BE-CO Activities for LIU-CPS and LIU-SPS Summary & conclusions Marine Pace – BE-CO Last week update with E.Carlier (ABT), L.Jensen (BI), M-Elena.Angoletta + H.Damerau +C.Rossi (RF), J-M.Cravero + J-L.Gomez Costa (EPC) + A.Masi (STI) LIU Meeting - 9 August 2016 Marine Pace, BE-CO
LIU-CPS LIU Meeting - 9 August 2016 Marine Pace, BE-CO
BI System Deadline Controls HW Controls OASIS New Fast Wire Scanner prototype EYETS 2016-2017 1 CO FEC - request to be sent No request received. Action on OP if needed. Replacement of obsolete SEMs FEC not needed New ionization BLMs 1 BI FEC New diamonds BLMs (17) New installation registered for B359. Lack of signal specification. Outstanding: # of signals (17 or 34?). Space issue in the rack. Action on Rende. Removal of BCT in SS26+44 Installation of BGI & BPM 1 CO FE (request done) New Wideband Electrostatic PU New installation registered for B354. New Fast BWS prototype in SS54 YETS 2017-2018 1 CO FEC Too early Summary for EYETS2016-17: 2 CO FEC requests + 2 OASIS installations registered; one waiting for signals characteristics specification. Additional OASIS installations to be requested, if any. LIU Meeting - 9 August 2016 Marine Pace, BE-CO
EPC Summary for EYETS2016-17: System Deadline Controls HW Controls OASIS Injection Septum converter (SMH42) LS2 1 or 2 FGC-Ethernet GW in B365 & B269 with Timing Receiver Card (CTRI) TBC with Serge Pittet & request to be sent No HW installation. DataSource SW integration to see converters’ signals in OASIS VIEWER Application (general policy by EPC management) Injection Bumper Septum converter (BSM42) Injection Bumpers converters (BSW40,41,43,44) QSK and DVT correctors converters EYETS 2016-17 use existing GW in B355 As above. DHZ correctors converters 1 FGC-Ethernet GW in B368 with CTRI - Request to be sent PS 40 and 80 MHz RF Cavities converters Injection low beta quadrupoles converters 1 FGC-Ethernet GW with CTRI in Building (?) Vertical IPM converter ? TBC with Gilles Le Godec. TT2 30 converters Jan-19 1 FGC-Ether GW in B269 with CTRI . New installation registered for 42 signals. TBC ASAP with Konstantinos: dedicated OASIS HW installation or SW integration ? Summary for EYETS2016-17: 1 FGC-Ethernet GW with Timing reception module. OASIS request for TT2 converters to be checked. LIU Meeting - 9 August 2016 Marine Pace, BE-CO
RF System Deadline Controls HW Controls OASIS Transverse Damper Installation deployed- No new request for LIU. Confirmed ? 1 turn delay feedback 20-40-80 MHz Longitudinal damper Beam Controls upgrade LS2 20-30 new FECs + standard HW (CTR, CVORB). Timing already in building. No new signals New 80 MHz fast tuner prototype in SS08 (for PPM usage of C80 between Ions and P+) PROTOTYPE at soonest mid 2017. Final system in LS2 1 FEC + Timing repeater in B151 - Confirmation by C.Rossi early 2017 ?? Summary for EYETS2016-17: Timing repeater + 1 FEC – to be specified early 2017 by RF ABT System Deadline Controls HW Controls OASIS New injection kicker(KFA45) LS2 1 CO FEC with standard HW modules (CTRV, VMODxx, FineDelay) No new signals. Existing ones connected to new HW. New Injection Septum (SMH42) New displacement system in YETS 2017 1 new FEC (TBC) Front-end SW + HW controls by ABT No signals Summary for EYETS2016-17: 1 FEC. STI Internal dumps replacement and new location (LS2): No CO requests except logging. TBC? LIU Meeting - 9 August 2016 Marine Pace, BE-CO
LIU-SPS LIU Meeting - 9 August 2016 Marine Pace, BE-CO
