental Areas
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

BE-ICS activities for LIU Project LIU Project Work Breakdown Structure: LIU-PSB 18 Alarms N.A.* LIU-PSB 19 Access system, doors N.A* LIU-PS 18 Alarms S. Grau LIU-PS 18 Access system, doors R. Nunes LIU-SPS 18 Alarms N.A.* LIU-SPS 19 Acess system, doors T. Ladzinski LIU-ION 17 Alarms N.A. LIU-ION 18 Access system, doors N.A. BE-ICS correspondants to be appointed A. Funken, 20/09/2017 LIU Project

BE-ICS: types of safety systems Level-3 alarm safety systems (AL3S) and safety alarm transmission: design, supply, installation, commissioning and acceptance test with HSE, maintenance and operation Access control and Personal Protection System: design, supply, installation, commissioning, acceptance test and maintenance Definitions according to IS37 – Level-3 safety alarms and alarm systems: Level-3 alarm Warns of the presence of a potential danger to human life, to property, or to the environment Level-3 alarm system (AL3S) Technical installation designed to detect and to inform principally the SCR of a potentially dangerous abnormality. It consists of a detector (or detection system), a transmitter (or transmission system), and a receiver (or reception system). A. Funken, 20/09/2017 LIU Project

BE-ICS: types of safety systems Access safety system linked to the safety elements - EIS (radiation hazards from beam, hazards from the machine – electricity, laser, RF/X-rays) Beam Imminent Warning (radiation hazard from beam) Automatic fire and/or smoke detection system* (risk of fire) Audible emergency evacuation system*: sirens and manual call points, break-the-glass type (risk to personnel), Emergency call system, e.g. red telephones* (information about various risks) Gas detection (flammable or toxic)* (risk of explosion or poisoning) Detection of oxygen deficiency* (risk of suffocation) Transmission of alarms Nota: Most systems (*) are AL3S, acceptance test with HSE. Risk mentioned into brackets according to IS37 – Level-3 safety alarms and alarm systems A. Funken, 20/09/2017 LIU Project

BE-ICS activities for LIU Project Connection of the Linac4 Interface Linac4-Linac2  ECR CPS-LJ-EC-0002 New EIS-Access and new sector in the Switch-Yard area (Sector 3) (Access system of Linac2 will be moved into the tunnel – request integrated but not in the scope of LIU) New EIS-Beam for the Switch-Yard area: L4T.TDISA.0740 and L4T.MBH0250 instead of the two actual EIS-Beam located in Linac2. LT.STP.10 and LT.BHZ.20 will be disconnected from the access safety system (PASS) EIS-Beam for the Booster area (PSB-Y-ES-0001): During Linac4 commissioning (beam up to LBE with access in the Booster): disconnection of the present EIS-Beam BI.STP FA and SW from the PASS For Linac4 operation: connection of the EIS-Beam L4T.TDISA.0740 and L4T.MBH0250 to the PASS Partial disassembly of Linac2  ECR CPS-LJ-EC-0003 Disconnection of the Linac2 MAD/PAD access control system, named YEA01.LN2-363 Access system to be provided during the working period or a guardian as compensatory measure A. Funken, 20/09/2017 LIU Project

BE-ICS activities for LIU Project PS Booster Installation of the new power converters in b.361  ECR PSB-K-EC-0001 Two additional smoke detectors will be installed in the new alcove and will be integrated to the existing fire detection system of BFR2 room in building 361 A fire warning horn will be placed above the alcove entrance grated door No additional smoke detection in BRF2 and BAT due to the new equipment New MPS for LIU Booster (POPS-B)  ECR PSB-EJ-EC-0008 Fire detection and emergency evacuation system in the new building Access control system for the reference magnet area in 245/S-403 under study (access to TE/MSC through D3 door shall be authorized by TE/EPC) No access control system foreseen for the building. Should it be in the light of the request from EN-ACE for an access control and CSA surveillance of the PSB technical areas building 361 (also a question from the PS-CSAP on 13 July 2017) ? D3 A. Funken, 20/09/2017 LIU Project

