Value Engineering Study and Risk Assessment

Slides:



Advertisements
Similar presentations
Resource Team/TEER Meeting October 19, CBRT Meeting October 19, 2006 Agenda 10:00 AM 10:05 AM 10:30 AM 11:30 AM Noon Introductions and Housekeeping.
Advertisements

Metro Muncipal Agreement Program
ODOT Structure Project Management Seminar Bridge Preliminary Design Report.
Project Development Process (PDP) Structures. PDP – Three Project Levels Major Project ~ 14 Steps Major Project ~ 14 Steps Minor Project ~ 10 Steps Minor.
Value Engineering How DOT’s uses this valuable tool in project development What is it When is it used How do we use it.
Railway Grade Separations Issues. Railway Grade Separations 1.Introduction Qualifications/experience to undertake bridge planning for railway grade separations:
CMGC Contracting at UDOT Program, Projects & Lessons Learned
PROJECT RISK MANAGEMENT
Environmental Project Commitments The Alberta Experience
New I-65 Interchange at Worthsville Road Welcome!.
South Side Red River Bridge Corridor Study Phase III Preliminary Geotechnical Study Phase IV New Alignment Alternatives Evaluation.
2012 CSVA Conference VE Scan of Western Canada Projects – The Flexibility of VE for Decision Making.
Clinton Street Bridge over the Maumee River ODOT Project DEF April 1, 2015 Stakeholder’s Meeting.
1 Preconstruction Site investigation, Scheduling, Estimating, and design Preconstruction Site investigation, Scheduling, Estimating, and design Prepared.
Managing Risk to Reduce Construction Claims (And Improve Project Success) Presented by Laurie Dennis, PE, CVS-Life, FSAVE.
© 2011 HDR All rights Reserved. Value Engineering Ken L. Smith, PE, CVS (360) April 27 th, 2011.
FM Guidance for Design Teams MEFMA Focus Group. Team Members Neil Blakey FM Consultant, Mace Macro Stuart Clayton Project Manager, Serco Middle East Ryan.
Business Acquisition Process Implementation & transition Closing Negotiation of the transaction Due Diligence Engagement TargetIdentification.
Clinton Street Bridge over the Maumee River ODOT Project DEF May 14, 2015 Public Meeting.
EAST DON TRAIL ENVIRONMENTAL ASSESSMENT Project Overview Ward 31 Ravine Meeting November 4, :00 to 9:00 p.m. Presteign-Woodbine United Church.
Environmental Assessment Public Information Meeting – September 2010 Realignment of a Portion of a Utah Lake Drainage Basin Water Delivery System (ULS)
Page 1 MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway) Detail Design Study Group Work Project
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation.
Steven C. Braun, P.E. Senior Project Manager. A Master Plan identified a Locally Preferred Alternative (LPA) for the corridor … This LPA was adopted by.
Alameda Creek Bridge Replacement Scoping Meeting March 4, 2014.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.
PROJECT SCOPING FOR LOCAL AGENCY FEDERAL AID PROJECTS.
GREENWAYS Connecting Communities November Greenways Plan 350 km planned Over 80 km built Construction of 4-5 km / year.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
4733 Bethesda Ave, Suite 600 Bethesda, MD (P) Developing Criteria for Project Programming.
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Public Information Meeting.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Fern Valley Interchange Project Development Team Meeting February 3, :00 – 11:00 p.m.
AT FPS Bridge Planning Expectations 1 Bridge Planning Seminar 2008.
August 19, 2015 Port Bienville Rail EIS Scoping Meeting Presented by: Rhea Vincent Mike McGuire.
Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.
Planning Commission Study Session: Preferred Plan July 23, 2015.
1% Sales Tax Commission Board Meeting June 3, 2015.
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
EIAScreening6(Gajaseni, 2007)1 II. Scoping. EIAScreening6(Gajaseni, 2007)2 Scoping Definition: is a process of interaction between the interested public,
Transportation Master Plan Update Warden’s Forum May 7, 2015.
I-4 Express Lanes Project Development and Environment (PD&E) Study From east of 50 th Street to the Polk Parkway (SR 570) WPI Segment No: Polk.
Proven Management – Proven Gold Districts – Safe Jurisdictions Symbol:PG Exchange:TSX Hardrock Project Environmental.
County Road 19(Manning Road) & County Road 22 Improvements Environmental Study/ Preliminary Design Report November 2008.
Alternative Alignments Public Meeting
The I-465 West Leg Reconstruction Project
Public Information Centre No. 2
NGTA Halton Planning and Public Works Committee
Case Road Sewer Joe Mouawad, P.E. October 27, 2016.
FOR LOCAL AGENCY FEDERAL AID PROJECTS
Technical and Public Advisory Committee Meeting #3
Draft Transportation Element September 6, 2017
Module 2 Key Phases of the Peer Review Programme
Guidance notes for Project Manager
Critical Transportation Issues
Issaquah-Fall City Road
FOR LOCAL AGENCY FEDERAL AID PROJECTS
Progress Report on proposed GUID on Information System Security Audit
Long Range Facilities Plan
Controlling Project Cost and Schedule
Environmental Commitments
Brackish Water Desalination Project
Walker Street Reconstruction Project 25% Design Public Hearing
Manilla Low Level Crossing Project
Monterey County Project Report for Measure X Expenditures
3 November 2017 Fraserburgh and Peterhead to Aberdeen Strategic Transport Study: STAG Part 1 Plus Bob Nicol: Project Director David Murtagh: Project Manager.
HIGHWAY DESIGN PROCESS & ROUTE LOCATION
Space Coast TPO State Road (S.R.) 528 Update
Presentation transcript:

