Lynnhaven Parkway Widening Project Update November 12, 2015 Mitch Conner Area Construction Engineer Michael Johnson Construction Manager
Welcome Why We’re Here: Current Status of the Project Project Challenges What’s to Come
Current Status: 49% Complete Work is progressing on the bridge superstructure. Crews have begun sound wall installation. Water, sewer and storm drain installation is ongoing.
Project Challenges HISTORY Private utilities relocation – this is causing delays with placing the sound walls. Grade changes Drainage improvements Minimizing traffic and noise disruptions These challenges are putting the scheduled completion date of fall 2016 at risk.
What’s to Come Albright Drive/Lynnhaven Parkway: Two weekend closures for paving operations. Lynnhaven Parkway/Dalrymple: Partial closure for about 7 months
Questions?
Contact Information VDOT: Jennifer Gwaltney, Public Information Officer Jennifer.Gwaltney@VDOT.Virginia.gov 757-925-2583 City of Virginia Beach: Jessica Blackburn, P.E., Senior Project Manager Public Works – Engineering Jblackbu@vbgov.com 757-385-4837