HFT project Overview and Status March 10, 2010

Slides:



Advertisements
Similar presentations
HFT Technical Overview September 26, HFT 2013 TPC FGT 2011 STAR Detectors Fast and Full azimuthal particle identification EMC+EEMC+FMS (-1 ≤ 
Advertisements

TITLE OF PROJECT PROPOSAL NUMBER Principal Investigator PI’s Organization ESTCP Selection Meeting DATE.
HFT PXL Mechanical WBS 1.2 March 2010 Howard Wieman LBNL 1.
HFT Safety --PXL detector September 26, Dana Beavis.
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
PXL Electronics Status update for HFT TC meeting on May 11, 2010 at LBNL 1HFT TC 05/11/ LG.
SSD Ritter Review June 20, 2012 The Silicon Strip Detector an overview and introduction Jim Thomas Lawrence Berkeley National Laboratory.
SSD Operations Manual March 2014 SSD: 4 th layer of vertex detector Heavy Flavor Tracker Silicon Strip Detector – Operations Manual PXL Inserted from this.
Project Overview Flemming Videbaek Brookhaven National Laboratory.
The STAR HFT PXL system is designed to be inserted in situ. Is housed in 2 large frame aligned with rails inside Inner Detector Support. Inserted from.
Engineering Division 1 Mechanical and Integration CD0 Walkthru, 19-Dec, 2007 Eric Anderssen, LBNL.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
+ STAR HFT Upgrade – Installation and Integration Rahul Sharma Brookhaven National Laboratory.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
HFT project Overview and Status October 14, 2010 F.Videbaek BNL.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Ahmad Al-Ghoul. Learning Objectives Explain what a project is,, list various attributes of projects. Describe project management, discuss Who uses Project.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
HFT face-2-face F.Videbaek Brookhaven National Lab.
HFT project Overview and Status May 11, 2010 F.Videbaek BNL 5/11/20101.
STEP 4 Manage Delivery. Role of Project Manager At this stage, you as a project manager should clearly understand why you are doing this project. Also.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
HFT DOE Review July 17-18, 2012 The Silicon Strip Detector WBS 1.4 Jim Thomas Lawrence Berkeley National Laboratory SSD.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
IAEA International Atomic Energy Agency Methodology and Responsibilities for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
IEEE /r5 Submission November 2008 John Notor, Cadence Design Systems, Inc.Slide 1 IEEE IMT-Advanced Review Process Date:
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii.
Principal Investigator ESTCP Selection Meeting
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Camera PDR/CD1 Planning 19 September 2008
Project Management MGT 30725
Schedule Margin July 2013 NAVY CEVM
Status of the MICE Construction Project
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
Project Management W. J. Foyt
ENGR 281 Engineering Scholars Program Project Management Life Cycle Overview K. F. Reinschmidt J. L. Frank / Marathon Ashland Petroleum LLC Chair in.
Systems Analysis and Design in a Changing World, 4th Edition
Accounting: Graded Unit 2 F8KF 35
WBS 1.03 Readout Systems Scope, Cost and Schedule
Risk Identification HL-LHC Detector Upgrades Project
Principal Investigator ESTCP Selection Meeting
Face to Face Meeting – March 2012 Sarah Morgan
ISA 201 Intermediate Information Systems Acquisition
ITPD ISSUE MANAGEMENT PROCESS SEPTEMBER 5, 2008
Preparations for a Lehman Review
End of Year Performance Review Meetings and objective setting for 2018/19 This briefing pack is designed to be used by line managers to brief their teams.
External Independent Review (EIR)
Project Management Process Groups
[Team Name] Monthly Technical Report [Safe Genes Program]
Schedule Margin July 2013 NAVY CEVM
Mark McKinnon EVLA Project Manager
IEEE IMT-Advanced Review Process
Schedule Margin July 2013 NAVY CEVM
IEEE IMT-Advanced Review Process
Principal Investigator ESTCP Selection Meeting
IEEE IMT-Advanced Review Process
CAD DESK PRIMAVERA PRESENTATION.
Preliminary Project Execution Plan
Conventional Facilities
Second Avenue Subway Project Execution Strategy
Principal Investigator ESTCP Selection Meeting
Presentation transcript:

HFT project Overview and Status March 10, 2010 F.Videbaek BNL

Welcome introduction Organization Today: talks by sub-system Tomorrow: Brief overview Progress since pre CD-1 review Plans towards finalizing design Development plans Tomorrow: Management meeting Grounding plans Preparation for TDR, WBS , CD-2/3 review Closeout- delegation of tasks

Content Brief (very) overview Review of homework Completed Yet to come Preparations for CD-2/3

HFT Detector within STAR IFC TPC Volume Magnet Return Iron Solenoid OFC Outer Field Cage IFC Inner Field Cage SSD IST PXL EAST WEST FGT HFT

Naming Conventions IDS MSC Inner Detector Support Pixel Insertion Tube Pixel Support Tube IDS East Support Cylinder Outer Support Cylinder West Support Cylinder PIT PST ESC OSC WSC Shrouds Middle Support Cylinder Inner Detector Support Assembly via bolted interfaces MSC installed into IDS after IDS assembled (detectors not shown) IDS w/MSC installed into STAR

Basic requirements

Review of CD-1 homework Develop a plan for a ladder system test as soon as possible, using the available MIMOSA-26 chip, which has the architecture fully validated for the needs of STAR. Report draft system test plan to DOE by December 31, 2009. Prepared by Leo++ and submitted on Dec 31.

Labor contributions Provide, by institution, an annual breakdown of the project cost into capital, labor costed to the project, requested redirected labor cost, and all contributed labor. Submit to DOE by December 31, 2009. This is quite a new twist on DOE management, normally contributed labor is non accounted for. We did gather the information and submitted a report.

