MICE RF System Power Supplies, Control and Monitoring Status report

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Advertisements

MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
RF systems for MICE Andrew Moss The MICE RF Group and the TIARA WP7 Team Contributions include Daresbury, RAL, CERN, LBNL, LANL, FNAL, Strathclyde & Sheffield.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
MICE RF & Controls Paul Drumm. RF Layout 2 MW Amplifier Master Oscillator Controls etc 201 MHz Cavity Module 2 MW Amplifier 201 MHz Cavity Module CERN.
MICE VC Alain Blondel 1 NEWS and RF review.
THE MICE RF SYSTEM J.F.Orrett* A.J.Moss, ASTeC, Daresbury Laboratory, WA4 4AD, UK Accelerator Science and Technology Centre
MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
Microwave Amplifier Power Supply
Daresbury MICE Progress Andrew Moss Joe Orrett Peter Corlett.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
CLIQ power supply Integration. General view: -Schroff rack 19’’ 25U (500mm x 600mm x 1120mm). -2 fixed wheels +2 castor wheels with brake ⦰100mm.
RF Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration Meeting.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
TE-MPE-EE, 16-Apr CLIQ Power supply design J. Mourao TE-MPE-EE.
MICE - UK Project Progress Roy Preece 30 th April 2013.
MICE Decay Solenoid Quench Detector Trevor Hartnett Daresbury Laboratory.
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
S A Griffiths Target Review Jan 2009 Target Electrical / Control Schematic HexBridge Power electronics Interface PSU Capacitor Bank Local Control Interface.
MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013.
MICE MICE Target Mechanism Control Electronics Upgrade P J Smith – University of Sheffield James Leaver – Imperial College 2 nd March 2009.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Electrical & Control Power Supplies Trevor Hartnett.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Power Supply System for DRFS
CLIQ unit Integration. General view: -Schroff rack 19’’ 25U (500mm x 600mm x 1120mm). -2 fixed wheels +2 castor wheels with brake ⦰100mm. Capacitors Capacitors.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
Progress on the MICE RF High Power Drive Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE CM38 RF Parallel Session.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
ALBA RF Amplifiers based on IOTs CWRF08 - CERN, March 2008 Michel Langlois & Paco Sanchez 1 Michel Langlois & Paco Sanchez.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
MICE RF Power Status Paul Drumm ~ Sunday August 1 st 2004.
Technology Department BI.DIS general controls status R.A.Barlow EC section
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
ALBA RF System Paco Sanchez - 13th ESLS RF - DESY, 30 September Paco Sanchez, RF Group, CELLS (Consortium for the Exploitation of the Synchrotron.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
MICE RF – Installation at RAL Tim Stanley, MICE RF Engineer, RAL 2 June 2014.
High Voltage modulators ESS developments Carlos A. Martins ESS Accelerator Division, RF electrical power systems.
Andrew Moss STFC, ASTeC Example amplifier control system Example of current STFC copper cavity in operation –Using SF6 insulated waveguide –Conditioning.
High Power RF Systems for 2-8 GeV Fast Cycling Synchrotron PROJECT X (ICD-2) John Reid September 11, 2009.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
S A Griffiths CM42 June 2015 Electrical & Control.
Electrical Configuration and System Protection
Development of a Marx-Generator for the drive beam electron gun
ProtoDUNE SP – Slow control Status
Electrical & Control.
MICE Target Report Video Conference 29/11/07
Safety Measures in Super Power and High Power Transmitters in
Construction and Commissioning of Electronic Test Benches
Construction and Commissioning of Electronic Test Benches
352MHz Klystron Control for the 3MeV Linac test stand
Focus Coil Quench Detector
ELEMENTS: Need to install, integrate, commission and operate:
ELEMENTS: Need to install, integrate, commission and operate:
PS System for DRFS PS System for Diode-type klystrons
BEPCII RF POWER SOURCE AND INPUT COUPLER
RF Power for C75 - Resources
Klystron Power Supplies for ILC
RF Power for C75 - Resources
Report on ATF2 Third Project Meeting ATF2 Magnet Movers ATF2 Q-BPM Electronics Is SLAC ILC Instrumentation Group a good name?
The 9th Collaboration Meeting
Rack installation and local tests for the MEBT Chopper Rack
Presentation transcript:

MICE RF System Power Supplies, Control and Monitoring Status report December 2011 Chris White, STFC Daresbury Laboratory

MICE RF Design Review December 2011

MICE RF Design Review December 2011 TH116 140 uF 29 uF 20 kV PSU to ISIS design MICE RF Design Review December 2011

20 kV Power Supply for 4616 HV Power Supply 20 kV 4616 Circuit Enclosure Auxiliary Rack RF Signal Generator (201 MHz) Control Crate Resistor bank RF cable RF output (co-ax) 4616 Tube PLC Crate Capacitor Charger 20 kV+ Screen cable Heater Controller Grid cable Water cooling circuits (4) RF solid state amplifier Earth Switch Compressed air cooling Crowbar (Ignitron) Grid PSU (300 Vdc) HV cable Dump Relay Screen Pulser (2000 Vdc) 0.95V 500A Capacitor 29 uF Screen PSU (600 Vdc) Heater Transformer MICE RF Design Review December 2011

MICE RF Design Review December 2011 38 kV Power Supply for TH116 HV Power Supply 38 kV TH116 Circuit Enclosure Auxiliary Rack Control Crate HV cable TH116 Tube Resistor bank RF output (co-ax) PLC Crate RF input from 4616 (co-ax) Capacitor Charger 40 kV+ Heater Controller Water cooling circuit Trigger pulse Cathode Modulator 450V DC Bias PSU Earth Switch Compressed air cooling Crowbar (Thyratron) Dump Relay Cooling Fans 20V 500A Capacitor 140 uF Heater Transformer MICE RF Design Review December 2011