Value Engineering Study and Risk Assessment Highway 7 New - Kitchener to Guelph

Presentation Outline Project Background Value Engineering and Cost Risk Analysis Study Outcomes

Key Plan

Highway 7 – Background Highway 7 is a congested 2-lane highway (AADT 21,000 - 32,000) Planning study commenced in 1989 Individual EA submitted in 1997 EA resubmitted in 2002 Individual EA approval obtained in March 2007 for an 18 km long, 4-lane freeway, following a new alignment generally north of and parallel to existing Highway 7

Value Engineering Study Largest single VE study ever undertaken by MTO VE Team jointly lead by Marshall Macklin Monaghan (MMM Group) and iTrans Additional members from: Faithful+Gould, MACTEC, Davis-Langdon, WCS, Thurber, Human Factors North, HCi, and MTO Site visit and information meeting was held April 2007 Safety Audit of base case undertaken pre-study. Value Engineering Study completed in Kitchener April 30 to May 4, 2007. VE Team presentation to MTO Senior Management held May 15, 2007. Focused 5 days on workshop. Split pre/post activities as concerned over maximizing time for workshop.

VE Scope The EA approved alignment was assessed The Study Team generated 212 ideas (of which 56 were developed) in eight Target Areas and evaluated using seven Performance Measures

Value Target Areas Team identified 8 Target Areas Kitchener-Waterloo Freeway to Freeway Interchange Grand River Bridge and Bridge Street Regional Road 17 Interchange Regional Road 30 Interchange County Road 86 Interchange Highway 6 Interchange Sideroads Mainline

Performance Measures Team Developed 7 Performance Measures Weight Safety (collisions) 22 Human Factors (predictability, signs, geometry) 17 Traffic Operations (v/c, weaving, queuing) 19 Access (interchange access, local road across) 13 Sustainability (environmental, growth) 12 Constructability (staging complexity, resources, access) 8 Maintainability (structures, roadway cross-section) 8

VE Ideas

VE Scenarios Of the 56 ideas evaluated in detail, 29 were developed into VE alternatives. The VE Team grouped these alternatives into 5 Scenarios based on function or impact. Scenario 1 - Minimal Improvements Scenario 2 - Minimal Improvements with various interchanges deferred Scenario 3 - Moderate Improvements with Roundabouts Scenario 4 - Moderate Improvements Scenario 5 - Reduced Expenditure / Constrained Funding

VE Conclusions Scenarios 1-5 had performance benefits over the base case. 29 VE Proposals were used to develop numerous other scenarios. 30 VE Design Suggestions were generated for consideration during preliminary and detail design.

Implementation Plan VE team developed 29 individual alternatives and packaged them into an Implementation Plan to Senior Management. Implementation of some alternatives are considered a substantive change to the approved EA. It will be necessary to prepare an addendum to the TESR to document the changes and obtain environmental approval from MOE. The alternatives from the VE Study that were recommended for implementation are currently being evaluated for performance and cost benefits.

Risk Assessment “No construction project is risk free. Risk can be managed, minimized, shared, transferred, or simply accepted, but it can not be ignored.” C.R.I. Clayton, 2001. “Managing Risk”

Cost Risk Analysis Objectives: Review MTO concept base construction estimate Incorporate latest property estimate Review schedule Identify constraints to schedule Quantify risks as to likelihood of occurrence and impact in terms of $ and extended project duration Discuss possible mitigation reduce, avoid and / or transfer risks

Process Risk identification (completed concurrently with the VE Study) Pre workshop ‘Top Risk’ questionnaire issued to VE team Risk analyst compiled draft risk register Risk analyst built schedule and cost model ‘base case’ working with VE / MTO team Risk analyst identified constraints to schedule with VE team Draft risk register circulated to VE team for confirmation / comments on risks identified – risk register updated Production of risk analysis, summary and report

Cost Risk Analysis Grand River Bridge Issues Material price volatility Greatest Risks to Projects Cost and Schedule Grand River Bridge Issues Material price volatility Market forces/number of bidders Escalation Environmental Mitigation Relocation of Utilities Variability in earthwork quantities Complex KWE structures

Project Schedule Constraints Key Project Constraints identified as: In-water timing restrictions Bird nesting season – impacts tree clearance in wetlands Winter work – impacts paving and influences structure and earthworks construction Wetlands clearance – requires special protective measures and consultation River crossings – requires detailed consultation with First Nations Funding Availability – impacts phasing of project Minimizing traffic impact during construction Reducing Rail impact – CN under-bridge construction

Top Risks from Risk Register

Top Risks from Risk Register

Study Outcomes - Where are we now? Implementation Plan endorsed by MTO Sr. Mgmt. 2 engineering assignments currently underway. MMM Group developing VE recommendations within a Preliminary Design/Detail Design assignment. Thurber Engineering undertaking a Foundation and Pavement Field investigation. Property Request to be available in early 2009.

Study Benefits New perspective on study New PM had no ownership Risk analysis (cost/schedule)