We were requested to detail this further with names etc We were requested to detail this further with names etc. Ready for submission.

reports Evaluate the cost, schedule and workforce trade-offs between adding a second layer to the IST and a single-layer IST plus retaining the SSD. Report results to DOE by March 1, 2010. Prepared by Gerrit Submitted March 2 by Vigdor quoting The bottom line is that choosing a second IST layer would add very substantial cost and time delay to the HFT project, while not improving the anticipated performance from even an SSD that suffers loss of some fraction of its sensors or readout electronics.

IST additional- comment The APV chip used in the IST readout has a known issue with heavily ionizing particles which causes occasional dead time. There are mitigation strategies, but the collaboration should verify that this will not be an issue in the STAR environment. A report on this was prepared by Gerrit, also in December,

Updated PEP and CD-4 parameters Major Updates; cd-4 parameters & workforce/ In tc we agreed to relax parameters for pixel.We still strive for the thinner layers, There are clear implications if this cannot be achieved in terms of running time.

On-Project labor is defined as the effort associated with preliminary/final design, construction, and assembly. The scope is included in the work breakdown structure; the cost is included in the HFT TPC and is funded by the DOE.   Redirected labor is also associated with all design, construction, and assembly. The scope is included in the work breakdown structure; the cost is included in the HFT TPC and is planned as a redirection of base DOE funding at LBNL, BNL and MIT. Contributed labor is scientific and IT labor supporting the overall development and operational capability of the HFT detector within the STAR experiment including software and physics analysis models.  Contributed labor cost is not included in the HFT TPC but tasks and milestone dates related to this scope are embedded in the HFT Project schedule. Part of the funding comes from the DOE Base for Heavy Ion Physics Research Program. 

Control via MOU’s MOUs between BNL/HFT and the collaborating institutions will describe the expected efforts of both redirected and contributed labor; summarizing people (names/category) and their anticipated fraction (%) of activity related to specific tasks in the WBS. Draft MOUs which summarize the full scope and detail the first year’s expected effort and milestones will be prepared for CD-2 and signed thereafter. The MOUs will then be updated annually to assert the task efforts for each institution for the next 12 month period.  

Reporting/control Redirected labor will be tracked by each institution on a monthly basis and will be appropriately included in the Total Project Cost (TPC).   Contributed labor will be tracked from reports by institutions which will reflect the overall fractional time spent by individuals on the HFT project. This information will be reported at the DOE NP annual review. Progress on all tasks will be monitored by sub-system managers by having sufficiently frequent milestones at level 4, such that task completions are noted, and changes to the schedule float (+/-) can be evaluated as soon as possible. Non-DOE contributed labor will be tracked by monitoring milestones set forth in the MOUs.

Contingency Scope funded as redirected labor will be assigned risk and contingency in the WBS. Contributed efforts will be assigned risk. Overruns in this category may result in overall schedule slip due to the special expertise of contributed scientific labor. Contingency funds will be set aside for use of short-term hires or support of scientist and students, and/or other measures that can be made available to alleviate a shortfall in effort on specific WBS tasks. In case an institutional commitment cannot be met, the HFT and STAR management will jointly seek solutions to identify and commit resources.

Pre-CD2 scheduling Studies should be carried through to the final physics measurement, showing the degradation of the final physics significance if key requirements are not met: Give an explicit evaluation of what the loss in low-pT efficiency does regarding the fundamental physics questions relating to flow and energy loss of heavy quarks in the hot-dense medium. Evaluate this loss in terms of current theoretical models and show whether these are well tested by the measurement above ~2 GeV/c or if the loss of statistics at lower pT is a critical loss. Compare the significance of planned charm and beauty measurement to be done with the HFT to similar measurements expected from the upgraded PHENIX detector. Comment on how significant an advance in theoretical understanding of energy loss and flow for the hot-dense medium the HFT would provide compared to the earlier anticipated PHENIX measurements Important subject for the Software talk by Spiros. Establish timeline for having a preliminary report we can discuss with Steve Vigdor The key requirements very much related to modificed c-4. Should make clear how this effect the STAR measurements and requirements for running time later.

Other pre CD-2 actions Prior to CD-2, develop a grounding and shielding plan. Prior to seeking CD-2 approval, include additional milestones (at least quarterly) on the project critical path so that performance can be effectively monitored and managed. Prior to CD-2, develop a consistent, defensible methodology to calculate project contingency that takes in account documented project risks. Evaluate the potential risk of design changes resulting from the engineering run and apply the appropriate cost contingency. Evaluate areas of the project that could be identified as scope contingency.

Actions by approval CD-2 Establish performance baseline Continue Design Request construction funding CD-2 Approve expenditure for construction

Documents pre-CD 2&3 review Performance Baseline Preliminary Design Updated Risk Assessment Update PEP Updated Hazard Analysis Updated SVAR NEPA documentation CD-3 Final design Updated CD-2 documents Updated QA program An approved Construction Project safety and health plan

Pre next Review Significant work to be done for CD2/3 as you can see from previous slide. Particular complete design and resource loaded cost and schedule. We need before going to DOE to have internal design and cost review so this is in good shape. The original timeline of June cannot hold.

Schedule Need to setup realistic schedule for all these tasks. Included answering remaining homework. Revisit at tomorrows discussion.

Tomorrow A word on tomorrow. Management discussion Meant to be in-depth discussion, material as needed Management discussion Organization, resources Integration, specifications (Eric) Grounding plans (Leo, Gerrit, Micheal) Documentation (an open issue) Future meeting, preparing for CD-2