Daresbury Laboratory - Plant Room 1 - RF Test Area MICE RF Design Review December 2011

Cooling Water Systems (DL) DL site cooling system decommissioned Ex-SRS twin-circuit chiller installed Demin for amplifiers Glycol for load Now fully operational MICE RF Design Review December 2011

MICE RF Design Review December 2011 TH116 Circuit #1 Mechanically complete New fans fitted Cathode modulator built Motorised tuners Electrical control panel Heater controller Safety interlocks Tested to 1 MW RF output MICE RF Design Review December 2011

MICE RF Design Review December 2011 Cathode Modulator IGBT switch IGBT control board Potential divider Zener diode array 38 kV Trigger 450Vdc 15k 2R7 33R From 4616 IGBT TH116 TH116 CATHODE MODULATOR CIRCUIT Fully operational Second unit almost complete MICE RF Design Review December 2011

MICE RF Design Review December 2011 Circuit tuning motors MICE RF Design Review December 2011

TH116 Electrical Control Panel Fan control-gear Heater controller (thyristor) Circuit-breakers Tuning control relays MICE RF Design Review December 2011

MICE RF Design Review December 2011 TH116 38kV Power Supply 2 x 70 μF Capacitors Crowbar (thyratron) Control unit Power module Dump relay Earth switch Charger (40 kV) Resistors Crowbar testing Crowbar (Thyratron) HV Resistors HV Capacitors (140 uF) Power Supply Rack (Front) MICE RF Design Review December 2011

RF HV Power Supplies - Components HV PSU Control Unit TH116 Circuit (lower part) 20 kV PSU & Aux. rack – front view 38 kV PSU – rear view 38 kV PSU – 1 MW RF output 38 kV PSU – resistor bank Crowbar (38 kV Thyratron) MICE RF Design Review December 2011

RF Control & Monitoring System EPICS Server 4616 & TH116 Aux. Racks Network/ Controls Rack VME Crate Canbus modules DAC/ADC modules Typical I/L Digital signals/serial link PLC Crate (TH116) Interlocks Compressed air pressure Digital signals/serial link PLC Crate (4616) Interlocks Water flow Panel switches Analog signals Grid PSU (4616) Enable Analog signals Screen PSU (4616) Enable Heater Controller (4616) Enable Analog & digital signals Heater V and I Heater Controller (TH116) Enable Analog & digital signals Heater V and I Analog & digital signals Enable 450V DC Bias PSU Interlocks MICE RF Design Review December 2011

RF Power Supplies - MICE Hall Layout RF Amplifiers RF Power Supply Racks Air Conditioning Units RF Network/Control Racks Layout of North Mezzanine MICE RF Design Review December 2011

MICE RF Design Review December 2011 Timescale Current work in progress: RF testing of System #1 with new 4616 and TH116 tubes Nov 11 to Dec11 Future work (Step V): time-scales to be confirmed Assembly of CERN TH116 amplifier (System #2) ---------------------- (July 2012) Test CERN amplifier at Daresbury ----------------------------------------- (December 2012) Develop RF Control Systems Pack & ship complete system #1 to RAL --------------------------------- (January 2013) Install RF System #1 in MICE Hall ----------------------------------------- (May 2013) Test complete RF system #1 at RAL -------------------------------------- (September 2013) Construct & test 4616 #2 amplifier, power supply & controls Construct & test TH116 #2 power supply & controls Test complete RF system #2 at DL Pack & ship system #2 to RAL Install RF System #2 in MICE Hall Test complete RF system #2 at RAL Tasks in red are required for TIARA (deadline in brackets) MICE RF Design Review December 2011

Power Supplies – Construction Status - Step V RF System #1 built and under test (manually controlled) Work required: Control & monitoring upgrade for 4616 Screen Pulser (2 kV) Interface to MICE control system Interface to PLC (Siemens S7-200) Interface to Heater Controller (Eurotherm) Interface to Low Level RF and Timing System RF System #2: 4616 amplifer circuit refurbishment has started 20 kV Power Supply rack to be built (some components available, some ordered) 4616 Auxiliary rack to be built (components to be ordered) CERN amplifier at DL – to be assembled when required Cathode modulator virtually complete 38 kV Power Supply rack to be built (components to be ordered) TH116 Auxiliary rack to be built (components to be ordered) Second dummy load to be procured for use with CERN amplifier (twin output) 4616 Tube & Connections MICE RF Design Review December 2011

Power Supplies – Construction Status - Step VI RF Systems #3 and #4: TH116 amplifier circuit (ex-LBNL): Mechanical refurbishment complete, tuning motors fitted Electrical control panel to be built Second CERN amplifier at DL – to be assembled when required Cathode modulators to be built 4616 amplifer circuit (ex-LBNL) refurbishment has started Fourth 4616 amplifier circuit to be purchased 20 kV Power Supply racks to be built (some components available, some ordered) 4616 Auxiliary racks to be built (components to be ordered) CERN amplifier at DL – to be assembled when required 38 kV Power Supply racks to be built (components to be ordered) TH116 Auxiliary racks to be built (components to be ordered) 20 kV PSU and Aux. Rack MICE RF Design Review December 2011

MICE RF Design Review December 2011 RF Power Supplies Questions ? 20 kV PSU (front) 38 kV PSU – Charger (rear) 38 kV PSU Dump Relay & Voltage divider 38 kV PSU - rear view MICE RF Design Review December 2011