BE-ICS activities for LIU Project PS Booster EIS-Machine related to the Powering Configuration of the PSB bending magnets  ECR PSB-Y-EC-0001 Change of the access safety system in order to take into account the new MPS of the PS Booster without jeopardizing personnel protection. The request is to be able to determine in real time, the interlocks of the EIS-machine, called "BR.popsB", according to the powering configuration of the bending magnets. EIS-Beam for the Booster area (PSB-Y-ES-0001) Disconnection of the present EIS-Beam BI.STP FA and SW from the PASS (for Linac4 commissioning) Connection of the EIS-Beam L4T.TDISA.0740 and L4T.MBH0250 to the PASS (for Linac4 operation) There is no dedicated section concerning safety systems in the descriptive part of LIU-PSB Injection, Rings, Extraction No impacts of the LIU project on the existing safety systems installed in the PSB accelerator have been identified until now. This will be confirmed and documented while producing the demonstrative part (hazards inventory, risks induced and control measures to put in place, fire risk assessment). A. Funken, 20/09/2017 LIU Project

BE-ICS activities for LIU Project PS and TT2 There is no dedicated section concerning safety systems in the descriptive part of LIU-PS Injection, Ring, RF systems, TT2 consolidation and dump No impacts of the LIU project on the existing safety systems installed in the PS accelerator have been identified until now. This will be confirmed and documented while producing the demonstrative part (hazards inventory, risks induced and control measures to put in place, fire risk assessment) A. Funken, 20/09/2017 LIU Project

BE-ICS activities for LIU Project SPS Ring & Transfer lines There is no dedicated section concerning safety systems in the descriptive part No impacts of the LIU project on the existing safety systems installed in the SPS accelerator have been identified until now. This will be confirmed and documented while producing the demonstrative part (hazards inventory, risks induced and control measures to put in place, fire risk assessment) RF system upgrades  SRR SPS-LJ-EC-0001 Tunnel LSS3: no impacts of the LIU project on the existing safety systems installed in the SPS accelerator have been identified. The present cavities in LSS3 and the new ones will not produce X-rays. As a consequence, the cavities are not classified as EIS-Machine and are not interlocked with the SPS access safety system New building BAF3: Fire detection and emergency evacuation system in the new building No access control system foreseen for the building. Should it be in the light of the request from EN-ACE for an access control and CSA surveillance of the PSB technical areas building 361 (also a question from the PS-CSAP on 13 July 2017 for building 245) ? Plan activity 11415 declared related to the upgrade of the fire safety system in BA3 Faraday cage (in LS2) A. Funken, 20/09/2017 LIU Project

BE-ICS activities for LIU Project SPS New beam dump in ECX5  SRR SPS-LJ-EC-0003 Tunnel LSS5, ECX5: no impacts of the LIU project on the existing safety systems installed in the SPS accelerator have been identified, excepted: EIS-Beam: two Direct Current Transformers (DCCT) being part of the ion safety system in the North Area (BCTDC.51897 and BCTDC.51895) need to be moved downstream by ~25 m to half period 519 (BCTDC.51951 and BCT.51952) ECA5, kicker area: Fire detection: layer of fire detection units monitoring of the air will be installed near the kicker pulsed generators electronics and controls racks (by row of racks), and near the powering area Reconfiguration of the access sectorization A. Funken, 20/09/2017 LIU Project

BE-ICS activities for LIU Project LIU-Ions There is no dedicated section concerning safety systems in the descriptive part of LIU-Linac3 and LEIR No impacts of the LIU project on the existing safety systems installed in the Linac3 and LEIR accelerator have been identified A. Funken, 20/09/2017

BE-ICS activities for CONSolidation linked to LIU Project ??? To request to the consolidation project by BE-ICS : overhauling of the fire detection in the ECA5 cavern? It is recommended by HSE to evaluate the need of overhauling of the existing fire detection system located at the ECA5 ceiling level, to install (or update the existing) evacuation alarm system, to extend the automatic fire detection and evacuation coverage to the volumes that are used to evacuate SPS and ECA5 A. Funken, 20/09/2017 LIU Project