BI STI Summary for EYETS2016-17: System Deadline Controls HW Controls OASIS New Diamonds BLMs in LSS1 EYETS 2016-2017 1 CO FEC – Request to be sent No request received. Action on OP if needed. New fast BCTs in LSS5 FEC not needed as above Layout changes for BI detectors EYETS 2016-217 BYBPM racks under SPS dipole magnets as part of MOPOS upgrade 2 New BLMs 5 New Fast Wire Scanners New BGI Move BSRT New ionisation BLMs New fast BCTs in LSS3 LS2 Too early Summary for EYETS2016-17: 1 CO FEC request. Additional OASIS installations to be requested, if any. STI Summary for EYETS2016-17 (CONSOLIDATION budget ?): Removal of scraper (BSHV.51659) from LSS5 & change of TIDVG: No CO requests. TBC? LIU Meeting - 9 August 2016 Marine Pace, BE-CO
EPC System Deadline Controls HW Controls OASIS SR2 with 2 new COMET converters ??? TBC with Serge 1 FGC-Ethernet GW with Timing Receiver Card (CTRI) TBC No HW installation. SW integration only. Relocate converters from BA5 to BA1 As above Summary for EYETS2016-17: to be checked with Serge as soon as back ABT System Deadline Controls HW Controls OASIS Beam Dump move from LSS1 to LSS5 = new controls LS2 1 CO FEC with Timing Receiver card New HW installation. Upgrade of protection systems TPSG4/6 No FEC needed No signals Summary for EYETS2016-17: no CO requests; Milestone is LS2 only: TBC ? RF System Deadline Controls HW Controls OASIS New CRAB cavity EYETS 2017-2018 No request so far. TBC with Philippe B. No request so far. Summary for EYETS2016-17: no CO requests. to be checked with Philippe as soon as possible LIU Meeting - 9 August 2016 Marine Pace, BE-CO
Summary Estimate of CO activities for LIU Answers to Malika’s meeting questions Proposals for next actions LIU Meeting - 9 August 2016 Marine Pace, BE-CO
Estimate of CO activities for LIU BE-CO is confident so far to be within the expected timeline for LIU installation, commissioning & operation Requirements for coming EYETS/YETS/LS2 look moderate in terms of personal and material resources NO special requests for custom specific HW nor SW development But This assumption is based on a rough + inaccurate estimate of CO requirements from partners groups. Registered requirements today are far from being finalized. No requirements from some groups (VAC, …) No accurate specifications sent to us (OASIS signals specif, HW installation form..). No SW requests registered so far (LOGGING, SIS, LSA, Generic APs). Too early anyway. Also difficult to get all work-packages from a central repository. EDMS website: missing specif. for several systems. CO requirements usually not mentioned at all. PLAN.CERN.CH: most of BE-CO contributions expected from partners groups are missing. Only ABT + RF available. LIU PLANNING & INSTALLATION (https://espace.cern.ch/LIUPLI): useful but not complete / up to date. Ex. One PSB ABT missing system. LIU Meeting - 9 August 2016 Marine Pace, BE-CO
Extract of BE-CO contributions from PLAN.CERN.CH last Friday NO activity from EPC, BI, STI with CO contributions : WHY ? BE-RF but only for PS LIU Meeting - 9 August 2016 Marine Pace, BE-CO
Proposals for next steps Actions on partner groups Formal requests have to be sent ASAP to allow us to define precisely our work plan and to adjust priorities if needed With focus on HW / CABLING /OASIS /TIMING needs With priority on EYETS 2016-2017 Practically: Fill PLAN.CERN.CH with contributions expected from BE-CO Send HW installation/modification requests using the standard template, even if details are not finalized yet. Contact: HW installation team. Send OASIS Signals requests using the standard template (from OASIS WIKI space). Contact: Anastasiya. Keep your MCC updated. S/He is your main contact in CO for LIU. Actions on CO MCCs Fill and update PLAN with BE-CO activities Update EVM (fill it for LIU-Ions) [Likely useful] Create a EDMS with summary of all CO requirements Actions on LIU chairpersons Keep LIU Planning up to date One review meeting in Q4-2016 (before EYETS) with partner groups to validate the finalized list of requirements. LIU Meeting - 9 August 2016 Marine Pace, BE-CO
HW Installation Request Template LIU Meeting - 9 August 2016 Marine Pace, BE-CO