PLAN PLC related (not safety systems) Activities declared by BE-ICS WBS Level 3 Activity Title Responsible Group Person Responsible Activity Phase Contribution Group Contribution Contribution Resources Available Contribution finished Accepted periods PBU-PRJ 10697 POPS-B - New project BE-ICS JEAN-CHARLES TOURNIER (BE-ICS-AP) Coordination Yes Not Assigned na 10732 Install - Fire detection & Evacuation - New B245 - POPS Booster SILVIA GRAU (BE-ICS-AS) 2016-YETS-2017 Installation EN-EL Control cabling No Commissioning HSE-SEE Safety validation PBU-LN4 10048 Modify PS PPS (Personnel Protection System) for LN4 connection LOUIS HAMMOUTI (BE-ICS-CSE) LS2 Preparation EN-ACE Refurbishing works and construction new door with Switch Yard . Current LN2 integrated to SWY. A. Funken, 20/09/2017 LIU Project

PLAN LIU-IONS Contribution requests to BE-ICS No request A. Funken, 20/09/2017 LIU Project

PLAN LIU-PSB PLC related (not safety systems) Contribution requests to BE-ICS PLC related (not safety systems) Contribution Group WBS Level 3 Activity Phase Activity Title Responsible Group Person Responsible Contribution Contribution Resources Available Contribution finished Accepted periods BE-ICS PBU-PRJ Coordination 10697 POPS-B - New project JEAN-CHARLES TOURNIER (BE-ICS-AP) Yes Not Assigned na 10732 Install - Fire detection & Evacuation - New B245 - POPS Booster SILVIA GRAU (BE-ICS-AS) 2016-YETS-2017 Preparation 10311 Supply new converters for Booster Main Magnets (Dipole & Quadrupole) & Trims [POPS-B] TE-EPC FULVIO BOATTINI (TE-EPC-HPC) Installation of EIS new System No 2016,2017,2018 PBU-LN4 10048 Modify PS PPS (Personnel Protection System) for LN4 connection LOUIS HAMMOUTI (BE-ICS-CSE) LS2 Installation 10312 Connection of Linac4 to the PSB BE-ABP JEAN-BAPTISTE LALLEMENT (BE-ABP-HSL) safety checks, modifications of the access system, interlocks A. Funken, 20/09/2017 LIU Project

PLAN LIU-PS Contribution requests to BE-ICS No request A. Funken, 20/09/2017 LIU Project

PLAN LIU-SPS PLC related (not safety systems) A. Funken, 20/09/2017 Contribution Group WBS Level 3 Activity Title Responsible Group Person Responsible Activity Phase Contribution Contribution Resources Available Contribution finished Accepted periods BE-ICS SPU-PRJ 10754 Relocate SPS Beam Dump in LSS5 and LSS1 reconfiguration TE-ABT ETIENNE CARLIER (TE-ABT-EC) Preparation Reconfigure ECA5 sectorisation for easy access during operation Yes No 2016 Installation access system installation LS2 Commissioning Access system to ECA5 commissioning. LS2-Semester 4 10835 LIU-SPS RF power upgrade BAF3 BE-RF ERIC MONTESINOS (BE-RF-PM) coding of the control software 2016,2017,2018 Support during testing of CV installations 2016,2017,2018,2019,2020 10856 Relocate SPS Dump kicker HV systems in LSS5 VILIAM SENAJ (TE-ABT-PPE) 11415 SPS RF Low Level upgrade for LIU PHILIPPE BAUDRENGHIEN (BE-RF-FB) Upgrade of the Fire-Safety system Unknown PLC related (not safety systems) A. Funken, 20/09/2017 LIU Project LIU Project

PLAN Contribution requests to BE-ICS not yet declared in PLAN: LIU-PSB BRF2 alcove : Two additional smoke detectors to be installed in the new alcove and integrated to the existing fire detection system of BFR2 room in building 361 A fire warning horn will be placed above the alcove entrance grated door POPS-B: Access control system for the reference magnet area in 245/S-403 under study (access to TE/MSC through D3 door shall be authorized by TE/EPC) LIU-SPS ECA5, kicker area: Layer of fire detection units monitoring of the air will be installed near the kicker pulsed generators electronics and controls racks (by row of racks), and near the powering area A. Funken, 20/09/2017 LIU Project